Atch 6 Cost Breakdown Sheet Rev1.xlsx
XLSX spreadsheet 22 KB Posted
- Attached to
- AMENDMENT 06 (15 Sept 2025): Topside Deep Clean at 15 Missile Alert Fields (MAFs), FE Warren AFB, Wyoming
- Solicitation number
- FA461325R0009
About this file
Attachment 6 is a Cost Breakdown Sheet for a deep cleaning project at 15 Missile Alert Facilities (MAFs) located at FE Warren Air Force Base in Wyoming. The Excel spreadsheet provides a detailed pricing template for contractors to complete, requiring unit pricing for specific cleaning areas including flooring (1800 sq ft), ceiling (500 sq ft), walls (500 sq ft), and various accessories like bathroom fixtures, mirrors, and other elements. The document instructs contractors to fill in unit prices, which will automatically calculate total prices for one MAF and all 15 MAFs, with a note that if verified square footage changes, total contract costs will be adjusted while maintaining the original unit pricing.
The related federal contract opportunity, solicitation number FA461325R0009, is issued by the Department of the Air Force Global Strike Command and involves a topside deep cleaning project. Key submission requirements include a signed CUI (Controlled Unclassified Information) receipt, NIST SP 800-171 assessment with a minimum score of 110, a Quality Control Plan, and a 2-page past performance document. Funding is contingent on appropriation availability, and offers must be submitted via email by 11:00 am MST on Tuesday, 16 September 2025, to megan.evans.3@us.af.mil and liezel.mcintyre@us.af.mil.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Conformed Copy.pdf | ||
| Amendment 06.pdf | ||
| Atch 6 Cost Breakdown Sheet Rev3.xlsx | XLSX spreadsheet | |
| Atch 8 Additional Info During Extension.pdf | ||
| Conformed Copy.pdf | ||
| Atch 6 Cost Breakdown Sheet Rev2.xlsx | XLSX spreadsheet | |
| Amendment 05.pdf | ||
| Atch 6 Cost Breakdown Sheet Rev1.xlsx | XLSX spreadsheet | |
| Amendment 04.pdf | ||
| Conformed Copy.pdf | ||
| Atch 7 PreBid Questions and Answers 3 Sept 25.pdf | ||
| Amendment 03.pdf | ||
| Amendment 02.pdf | ||
| Atch 1 PWS 27 AUG 2025 R1.pdf | ||
| Conformed Copy 27 Aug 2025.pdf | ||
| Amendment 01.pdf | ||
| Conformed Copy.pdf | ||
| Atch 6 Cost Breakdown Sheet.xlsx | XLSX spreadsheet | |
| Atch 5 Combined Wage Determinations.pdf | ||
| Atch 1 PWS 06 AUG 2025.pdf | ||
| Atch 4 Hazmat Authorization Request.pdf | ||
| Atch 3 AF 66 Submittal Register.pdf | ||
| Atch 2b NIST SP800-171 Entry Guide.pdf | ||
| Atch 2a NIST SP 800-171 Assessment.pdf | ||
| Solicitation - FA461325R0009.pdf | ||
| Atch 2c SPRS Registration.pdf | ||
| Atch 2 MFR CUI Receipt.pdf |
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Costs Breakdown | ||||
| MAF Areas to be Cleaned | **Estimated Sq Ft used as a common multiplier (Contractor to verify area according to drawings). | Unit Price | Total for 1 MAF | Total for 15 MAFs |
| Flooring | 1800 sf | $ - 0 | $ - 0 | $ - 0 |
| Ceiling | 500 sf | $ - 0 | $ - 0 | $ - 0 |
| Walls | 500 sf | $ - 0 | $ - 0 | $ - 0 |
| Accessories: Bathroom/Kitchen | 1 Gallon | $ - 0 | $ - 0 | $ - 0 |
| Accessories: Bathroom Mirrors | 4 Each | $ - 0 | $ - 0 | $ - 0 |
| Accessories: Fixtures (faucet, sink, urinal, etc.) | 30 Each | $ - 0 | $ - 0 | $ - 0 |
| $ - 0 | ||||
| TOTAL EVALUATED PRICE | $ - 0 |
| Instruction for Contractor: |
| 1. Contractor fills out unit price in Cells C4-C9 for each area. |
| 2. Column D is the final price per area for 1 MAF. |
| 3. Column E is the final price per area for all 15 MAFs. |
| 4. Cell E11 is the total evaluated price proposal. |
| **If there is verified discrepancy in square footage (increase or decrease), the total contract costs shall be adjusted but the contractor's unit price per performance elements shall remain the same for award purposes. |
File details come from the government source that posted it. Updated .