These meeting minutes document key details for the Whiteman AFB Temporary Lodging Facilities (TLF) Roof Replacement project. The minutes indicate that the facilities will be vacated during construction, with a 14-day notice to be issued beforehand. The contractor (KTR) anticipates needing to replace more than 10% of the existing roof sheeting, with any work beyond that 10% threshold requiring a contract modification to account for additional work scope.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TLF Roof Replacement Solicitation Site Visit Meeting Minutes
1. The Temporary Lodging Facilities will be made vacant during construction.
a. 14-day notice will be issued beforehand.
2. KTR believes more than 10% of the sheeting will need to be replaced.
a. Any work over the 10% of cumulative sheeting replacement will be need a modification as it will intend additional work.