Attachment 2 - Sample Project Specifications

View the file

Other files for this federal contract opportunity

Other files attached to Dyess AFB MACC, newest first.
File Type Posted
Amendment_3.pdf PDF
Attachment__8 _Fan_Coil_Unit_Spec_for_Sample.pdf PDF
FA4661-15-R-0002-0002.pdf PDF
1-Prototypical_3_Story_Dorm_(Bldgs_7232_ _7233)_-_Initial_Construction_-_1954.pdf PDF
3-Bldg_7233_-_Available_As-Built_Drawings_after_Initial_Construction.pdf PDF
4-Bldg_7223_-_Available_As-Built_Drawings.pdf PDF
2-Bldg_7232_-_Available_As-Built_Drawings_after_Initial_Construction.pdf PDF
Response_to_Questions_29_June_15.pdf PDF
_7 _Sample_Project_Bid_Schedule.docx DOCX document
Slides.pdf PDF
Q A_Post_18_June_15.pdf PDF
FA466116R0002_Amendment_1.pdf PDF
SignIn_Sheet.pdf PDF
Site_Visit_Minutes.pdf PDF
_4 _Past_Performance_Questionaire.pdf PDF
_3 _Sample_Project_Drawings.pdf PDF
Dyess_AFB_MACC_FY15_Solicitation.pdf PDF
_5 _Site_Visit_Registration.doc DOC document
_6 _Question_Submission.doc DOC document
_2 _Sample_Project_Specifications.pdf PDF
_1 _General_MACC_Specifications.pdf PDF
_6 _Question_Submission.doc DOC document
_4 _Past_Performance_Questionaire.pdf PDF
_1 _General_MACC_Specifications.pdf PDF
_3 _Sample_Project_Drawings.pdf PDF
_5 _Site_Visit_Registration.doc DOC document
Dyess_AFB_MACC_FY15_Solicitation.pdf PDF
Clarification_on_Draft_Documents_6_May_15.pdf PDF
MACC_FY15_Draft_RFP.doc DOC document
_7 _Site_Visit_Registration.doc DOC document
_2 _Seed_Project_1.pdf PDF
_5 _Seed_Project_4.pdf PDF
_8 _Question_Submission.doc DOC document
_1 _General_MACC_Specifications.pdf PDF
_4 _Seed_Project_3.pdf PDF
_6 _Past_Performance_Questionaire.docx DOCX document
_3 _Seed_Project_2.pdf PDF
Show all 37

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Synopsis:

EXISTING CONDITIONS AND SCOPE OF PROJECT:

Work in this project will involve buildings 7223, 7232 and 7233. Buildings 7232 and 7233 are each approximately 30,000 sq. ft., three-story in height and located in the central area of the base. Formerly serving as barracks, both buildings are currently utilized primarily as administrative offices for the Mission Support Squadron. Building 7232 houses the education office and has a series of classrooms for satellite college courses.

Building 7223 is called the central plant and is approximately 1,000 sq. ft. and single story. It houses the chilled and heating water systems that serve buildings 7232 and 7233.

The existing HVAC (Heating, Ventilation and Air Conditioning) system for each of buildings 7232 and 7233 consists of a two-pipe system with each room served by one or more vertical stack type fan coil units fed by vertical pipe risers. The HVAC systems were constructed during total renovations in 1992 for building 7232 and 1989 for building 7233. The existing chilled water system is served by the central plant building (7223). The existing heating water system is served by a gas-fired hot water boiler located inside the central plant building. Chilled/heating water is pumped from the central plant building in piping below ground to buildings 7232 and 7233. The existing two-pipe system is unable to provide simultaneous heating and cooling on demand. The heating water system operates during the colder months and the chilled water system operates during the warmer months. With this system, it is not possible to maintain comfortable room temperatures during the seasonal transition seasons of spring and fall when outside temperatures can vary between extremes.

The scope of this construction project is to accomplish the following:

A. Replacement/addition/modification of the existing two-pipe HVAC system for buildings 7232 and 7233 with a new four-pipe system. This will include providing new fan coil units in both buildings, new piping throughout, underground chilled water lines, and chilled water pump in the central plant building.

B. Coordinate contractor-provided DDC controls for implementation with new

HVAC system.

C. Contractor shall review the government provided asbestos survey of all areas affected by the proposed work. Provide abatement where removal of asbestos containing materials is required to facilitate new construction. Refer to plans and specifications.

D. Incorporation of detailed phasing to maintain operation of the facilities during the work of this project.

E. Refer to Plans & Specifications for work to be performed.

Jacobs FDZD1402 TOC - 1 03/23/2015 Final Submittal

TABLE OF CONTENTS

Division Section Title

PROCUREMENT AND CONTRACTING DOCUMENTS GROUP

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

000102 SPECIAL CONDITIONS

000103 UTILITIES

000104 ENVIRONMENTAL

SPECIFICATIONS GROUP

General Requirements Subgroup

DIVISION 01 - GENERAL REQUIREMENTS

017800 AS-BUILT DRAWINGS

017823 OPERATION AND MAINTENANCE DATA

Facility Construction Subgroup

DIVISION 02 - EXISTING CONDITIONS

024119 SELECTIVE DEMOLITION

DIVISION 03 - CONCRETE

033053 MISCELLANEOUS CAST-IN-PLACE CONCRETE

DIVISION 05 - METALS

054000 COLD-FORMED METAL FRAMING

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

061000 ROUGH CARPENTRY

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

072500 WEATHER BARRIERS

073113 ASPHALT SHINGLES

074646 FIBER-CEMENT SIDING

076200 SHEET METAL FLASHING AND TRIM

078413 PENETRATION FIRESTOPPING

079200 JOINT SEALANTS

DIVISION 08 - OPENINGS

087100 DOOR HARDWARE

DIVISION 09 - FINISHES

092216 NON-STRUCTURAL METAL FRAMING

092900 GYPSUM BOARD

095113 ACOUSTICAL PANEL CEILINGS

Jacobs FDZD1402 TOC - 2 03/23/2015 Final Submittal

Division Section Title

096513 RESILIENT BASE AND ACCESSORIES

099113 EXTERIOR PAINTING

099123 INTERIOR PAINTING

Facility Services Subgroup

DIVISION 22 - PLUMBING

221116 DOMESTIC WATER PIPING

221316 SANITARY WASTE AND VENT PIPING

DIVISION 23 - HEATING VENTILATING AND AIR CONDITIONING

230054 PLUMBING AND HVAC DEMOLITION

230516 EXPANSION FITTINGS AND LOOPS FOR HVAC PIPING

230517 SLEEVES AND SLEEVE SEALS FOR HVAC PIPING

230518 ESCUTCHEONS FOR HVAC PIPING

230519 METERS AND GAGES FOR HVAC PIPING

230523.12 BALL VALVES FOR HVAC PIPING

230523.13 BUTTERFLY VALVES FOR HVAC PIPING

230523.14 CHECK VALVES FOR HVAC PIPING

230529 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT

230548 VIBRATION AND FORCE PROTETION CONTROLS FOR HVAC

230553 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT

230593 TESTING, ADJUSTING, AND BALANCING FOR HVAC

230713 DUCT INSULATION

230716 HVAC EQUIPMENT INSULATION

230719 HVAC PIPING INSULATION

230923 DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC

230923.11 CONTROL VALVES

230923.12 CONTROL DAMPERS

232113 HYDRONIC PIPING

232113.13 UNDERGROUND HYDRONIC PIPING

232123 HYDRONIC PUMPS

232300 REFRIGERANT PIPING

233113 METAL DUCTS

233300 AIR DUCT ACCESSORIES

233416 CENTRIFUGAL HVAC FANS

233713 DIFFUSERS, REGISTERS, AND GRILLES

236313 AIR-COOLED REFRIGERANT CONDENSERS

237200 AIR-TO-AIR ENERGY RECOVERY EQUIPMENT

238127 VARIABLE REFRIGERANT FLOW SYSTEMS

238219 FAN COIL UNITS

Jacobs FDZD1402 TOC - 3 03/23/2015 Final Submittal

Division Section Title

DIVISION 26 - ELECTRICAL

260500 COMMON WORK RESULTS FOR ELECTRICAL

260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

260529 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

260533 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS

260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS

262416 PANELBOARDS

262726 WIRING DEVICES

262816 ENCLOSED SWITCHES AND CIRCUIT BREAKERS

265100 INTERIOR LIGHTING

265219 EMERGENCY AND EXIT LIGHTING

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

283111 DIGITAL, ADDRESSABLE FIRE-DETECTION SYSTEM

APPENDICES

ASBESTOS SURVEY – BUILDING 7232

ASBESTOS SURVEY – BUILDING 7233

END OF TABLE OF CONTENTS

Jacobs FDZD1402 TOC - 4 03/23/2015 Final Submittal

PAGE INTENTIONALLY LEFT BLANK

Section 00 01 02 Dyess AFB, Texas SPECIAL CONDITIONS Repair HVAC Bldgs 7232, 7233

Special Conditions – Section 00 01 02 - page 1 of 6

PART 1 – GENERAL

1. SCOPE: The work covered by this project consists of the Contractor furnishing all layout, survey, plant, labor, supervision, quality control, materials, equipment, machines, tools, appliances, services, supplies, and incidentals and of performing all operations in connection with the repair and replacement of HVAC systems in Buildings 7232 and 7233 at Dyess AFB, Texas, complete and in strict accordance with the plans and specifications."

2. WORKING CONDITIONS: Contractor shall carefully consider the following when contemplating any specific task identified by the government reflecting any special or unusual conditions which may affect the Contractor's work such as:

- phasing requirements- portions of these buildings will remain occupied during construction

- work area availability

- joint occupancy

- scheduling – submit for approval a detailed schedule; weekly updated

- down time – provide5-day written notice of downtime

- required notice requirements

- requirements for Contractor employees to enter secured work areas

- traffic control

- temporary heating/cooling – provide temporary heating and cooling for occupied areas

- required certificates prior to award

- required work plans

- any other special conditions

- contractor isi responsible for moving, protecting, storing, and reinstalling all office furniture

Above all, insure this item is properly coordinated and discussed in detail with the user/occupant.

3. WORK SCHEDULE: Working hours for the Contractor will normally be between the hours of 7:30 a.m. and 4:30 p.m. excluding Saturdays, Sundays, and Federal holidays. If the Contractor desires to work during periods other than above, additional government inspection forces may be required. The Contractor must make their request to the Contracting Officer five (5) calendar days in advance of their intention to work during other periods to allow assignment of additional inspection forces. If such force is reasonably available, the Contracting Officer may authorize the Contractor to perform work during periods other than normal duty hours/days.

3.1 DOWN TIME: Down time shall be defined as delays in excess of one hour at a given period, caused by the Government through no fault of the Contractor.

a. MEASUREMENT: Contractor shall comply with all security requirements under paragraph 13 of this specification section to qualify for down time compensation.

(1) Down time will be measured by the unit time-of-the-clock hour which will include all Contractor and sub-Contractor (at any tier) work forces scheduled for, or working during the hour.

(2) No delays less than one hour in duration at any given period will be measured nor considered for down time, nor will delays of less than one hour be cumulative over several time periods.

(3) Down time will not be measured/considered for delays before or after contract work schedule hours as defined in the contract General Provisions.

Special Conditions – Section 00 01 02 - page 2 of 6

(4) No time after 10 minutes from the time that Contractor is notified that he can resume work after a stoppage will be considered down time.

b. PAYMENT: Payment for down time will be made at the contract unit price for down time as shown on the bid schedule in accordance with the Contact Clause entitled Payments Under Fixed Price Construction Contracts.

4. SAFETY AND HEALTH:

4.1 All Contractor operations shall be conducted and performed in accordance with Department of Labor, OSHA requirements found in 29 CFR 1910 and 29 CFR 1926, project identified national standards, military manuals, instructions, pamphlets, and standards and handbooks.

4.2 All companies who conduct business within the state of Texas must, in accordance with Texas Workman Compensation laws (Texas House Bill 62), have an approved company safety policy and an Accident Prevention Plan. The plan, approved by the Texas Workman Compensation Commission (TWCC), shall be submitted For Information Only (FIO) in accordance with paragraph SUBMITTAL REQUIREMENTS. In addition to meeting the TWCC requirements; the plan must also include the requirements of COE Safety Manual, latest edition.

4.3 All holes/pits/trenches/manway openings, etc, that are to be left open shall be surrounded with a 48 inch high mesh fence with highly visible orange plastic coating. The fence shall be securely anchored with tension wires and posts as required to prevent sagging and located a minimum of 3 feet from the opening so as to prevent an individual, should they fall across the fencing, from falling into the opening.

Holes shall also be covered, when not being worked in, with three quarter inch plywood or a metal grating that will prevent small children from entering the hole. If the hole/pit is too large to cover, then a ladder of sufficient length shall remain in the hole/pit for egress.

4.4 Radiation Permits and Authorizations: Contractors contemplating the use of devices containing radioactive materials (i.e., soil moisture/density probes) or non-ionizing radiation producing equipment (radio frequency radiation emitters or lasers) while performing work on this contract must obtain written authorization/permit from the Dyess AFB Radiation Safety Officer (RSO), 7 ADOS/SGGB. To obtain the required authorization permit, an application to bring a radioactive device on Dyess AFB must be forwarded to 7 ADOS/SGGB, 697 Hospital Road, Dyess AFB, TX 79607-1367 (this is mailing address, physical address is 880 Third St.) or (325)696-2325 / 3289, at least 45 days prior to the anticipated use.

Without the proper authorization, Contractors will not be allowed to bring these devices on base. Also, Contractor shall provide Bioenvironmental Engineering (7 ADOS/SGGB) a copy of contractor’s radioactive materials permit and training certificates, if radioactive material will be brought onto Dyess

AFB.

4.5 Confined Space Entry: All operations involving entry into confined spaces shall meet the requirements of OSHA 29 CFR 1910.146, AFOSH Std 91-25, and specifically the following:

a. All entry supervisors, attendees, and confined space entrants shall have been properly trained in the safety hazards, proper use of Personal Protective Equipment (PPE), entry procedures, and self-rescue.

Records of this training must be readily available.

b. Entry supervisors shall maintain a Master Entry Plan (MEP) consisting of:

(1) Descriptions of confined spaces to be entered including location, classification, and acceptable

Special Conditions – Section 00 01 02 - page 3 of 6 entry conditions

(2) Designation of authorized entry supervisors, entrants, and attendees

(3) Identification of the types of tasks to be performed in the confined space, including duration

(4) Procedures for entry, and emergency rescue

(5) Identification of Personal Protective Equipment (PPE), communication equipment, rescue equipment, and monitoring equipment; conditions under which they will be used; and verification of condition of equipment

(6) Designation of frequency and type of atmospheric monitoring

(7) Designation of controls required (e.g., lockout/tagout, ventilation, etc.)

(8) Procedures for communication during confined space operations

c. All confined spaces shall be tested by a qualified person using a properly calibrated monitor for percent oxygen, lower explosive limit (LEL), and toxicity each time before entry and periodically during operations that have the potential to alter atmospheric conditions. Supervisors shall contact 7 BW/SEG when these or any other entry conditions are not consistent with the MEP.

4.6 Additionally, other special considerations which may apply such as speed limits in MFH, vehicles with catalytic converters operating within 50' of aircraft, work being performed in explosives clear zones, equipment disposition in the Munitions Storage Area (MSA) during and after work hours, etc. For most conditions FAR 52.236-13 Accident Prevention, which Contracting will include by reference, will be sufficient. A paragraph on "Airfield Safety Precautions," DFARS 252.236-7005, should automatically be included by reference by Contracting in the General Provisions of applicable airfield construction contracts. Verify the FAR references to avoid duplication. Resolve with Contracting if in doubt.

5. DISPOSITION OF WASTE, EXCESS, SCRAP, AND SALVAGE MATERIALS: The title to all waste, excess, scrap, and salvage materials generated as a direct result of this contract is vested in the Contractor - unless specifically excepted below. Further (unless listed below in exceptions), these materials shall be disposed of off the Base by the Contractor in accordance with all applicable Federal, State, and Local Regulations. Following is a list of materials (Exceptions) that will be generated as a result of this contract and shall be turned-in to the Government at a location at Dyess AFB designated by the Contracting Officer:

Exceptions: Government will identify salvage in SOW/SOO for each project.

6. STORAGE AREA (I.E. TEMPORARY FIELD OFFICE, STAGING AREAS, TOOL/JOB SHACKS,

AND OTHER CONSTRUCTION FACILITIES): There are no Government furnished covered or secure storage areas. Limited on-base, off-site storage will be permitted on a space available basis. The location on Dyess AFB of the Contractor’s temporary field office, storage, and other construction buildings required temporarily in the performance of the work, shall require written approval of the Contracting Officer. Plans showing temporary field office, storage, and other construction buildings shall be submitted for approval (GA) of the Contracting Officer. Utilities at the storage area may or may not be available for Contractor use. The Government implies no responsibility for lost or stolen materials, equipment or tools, the security of which lies solely with the Contractor. Contractor shall keep their storage areas clean, neat and orderly and will keep grass mowed to a maximum height of 4 inches.

Temporary fencing used by the Contractor to delineate constructor sites shall be securely anchored with tension wires and posts as required to prevent sagging and an unsightly appearance. Fencing shall be maintained by the Contractor in this manner throughout the life of the contract. Due to high winds in West Texas, Contractor shall take every precaution to preclude trash from blowing off site.

6.1 CONSTRUCTION AREA & CONTRACTOR LIMITS OF CONSTRUCTION: Contractor shall keep their construction areas clean, neat and orderly and will keep grass mowed to a maximum height of

Special Conditions – Section 00 01 02 - page 4 of 6

4 inches.

7. TOILET FACILITIES:

7.1 Use of existing toilet facilities if available will identified in SOO/SOW. Contractor personnel will ensure facility cleanliness is maintained at all times.

7.2 If not identified in the SOO/SOW, there are no toilet facilities available for Contractor use.

Contractor shall provide his own portable/temporary toilet facilities.

8. CLEAN-UP: The Contractor shall at all times keep the construction site and storage area(s) free from accumulation of waste, rubbish, or construction debris. All loose or lightweight materials shall be secured to prevent blowing or scattering. The burning of trash or construction debris is strictly prohibited on Dyess AFB. Prior to final inspection, the Contractor shall remove all construction debris, tools, equipment, and materials not the property of the Government. Upon completion of the work, the Contractor shall leave the work site and storage area(s) in a clean, neat and workmanlike condition satisfactory to the Contracting Officer.

8.1 Additional requirements may be specified in the SOO/SOW such as special noise limitations, dust protection or existing equipment protection, etc.

9. INSPECTIONS:

9.1 Above Ceiling Inspection: The Contractor shall advise the Contracting Officer of the Contractor's desired above ceiling inspection date seven (7) calendar days in advance of that desired date to permit proper coordination.

9.2 Final Inspection: The Contractor shall advise the Contracting Officer of the Contractor's desired final inspection date seven (7) calendar days in advance of that desired date to permit proper coordination. The date selected shall provide adequate time for Contractor performed corrections of final inspection deficiencies within the contract performance time. The Contracting Officer will be the final authority for determining whether or not the Contractor's performance is sufficiently advanced to warrant a final inspection.

9.3 All wall penetrations and security measures shall be inspected/approved by BCE and Contractor shall submit documentation before it is covered up.

10. TESTING: Costs of all tests, unless specifically indicated as being performed by the Government, will be at the Contractor's expense. It is the responsibility of the Contractor to schedule all tests and to notify the Contracting Officer or his representative in a timely manner prior to any required testing. All test results shall be submitted to the Contracting Officer on AF Form 3000, Material Approval Submittal.

11. AS-BUILT DRAWINGS, INSTRUCTION MANUALS, AND TRAINING:

11.1 As-Built Drawings: The Contractor shall maintain two sets of project drawings for "as-built" notations and marking. The Contractor shall update these plans to indicate "as-built" construction and shall submit them to the Contracting Officer prior to final inspection under the cover of an AF Form 3000. Updated notations and markings shall be neat, clear, and legible in all respects.

11.2 INSTRUCTION MANUALS (O&M Data): Required instruction manual(s) shall be provided in three ring binder(s) with tabs and an index/table of contents. Provide permanent label on front and side

Special Conditions – Section 00 01 02 - page 5 of 6 with project title, project number, facility number, street address, Contractor/Subcontractor name, address, phone number(s), and manual title/contents description. Include all wiring diagrams and parts lists. Manuals shall be submitted to the Contracting Office for approval prior to Final Inspection.

11.3 TRAINING REQUIREMENTS: Provide training for government operating and service personnel in the proper operation of contractor furnished equipment. Schedule training time(s) with Contracting Officer to permit maximum participation by government personnel. Each instruction or training period shall be videotaped by the Contractor and files will be submitted to the Government in WMV, MPEG, or MP-4 format on a CD/DVD. The recording shall include the entire session(s). The original CD/DVD video(s) shall be labeled and turned over to the Contracting Officer shall be of a quality to enable clear and understandable playbacks of the recorded events.

12. SECURITY REQUIREMENTS:

Dyess AFB security may be viewed as being one of three broad levels, the level in effect being dependent on the location or AREA of Dyess AFB in question.

a. The lowest level of security exists in GENERAL ACCESS AREAS. These AREAS are all of Dyess AFB outside of the "USAF Controlled" and "USAF Restricted" AREAS.

b. USAF Controlled Access AREAS are the mid-level security AREAS. Presence within the CONTROLLED ACCESS AREA is by authorization; however, the movement of authorized personnel in and out of these AREAS is generally not impeded. Contractor personnel are given access to these

AREAS.

c. The third and highest level of security on Dyess AFB is that within the USAF RESTRICTED AREAS.

These AREAS are further subdivided to be known as Protection Level 1, 2 or 3 AREAS.

12.1 Referencing the above, the work on this contract will be identified in the SOO/SOW.

12.2 Requests for changes to the work schedule for work in USAF restricted areas, must be submitted a minimum of 7 calendar days in advance for approval and coordination of Dyess AFB Security Forces.

12.3 Dyess Air Force Base is a closed base. All personnel entering must have specific permission of the installation commander for entry. This permission is granted when a Contractor employee is issued an identification card. Information necessary to obtain identification cards will be provided by the Contracting Officer at the pre-performance conference. The Contractor shall be responsible to ensure that all of its employees obtain, and keep on their person at all times while working on the base, a USAF identification card. Upon completion of the work or termination of an employee, the Contractor shall be responsible for turn in of identification cards no longer needed to the Contracting Officer or to the Pass and Registration Office of the Security Forces. Failure to turn in badges will result in last payment of payroll to be withheld and revocation of any future badges issued by Pass and Registration Office to the employee and the contractor.

12.4 APPLICABLE TO RESTRICTED OR FLIGHTLINE CONTROLLED AREAS ONLY:

Contractor shall be required to enclose their contract work area, storage area and employee parking area with 3/8" yellow nylon rope. This rope fence will be supported by fastening it to the top of temporary posts or structures. The posts/structures will be 3 feet (+10%) high. The post/structures spacing and rope tautness will be such that the rope will be no closer than 2 1/2 feet above the walking surface. This fence may be omitted where existing structures bound the contract work area. The intent of this requirement is

Special Conditions – Section 00 01 02 - page 6 of 6 that all personnel (Contractors, Air Force, and visitors) will know the authorized boundary of each Contractor's area and thereby minimize unauthorized movement, and to help promote safety.

13. IDENTIFICATION OF CONTRACTOR VEHICLES: Contractor vehicles must be marked on each side with company name with either permanent or semi-permanent / magnetic signage.

14. WARRANTIES: Any warranties given to the Contractor or sub-Contractor at any tier from a manufacturer of equipment or other items which are provided under this contract shall be transferred to the Government upon final acceptance. Contractor shall submit in writing a single listing with all applicable warranties attached.

15. SUBMITTALS:

15.1 Required Submittals: All submittals required by the Contract Documents shall be submitted for approval to the Contracting Officer. Use a completed AF Form 3000 as a transmittal document. Where a submittal cannot be provided within the required submission date, Contractor shall submit in writing a letter stating the reasons why and furnishing a new projected submission date. All Material Submittals (Form AF 3000) and all submittal data shall be submitted electronically. All pdf’s shall be created from original electronic documents, no scans allowed due to file size, unless otherwise approved.

15.2 Variations/Deviations/Departures from the Contract Documents: Contractor proposed variations, deviations or departures from the contract requirements shall be noted/marked in red on each copy of the submittal data and shall be provided with a letter attachment to the AF Form 3000 summarizing the proposed variation, deviation, or departure. Variations, deviations, or departures shall contain sufficient information to permit complete evaluation. Additional sheets may be used to fully explain why a variation, deviation, or departure is requested. The Government reserves the right to disapprove or rescind inadvertent approval of submittals containing unnoted/unmarked/not-clearly-defined variations, deviations or departures.

**** END OF SECTION ****

Section 00 01 03 Dyess AFB, Texas UTILITIES Repair HVAC Bldgs 7232, 7233

Utilities – Section 00 01 03 - page 1 of 4

1. SCOPE: This section covers identification, interruption and use of utilities.

2. IDENTIFICATION: THE GOVERNMENT DOES NOT KNOW THE LOCATION OF UTILITIES

IN THE WORK AREA. Accordingly, the Contractor shall be SOLELY RESPONSIBLE for locating and marking the exact location of all existing utilities within the contract work area prior to any excavating, trenching, backfilling or disturbance. The Contractor is SOLELY RESPONSIBLE for any and all damage to existing utilities in the contract work area. Upon request by the Contractor, the Government shall furnish all available information in its possession concerning utilities in the contract work area. However, the accuracy of the information provided by the Government is not guaranteed and is only intended to provide some measure of assistance to the Contractor. The Contractor shall call 7 CS/SCOIT at 696-8065 a minimum of five (5) calendar days in advance to have underground communications cable routes marked. Base Civil Engineering does not have nor shall it provide record drawings of Bell Telephone cable plant. In the event the Contractor identifies utilities in the contract work area which interfere with the newly proposed construction, the Contracting Officer shall be immediately notified and the Government shall take necessary corrective action at no cost to the Contractor. The Contractor shall furnish to the Contracting Officer as-built drawings clearly identifying the exact location of all utilities identified in the work area prior to project final inspection.

2.1 Contractor must initiate a Work Clearance Request AF Form 103 (digging permit) from 7 CES/ CEPM a minimum of seven (7) calendar days prior to the start of any construction work. Excavation is not authorized without issuance of a completed and approved AF Form 103. After initial issue, it is the Contractor's responsibility to keep the Work Clearance Request coordinated and up-to-date/current through the remainder of the contract.

2.2 Any removal/relocation/reconnection of any communication device shall be coordinated in advance with 7 CS/SCOIT at 696-8065. Any removal/relocation/reconnection of any Cable TV device shall be also be coordinated in advance with 7 CS/SCOIT (ask for the NCOIC of Cable TV) at 696-2400.

Communications and Cable TV devices to remain shall be protected as required when work proximity dictates.

2.3 Any removal/relocation/reconnection of any fire protection device or intrusion detection systems shall be coordinated in advance with 7 CES/CEOFE at 696-5184. Any removal/relocation/reconnection of any security system should be coordinated with 7 SFS/S5C at 696-8523.

2.4 The locating and marking devices utilized by the contractor for existing utilities or proposed work shall be 2” wooden stakes with multicolored whiskers 4” to 6” in length.

2.5 Geospatial Information System (GIS) Data. The Contractor shall provide GIS where underground utilities are installed, note the elevation of the utility installed every 30 feet. Where new utilities cross-existing utilities, note the elevation of the new and existing utility and the vertical and/or horizontal separation. Where new utilities run parallel to new and existing utilities, note the elevation at which installed and the horizontal and/or vertical separation between utilities.

2.6 All labor, equipment, materials and rentals/fees required to provide Geospatial Information System Data shall be at no additional cost to the Government.

3. INTERRUPTIONS:

3.1 Planned Utility Outages: The Contractor shall coordinate all requests for utility outages with the Contracting Officer in writing fourteen (14) calendar days prior to date of requested outage. Water, gas, steam, sewer and electrical outages shall be held to a maximum duration of 2 hours unless otherwise approved in writing. See Contractor Request for Utility Outage included in this Section.

Utilities – Section 00 01 03 - page 2 of 4

3.2 Unplanned Utility Outages (Accidental Disruption of Utilities): In the event of accidental disruption of any utility, the Contractor shall immediately notify the Contracting officer of the unplanned outage.

The Contractor shall immediately take every reasonable step to repair the damage in a manner acceptable to the Government and will restore the utility to full use as soon as practicable. If the Contractor so desires, and the Government agrees, the Government may complete necessary repairs to the damaged utility and withhold from payments due to the Contractor the necessary amount to defray all costs associated with the repair of the utility.

4. USE: All reasonable quantities of existing utilities will be made available to the Contractor without charge. Any temporary connections or lines required shall be installed, maintained, and removed at the Contractor's expense. Any damage associated with the use of these utilities shall be repaired and/or replaced in a manner satisfactory to the Contracting Officer at Contractor's expense. See Contractor Request for Use of Dyess AFB Fire Hydrants included in this Section.

Utilities – Section 00 01 03 - page 3 of 4

The following information must be prepared and forwarded, on AF Form 3000, Material Approval Submittal, to the CO for approval and coordination with Civil Engineering.

Request For Utility Outage

From: __________________________________________________________________

Contract No:__________________Description and Location of Contract: __________

Date of Outage Requested:___________Type of Outage:_________________________

Location Affected by Outage:

Description of Work to be performed and Other Utilities Affected:

Requested Civil Engineer Support:

Date:_______________ Time:________________________

Type of Support:

Electrical X-5184_______ Water X-4481__________________

Access X-4155_________ Road Closure X-4155____________

Alarms X-5195_________ Fire Dept Standby X-4930________

Duration of Outage: Start:_____ Completed:____________________

Signature:

Contractor Representative: Date:

Utilities – Section 00 01 03 - page 4 of 4

The following information must be prepared and forwarded, on AF Form 3000, Material Approval Submittal, to the Contracting Officer for approval and coordination with Civil Engineering’s Fire Department and Utilities prior to use of Base fire hydrants.

Contractor Request for Use of Dyess AFB Fire Hydrants.

Project Title ___________________________________________________________________

1. The ____________________________ Company requests the use of fire hydrant number _______for the purpose of ______________________________________ used in the performance of the contract to ___________________________. Period of hydrant use will be ________________ to _____________.

I understand approval is contingent on all of the following:

a. The company providing a suitable connection with a Class III Back Flow Preventer (reduced pressure principle device) and screw type globe valve to be attached to the hydrant. The connection will be 2 1/2" National Standard fire thread. The backflow device and valve shall be installed prior to hydrant use & properly supported to prevent damage to fire hydrant threads.

b. Call the Water Shop for certification of your backflow device PRIOR TO INSTALLATION at 325-696-1807. Non-compliant devices will be removed without notice.

c. Backflow preventers shall be installed with the vent facing down & at least 12" clearance below the unit.

d. Leaving the connection in place during approval period.

e. Insuring the hydrant is fully opened and left in that position during approval period, except in periods of freezing weather. If hydrant is closed, it must be RECERTIFIED prior to reopening.

f. Insuring an approved fire hydrant wrench is used to open/close the hydrant.

g. Insuring all servicing from the hydrant is done at the top of the vehicle or tank. No bottom servicing will be permitted.

h. Using no quick opening valves causing excess water hammer in the main.

i. Discontinuing hydrant use if there is any hydrant malfunction or leakage from underground and reporting same to the Fire Department, 696-2486.

2. I understand and agree that __________________________Company assumes full responsibility for any damage to the hydrant, water mains, adjacent grounds, vegetation, buildings, or streets resulting from hydrant use.

(Signature) (Date)

(Print Name) (Print Title)

**** END OF SECTION ****

Section 00 01 04 Dyess AFB, Texas ENVIRONMENTAL Repair HVAC Bldgs 7232, 7233

Environmental – Section 00 01 04 - page 1

1. APPLICABLE ENVIRONMENTAL REGULATIONS, LAWS, AND PUBLICATIONS: In accordance with (IAW) Executive Orders (EO) 13101, 13123, 13134, and 13148, federal, state, and local environmental protection laws, Dyess Air Force Base (DAFB) is committed to the principals of “Leadership in Environmental Management” and “Greening the Federal Government.” In addition, DAFB implements EO 13045, 13229, and 13296, to ensure protection from environmental health and safety risks. The specifications and standards contained in this section are to ensure that DAFB meets the mandates as established by statute and EOs, as well as Environmental Protection Agency (EPA), Department of Transportation (DOT), Occupational, Safety and Health Agency (OSHA), and Department of Energy (DOE) policy and guidance.

1.1. ENVIRONMENTAL PROTECTION STANDARDS: The following list serves as the basis for standards of environmental protection for work accomplished on DAFB:

The Resource Conservation and Recovery Act authorized Comprehensive Procurement Guidelines (CPG), The National Technology Transfer and Advancement Act/OMB Circular A-119, DOE's Federal Energy Management Program Product Efficiency Recommendations, EPA's Waste Minimization Priority Chemicals, EPA's Indoor Environments Program Recommendations, and

EPA's Construction Industry Compliance Assistance Center Recommendations.

1.2. ENVIRONMENTAL GOALS:

1.2.1. General:

1.2.1.1. Resource Management: Promote stewardship of the earth's resources. The earth's resources include: perpetual resources, renewable resources, and non-renewable resources. Preserve or renew biodiversity and ecosystems.

Maximize use of bio-based and recycled content materials.

Maintain or improve water quality and promote water stewardship.

Employ job-site recycling and salvage procedures.

Employ DfE methodologies.

1.2.1.2. Toxicity/IEQ: Promote good indoor environmental quality (IEQ). Aspects of IEQ include: light quality, acoustic quality, and air quality.

Utilize a precautionary approach.

Maximize use of non-toxic, non-hazardous, healthy, and safe building materials.

1.2.1.3. Performance: Promote efficiencies in operational performance. Aspects of operational performance include: durability, maintainability, energy efficiency, and water efficiency.

1.3. CONTRACTOR’S ENVIRONMENTAL MANAGER: The Contractor shall designate an onsite party responsible for overseeing the environmental goals for the project and implementing procedures for environmental protection.

1.3.1. Qualifications: Minimum 5 years construction experience on projects of similar size and scope;

minimum 2 years experience with environmental procedures similar to those of this project; familiarity

Environmental – Section 00 01 04 - page 2 with Environmental Management Systems (EMSs) such as ISO 14001; and familiarity with environmental regulations applicable to construction operations.

1.3.2. Responsibilities: The Contractor’s environmental manager shall ensure:

Compliance with applicable federal, state, and local environmental regulations, including maintaining required documentation.

Implementation of Contractor’s environmental protection plans prepared IAW EPA EMS or ISO 14000 standards.

Training for Contractor personnel IAW their position requirements, and shall include at a minimum, an overview of environmental issues related to the building industry and overview of environmental issues and regulations related to the project.

1.4 CONFORMANCE WITH ENVIRONMENTAL MANAGEMENT SYSTEMS:

The Contractor shall perform work under this contract consistent with the relevant policy and objectives identified in the agency, organizational, or facility environmental management system (EMS) applicable for your contract. The Contractor shall perform work in a manner that conforms to all appropriate Environmental Management Programs and Operational Controls identified by the agency, organizational, or facility EMS, and provide monitoring and measurement information as necessary for the organization to address environmental performance relative to the environmental, energy, and transportation management goals. In the event an environmental nonconformance or noncompliance associated with the contracted services is identified, the contractor shall take corrective and/or preventative actions. In the case of a noncompliance, the Contractor shall respond and take corrective action immediately. In the case of a nonconformance, the Contractor shall respond and take corrective action based on the time schedule established by the EMS Site Coordinator. In addition, the Contractor shall ensure that their employees are aware of the roles and responsibilities identified by the environmental management system and how these requirements affect their work performed under this contract.

All Contractor employees must complete Air Force provided initial EMS awareness-level training. The COR needs to ensure the contractor and their employees complete the training prior to work start and maintain a list of completion in the contract folder for accountability and inspection. The following steps need to be completed by the contractor in order to logon and complete the required training:

To access and register to the ESOH Training Network:

Go to www.esohtn.com

Click on the to enter, then

Find the Registration box on the bottom right side of the screen.

Type into the Registration Password box esohtn

Click on Create an Account, and Follow the instructions on each screen to complete each step of the registration process all blocks with an “*” must be filled.

Step 1. First and Last Name and email address

Step 2 Account information User Id and password

Step 3 User Type: Select “Construction Contractor “or “Non-Construction” Next

Environmental – Section 00 01 04 - page 3

Step 4 Organization information, Select “Dyess AFB”, for your company name if listed, if not listed

Select “Company not Listed”. Select contractor number if applicable—Next.

Step 5 Under Job Functions select “Environmental Requirements for Contractors (Mandatory for all Installation Contractors)” Next

Step 6 Select “I agree”

Step 7 Select “Go To Training”

Step 8 Select “Go to my Training Modules”

Step 9 Select “Go to training” and complete training, complete test and print certificate

When training is complete, forward certificate to the Contractor.

PART 2 – RESOURCE PROTECTION

2. PROTECTION OF RESOURCES: Construction, renovation or demolition activities are not exempt from air emission, storm water, hazardous waste, and other environmental compliance, environmental protection or pollution prevention rules and regulations. Contractor shall investigate, comprehend, and comply with all environmental rules and regulations applicable to his chosen method of accomplishment of the work under this contract.

2.1. PROTECTION OF LAND RESOURCES: The Contractor shall confine his construction activities to areas defined by the plans or specifications. Except in areas to be cleared, do not remove, cut, deface, injure or destroy trees or shrubs without the CO’s approval. Do not fasten or attach ropes, cables, or guys to existing nearby trees for anchorage unless authorized by the CO. Where such use of ropes, cables, or guys is authorized, the Contractor shall be responsible for any resultant damage.

2.1.1. Restoration or Replacement of Landscape Damage: Any trees or other landscape feature scarred or damaged by the Contractor’s equipment or operations shall be restored as nearly as possible to its original condition at the Contractor's expense. The CO will decide what method of restoration shall be used, and whether damaged trees shall be treated or removed and disposed of under requirements for clearing and grubbing. If damaged trees are to be removed, they are to be replaced with equivalent, undamaged trees and landscaping features at the Contractor’s expense.

2.1.2 Topsoil and other Construction Fill Material from Off Base: Contractor must comply with the Federal Noxious Weed Act, as amended, 7 U.S.C. 2801-2814; 7CFR360: the Plant Protection Act (7 U.S.C. 7701 et seq.); 7 U.S.C. 7701-7772 and 7781-7786; 7 CFR 2.22, 2.80, and 371.3; and Executive Order 13112, Invasive Species. The Contractor shall not introduce any invasive or noxious weed identified on the latest Federal Noxious Weed List (Federal Noxious Weed Act of 1974), the Texas Administrative Code (TAC) Quarantines and noxious plants, Chapter 19 (24 May 2006). State of Texas;

the DAFB Integrated Natural Resources Management Plan, Chapter 7.12, Invasive Species Management.

2.1.3. Post-Construction Cleanup or Obliteration: The Contractor shall obliterate all evidence of temporary construction facilities such as haul roads, work areas, structures, foundations of temporary structures, stockpiles of excess materials, or any other vestiges of construction. It is anticipated that excavation, filling, and plowing of roadways will be required to restore the area to near natural conditions which will permit the growth of vegetation thereon. The disturbed areas shall be graded and filled as required, and topsoil shall be spread to a depth of approximately three inches over the entire area and the entire area seeded with at least two pounds (pure live seed) of common Bermuda per 1,000 square feet and then watered as required until a lush hardy growth is established to the satisfaction of the CO.

Restoration to original contours is required unless otherwise directed by the CO.

http://www.aphis.usda.gov/plant_health/plant_pest_info/weeds/downloads/weedlist2006.pdf http://info.sos.state.tx.us/pls/pub/readtac$ext.TacPage?sl=R&app=9&p_dir=&p_rloc=&p_tloc=&p_ploc=&pg=1&p_tac=&ti=4&pt=1&ch=19&rl=300

Environmental – Section 00 01 04 - page 4

2.2. PROTECTION OF THE STRATOSPHERIC OZONE: The Contractor shall comply with Title 40 of the Code of Federal Regulations, Part 82 (40 CFR Part 82). To the maximum extent practicable, the Contractor shall utilize safe alternatives and products made with, or containing, safe alternatives to Class I or II ozone depleting substances (ODS) identified in 42 U.S.C. 7671K. A Class I ODS is defined in section 602 (a) of the Clean Air Act (CAA) and includes the following chemicals:

CFC-11 CFC-12 CFC-13 CFC-111 CFC-112

CFC-113 CFC-114 CFC-115 CFC-211 CFC-212

CFC-213 CFC-214 CFC-215 CFC-216 CFC-217

halon-1211 halon-1301 halon-2402 carbon tetrachloride methyl chloroform

2.3. PROTECTION OF HISTORICAL AND ARCHAEOLOGICAL RESOURCES: All known historical, archaeological, and cultural resources, if any, within the Contractor’s work area will be designated on the contract drawings. The Contractor shall take precautions during the contract to preserve all resources as they existed at the time of contract award and comply with the National Historic Preservation Act (NHPA), 36 CFR 60-61 and 800-812; and Native American Graves Protection and Repatriation Act (NAGPRA), 43 CFR 10. The Contractor shall provide all protective devices such as off-limit markings, fencing, barricades or other devices as designated on the contract drawings and shall be responsible for preservation of the sites during this contract.

2.3.1. Recording and Preserving Historical and Archaeological Finds: All items having any apparent historical or archaeological interest outside of designated areas that are discovered in the course of any construction activities shall be carefully preserved. The Contractor shall protect the find in-place by leaving the archaeological find undisturbed and by using flags to mark a 50-foot radius area around the find. The find shall be immediately reported to the CO so that the proper authorities may be notified. All work shall be stopped in the immediate area of the discovery until directed by the CO to resume work.

Any work required to preserve or protect these finds shall be accomplished before work resumes.

2.4. PROTECTION OF WATER RESOURCES: The Contractor shall not pollute streams, tributaries, lakes, or reservoirs with substances including, but not limited to, fuels, oils, bitumen, calcium chloride, acids, construction wastes, contaminated storm water runoff, or other harmful materials identified in 40 CFR Parts 117 and 302. It is the responsibility of the Contractor to investigate, comprehend, and comply with all applicable federal, state, county, and municipal laws concerning pollution of rivers and streams--particularly the Clean Water Act (CWA), 33 CFR 151-158 and 320-338, 40 CFR 15, 20-25, 100-149, 220-233, 400-471, 501, and 503, and 49 CFR 130; Federal Water Pollution Control Act (FWPCA), National Contingency Plan (NCP), and Oil Pollution Act (OPA), 30 CFR, 33 CFR, 40 CFR, 46 CFR, and 40 CFR; Safe Drinking Water Act (SDWA), 40 CFR 141-149 and 42 CFR 50, 59, and 124; Pollution Prevention Act (PPA), 40 CFR 370-372; Texas Drinking Water Standards, Title 30 of the Texas Administrative Code, Part 290 (30 TAC 290); and the Texas Water Code, 30 TAC 205,216, 220, 279, 305, 307-308, 311-312, 314, and 321. All work under this contract shall be performed in such a manner that objectionable or nuisance conditions will not be created in lakes, reservoirs, or streams through or adjacent to the project areas. For construction sites of one (1) acre or more, and at least 30 days prior to the start of construction, the Contractor shall prepare a storm water pollution prevention plan (SWP3) and file with Texas Commission on Environmental Quality (TCEQ) a Notice of Intent (NOI), TCEQ-20022 (02/03) or successor form. The construction site notice specified in the Texas Pollutant Discharge Elimination System General Permit (TPDES GP) for Part II.D.2 shall be posted as specified in the permit.

Construction activities that start on or after 15 December of one year and are completed in all respects, including final stabilization, by 14 February of the next year may utilize low rainfall erosive waiver provisions of the TPDES GP, which do not require a SWP3, but do require submittal of an NOI to TCEQ using TCEQ-20064 (02/03) or successor form, and posting of a construction notice for Part II.D.1 of the GP. Contractor shall submit a Notice of Termination (NOT) as required by the GP using TCEQ-20023

Environmental – Section 00 01 04 - page 5

(02/03) or successor form. Contractor shall perform notifications as required by the GP. There shall be no fill, to include trees and vegetation, placed in a wetland or water of the U.S. as they are defined by the CWA or the 1987 Corps of Engineers Wetlands Delineation Manual. Wetlands and/or possible wetlands in the work area will be delineated prior to awarding of the contract. The Contractor shall be aware of CWA Section 404 requirements and permits and shall be responsible for compliance. Vehicles shall not pass through wetlands unless absolutely necessary, and mats will be placed on the area for protection prior to driving. Certain documents must be prepared, filed, and/or posted as generally outlined in the table below and specifically stated in the TPDES GP:

Site

Size, Acres

Low Erosive

Provision

Applies

Notice of

Intent (NOI)

Required

Storm Water

Pollution

Prevention

Plan (SWP3)

Required

Construction

Site Notice

(CSN)

Required

Notice of

Termination

(NOT)

Required

Provide to

MS4

< 1 N/A No No No No N/A

1 - < 5 Yes No No Yes No CSN

1 - < 5 No No Yes Yes No CSN

> = 5 No Yes Yes Yes Yes NOI, NOT

2.4.1. Erosion Control: The Contractor shall control erosion and disposing of wastes. Surface drainage from cuts and fills within the construction limits, whether or not completed, and from borrow and waste disposal areas, shall, if turbidity producing materials are present, be held in suitable sedimentation ponds, or the areas shall be graded to control erosion within acceptable limits. Temporary erosion and sediment control measures such as berms, dikes, drains, or sedimentation basins, if required to meet the above standards, shall be provided and maintained until permanent drainage and erosion control facilities are completed and operative. The area of bare soil exposed at any one time during construction operations shall be held to a minimum.