_7 _Sample_Project_Bid_Schedule.docx
DOCX document 26 KB Posted
- Attached to
- Dyess AFB MACC Federal contract opportunity
- Solicitation number
- FA4661-15-R-0002
About this file
Attachment 7 - Sample Project Bid Schedule
View the file
Other files for this federal contract opportunity
Show all 37
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid Schedule of Items: Design Repair for HVAC System, Buildings 7232 & 7233 16 June 2015
0001 Base Bid - Item 1 –Building 7232 This Item includes all survey, layout, plant, labor, supplies, equipment, materials supervision and incidentals required to complete all work in compliance with the specifications, drawings, and terms and conditions of the Contract for FNWZ 99-0013, Design Repair for HVAC System, except those items of work specifically included in Bid Item 2 & 3.
1 LS: $___________________________
0002 Base Bid - Item 2 –Building 7233 This Item includes all survey, layout, plant, labor, supplies, equipment, materials supervision and incidentals required to complete all work in compliance with the specifications, drawings, and terms and conditions of the Contract for FNWZ 99-0013, Design Repair for HVAC System, except those items of work specifically included in Bid Item 1 & 3.
1 LS: $___________________________
0003 Base Bid - Item 3 –Building 7223 (Central Plant) This Item includes all survey, layout, plant, labor, supplies, equipment, materials supervision and incidentals required to complete all work in compliance with the specifications, drawings, and terms and conditions of the Contract for FNWZ 99-0013, Design Repair for HVAC System, except those items of work specifically included in Bid Item 1 & 2.
1 LS: $___________________________
Total Construction Cost, Including all Items above: $___________________________
CONTRACT PERFORMANCE TIME:
1. Total of 385 calendar days to complete the work.
2. Performance time includes 20 working days of anticipated weather. No additional time weather related delays will be granted until these 20 anticipated weather days have been exceeded and approved by the Contracting Officer.
3. Performance time includes mobilization, submittal approval, delivery of materials, actual construction work, perform system testing, training base personnel, and provide as-built drawings, close out documents, and submitted DD Form 1354 at final inspection.
4. Liquidated damages will be assessed IAW FAR 52.211-12 in the amount of $427.81 for the first day and $301.90 for each subsequent day until all work is completed.
File details come from the government source that posted it. Updated .