Attach 10 - Site Visit Sign In and Meeting Minutes 10Aug26.pdf

PDF 842 KB Posted

Attached to
Whiteman AFB - FY27 Airfield Pavement
Solicitation number
FA462526Q1062
Issued by

About this file

This document contains the initial site visit sign-in sheet and meeting minutes for the FY27 Airfield Pavement IDIQ contract for Mill & Overlay work on Taxiway Golf, dated August 10, 2026 at 1000 hours.

The meeting minutes establish key contractor requirements and clarifications for the seed project, estimated for completion in summer 2027 pending funds availability. Asphalt trucks may access the flightline through Gate 9 or the gate between buildings B1720 and B1721; however, for IDIQ bid schedule purposes, offerors must include pricing assuming trucks will use standard Entry Control Points (ECPs). A separate credit line item may be submitted for the seed project considering streamlined access. The contractor is not required to perform saw cutting along the western edge where asphalt abuts existing concrete. Any damage to on-base paint caused by truck access must be repainted by the contractor. Cleanup of tac coat and asphalt marks on adjacent concrete is restricted—sanding is prohibited due to Foreign Object Damage (FOD) hazard concerns. Paint markings must be restored to match pre-work conditions exactly, except the black paint border will not be repainted; yellow stripes must be Airfield stripes with reflective type III beads (Line Item 019).

View the file

Other files

File Type Posted
FA462526Q1062 Combo Synopsis Solicitation 02Sept26.pdf PDF
Attach 12 - Solicitation Questions and Answers 02Sept26.pdf PDF
FA462526Q1062 Combo Synopsis Solicitation.pdf PDF
FA462526Q1062 Combo Synopsis Solicitation 26Aug26.pdf PDF
Attach 11 - Solicitation Questions and Answers 26Aug26.pdf PDF
FA462526Q1062 Combo Synopsis Solicitation.pdf PDF
Attach 11 - Solicitation Questions and Answers.pdf PDF
FA462526Q1062 Combo Synopsis Solicitation.pdf PDF
Attach 1 - SOW Airfield Pavement 4 Aug 2026.pdf PDF
Attach 9 - SOW SEED Taxiway Golf 4 Aug 2026.pdf PDF
Attach 1 - SOW Airfield Pavement 4 Aug 2026.pdf PDF
Attach 8 - Airfield Pavements Bid Schedule.xlsx XLSX spreadsheet
FA462526Q1062 Combo Synopsis Solicitation.pdf PDF
Attach 5 - Past Performance Questionnaire.docx DOCX document
Attach 9 - SOW 1157746 Repair Airfield Spalling DV Ramp 15 july 2026.pdf PDF
Attach 8 - Airfield Pavements Bid Schedule.xlsx XLSX spreadsheet
Attach 6 - General Decision Number MO20260001 18May2026.pdf PDF
Attach 7 - Provisions and Clauses.pdf PDF
Attach 1 - SOW Airfield Pavement 15 July 2026.pdf PDF
Attach 4 - SOW Atch 3 - TSPWG M 3-250-04.97-05 12 August 2019.pdf PDF
FA462526Q1062 Combo Synopsis Solicitation.pdf PDF
Attach 2 - SOW Atch 1 - WAFB - Security Procedures for Construction Contracts.pdf PDF
Attach 3 - SOW Atch 2 - WHITEMAN AIR FORCE BASE Supplement (16 August 2023).pdf PDF
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Initial Site Visit Sign In FY27 Airfield Pavement IDIQ- Mill & Overlay Taxiway Golf

Date: JO Aug 2026 Time: 1000

The following personnel were in attendance:

Name and Or anization Email and Phone Si nature

Initial Site Visit Meeting Minutes FY27 Airfield Pavement IDIQ – Mill & Overlay Taxiway Golf

Date: 10 Aug 2026 Time: 1000

The following are the meeting minutes for the above Site Visit:

• Asphalt trucks for the seed project may enter the flightline through gate 9 and the gate in between B1720 and B1721, directly Southwest and west respectively of the site. For bid schedule purposes, offerors are directed to include pricing in the IDIQ assuming trucks will go through the ECPs for flightline access. For the seed project, offerors may include a separate credit line item considering the streamlined access for the site.

• The contractor is not required to perform saw cutting along the western edge of the seed project where asphalt abuts the existing concrete.

• The seed project is estimated to be completed in the summer of 2027. Pending funds availability.

• If trucks damage or obscure paint on-base when accessing the seed project site, the contractor will be required to re-paint affected areas.

• For cleanup of tac coat and asphalt marks, if it occurs, on the concrete west of the project site, sanding will not be allowed to be used as it will create a FOD hazard.

• Paint markings on the mill & overlay area are required to match exactly as they were prior to work; however, the black paint boarder will not be repainted. The yellow stripes will be Airfield stripes, reflective with type III beads (Line Item 019).

Site Visit Sign In Sheet 11Aug26.pdf
Site Visit Meeting Minutes 11Aug26.pdf