Performance Period.pdf
PDF 42 KB Posted
- Attached to
- Saber Pre-solicitation notice Federal contract opportunity
- Solicitation number
- FA4600-10-R-0006
About this file
-
View the file
Other files for this federal contract opportunity
Show all 50
Saber Pre-solicitation notice has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
This project is broken into three parts in order to prevent the entire dining room from being shut down. The dining room work is broken into Phase 1 and Phase 2. The kitchen work is almost entirely separate from Phase 1 and 2. The kitchen can be completed before, after, or concurrent of the dining room work.
The estimated performance period for Phase 1 is 28-32 weeks. The performance period for Phase 2 is 3-6 weeks. The performance period for the kitchen is 24-30 weeks.
This correlates to 4 weeks for startup, base and building access, material order and delivery and other initial tasks with the remainder for construction and testing. Both Phase 1 and the kitchen have the 4 weeks for startup included. These are concurrent but may apply to either if scheduling has one starting before the other.
Overall the performance period is 31-38 weeks if the kitchen is done concurrently with the other Phases.
Long Lead Items:
Air Handling Units 8 – 12 Weeks
Exhaust Fans 4 – 6 Weeks
File details come from the government source that posted it. Updated .