Attachment 3 Rpr AHU's O-Club B462 Sept 2010.doc
DOC document 48 KB Posted
- Attached to
- Saber Pre-solicitation notice Federal contract opportunity
- Solicitation number
- FA4600-10-R-0006
About this file
Attachment 3
View the file
Other files for this federal contract opportunity
Show all 50
Saber Pre-solicitation notice has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Objectives
Date: 23 Sep 2010 Project #: Seed 10-0018
Project Title: Rpr AHU’s O-Club B462 Provide a proposal to repair AHU’s in the O-Club B462.
Please provide items listed below in Phase I and Phase II for technical review.
Phase I:
a. Detailed Statement of Work
b. List of UPB Line items (minus costs & quantities) and list of Non pre-priced items.
c. AutoCad drawings based on changes listed below.
Phase II:
a. Detailed Cost Estimate
b. Period of Performance
Objectives:
1. Drawings and specifications serve as SOO for this project with following changes listed below by sheet. Please update drawings accordingly.
2. Sheet 1 – Update Drawing index as required
3. Sheet 2 – No changes
4. Sheet 3 – Corridor between grid S7 and P11 not included in project, Kitchen area between L5 and H9 not included
5. Sheet 4 – Not Used (Omit from design)
6. Sheet 5 – Corridor between grid S7 and P11 not included in project, Kitchen area between L5 and H9 not included
7. Sheet 6 – Not Used (Omit from design)
8. Sheet 7 – No changes
9. Sheet 8 – Ductwork shown to be demoed starting in corridor between S7 and P11 is to remain
10. Sheet 9 – New ductwork and supporting services not required between grid L5 and J10 due to ductwork not being removed as shown on Sheet 8. Note 20 at F8 to be removed. Mechanical Key Note “6” to be removed.
11. Sheet 10 – Not Used (Omit from design)
12. Sheet 11, 12, and 13 – No changes
13. Sheet 14 – Detail 2 (AHU-8 and MU-1 not to be demoed), Detail 3 (MAU-1 not to be installed) Update details accordingly
14. Sheet 15 – No changes
15. Sheet 16 – MAU-1 not in design, remove from Air Handling Unit Schedule
16. Sheet 17 – Kitchen Air System Control Diagram Detail not used
17. Sheet 18 – AHU-8 not demoed at grid S8, and EF-1 and EF-2 not demoed from roof plan
18. Sheet 19 – Keynote “1” at S8, “11” at L7, and “9” at J7 removed from design. Installation of MAU-1, EF-1, and EF-2 not included in design on roof plan.
19. Sheet 20 – MAU-1, EF-1, and EF-2 removed from Panel HK General Requirements:
Project includes, but not limited to the following work elements. The contractor shall furnish all labor, equipment, materials, services and incidentals. No alterations, additions, or deletions shall be made unless by prior approval of the SABER Project Manager and the Contracting Officer. The project is to be designed in accordance with the Base Design Guidelines. Work shall be completed in a neat, substantial and competent manner.
· Item 1: All work will meet the International Building Code, Uniform Plumbing Code, National Electrical Code, NFPA 72 and any other applicable code requirement.
· Item 2: Maintain work site in a clean and orderly manner so that the safest possible site is provided for workers and AF members.
· Item 3: In the event of a conflict between the drawings and the Statement of Work (SOW), the SOW will take precedence.
Kelly J. Korenoski, Civ, USAF