This project is broken into three parts in order to prevent the entire dining room from being shut down. The dining room work is broken into Phase 1 and Phase 2. The kitchen work is almost entirely separate from Phase 1 and 2. The kitchen can be completed before, after, or concurrent of the dining room work.
The estimated performance period for Phase 1 is 28-32 weeks. The performance period for Phase 2 is 3-6 weeks. The performance period for the kitchen is 24-30 weeks.
This correlates to 4 weeks for startup, base and building access, material order and delivery and other initial tasks with the remainder for construction and testing. Both Phase 1 and the kitchen have the 4 weeks for startup included. These are concurrent but may apply to either if scheduling has one starting before the other.
Overall the performance period is 31-38 weeks if the kitchen is done concurrently with the other Phases.
Long Lead Items:
Air Handling Units 8 – 12 Weeks
Exhaust Fans 4 – 6 Weeks