Final 26 24 16 Panelboards.pdf

PDF 56 KB Posted

Attached to
Saber Pre-solicitation notice Federal contract opportunity
Solicitation number
FA4600-10-R-0006
Issued by
Department of the Air Force Air Combat Command

About this file

-

View the file

Other files for this federal contract opportunity

Other files attached to Saber Pre-solicitation notice, newest first.
File Type Posted
SIGN IN SHEET Oct 15 2010.doc DOC document
Seed project Honor guard room.pdf PDF
Amendment6.doc DOC document
Attachment 3 Seed SOO Rpr AHU's O-Club B462 28 Sept 2010.doc DOC document
Amendment5.doc DOC document
Question and Answers 24 Sep 2010.docx DOCX document
Sheet 05.dwf DWF file
Sheet 08.dwf DWF file
Sheet 16.dwf DWF file
Sheet 10.dwf DWF file
Sheet 13.dwf DWF file
amendment4.doc DOC document
Attachment 3 Rpr AHU's O-Club B462 Sept 2010.doc DOC document
Sheet 09.dwf DWF file
Sheet 17.dwf DWF file
Question and Answers.docx DOCX document
amendedsolicitation2.doc DOC document
final 23 05 93 Testing Adjusting and Balancing.pdf PDF
Sheet 10-10.pdf PDF
Performance Period.pdf PDF
final 26 05 33 Raceways.pdf PDF
final 26 05 19 Wires and Cables.pdf PDF
Sheet 2-02.pdf PDF
Final 09 91 00 Painting.pdf PDF
Sheet 3-Sheet 3.pdf PDF
final 07 92 00 Joint Sealers.pdf PDF
Final 05 50 00 Metal Fabrications.pdf PDF
Sheet 11-11.pdf PDF
final 26 05 53 Electrical Identification.pdf PDF
Final 23 38 13 Kitchen Ventilator Hood Systems.pdf PDF
final 23 07 00 HVAC Insulation.pdf PDF
final 23 00 00 General Provisions.pdf PDF
Final 26 05 26 Grounding.pdf PDF
final 23 01 30 HVAC Air-Distribution Cleaning System.pdf PDF
Sheet 19-Sheet 19.pdf PDF
Final 23 05 00 Basic HVAC Materials and Methods.pdf PDF
Sheet 9-9.pdf PDF
Sheet 5-Sheet 5.pdf PDF
Sheet 12-12.pdf PDF
Section 1B AF66 Master Oct 2008.xls XLS spreadsheet
Sheet 16-16.pdf PDF
Sheet 11-11.pdf PDF
Section 1C Master Copy June 2008.pdf PDF
SITE PLAN.dwg DWG drawing
Ntitle.dwg DWG drawing
Rpr Wing XP.dwg DWG drawing
Site Visit Sign In Sheet.pdf PDF
Preconstruction Conference Attachment 4.doc DOC document
Attachment 1.docx DOCX document
Attachment 5.docx DOCX document
Show all 50

Saber Pre-solicitation notice has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OFFUTT AIR FORCE BASE

(092036) 26 24 16-1 (Repair AHU O-Club, B462)

2010 by FEI

SECTION 26 24 16

PANELBOARDS

PART 1 - GENERAL

1.1 SUMMARY

A. Extent of panelboard and enclosure work, including cabinets and cutout boxes is indicated by drawings.

B. Types of panelboards and enclosures in this section include the following:

1. Lighting and appliance panelboards.

C. Refer to other Division 26 Sections for cable/wire, connectors, and electrical raceway work required in conjunction with panelboards and enclosures.

PART 2 - PRODUCTS

2.1 ACCEPTABLE MANUFACTURERS

A. Manufacturers: Subject to compliance with requirements, provide panelboard products of one (1) of the following:

1. General Electric Company.

2. Siemens.

3. Square D Company.

4. Cutler-Hammer.

2.2 PANELBOARDS

A. General: Except as otherwise indicated, provide panelboards, enclosures and auxiliary components, of types, sizes and ratings indicated, which comply with manufacturer's standard materials; design and construction in accordance with published product information; equip with proper number of unit panelboard devices as required for complete installation. Where types, sizes or ratings are not indicated, comply with NEC, UL and established industry standards for those applications indicated.

B. Lighting and Appliance Panelboards: Provide dead-front safety type lighting and appliance panelboards as indicated, with switching and protective devices in quantities, ratings, types and arrangements indicated; with anti-turn solderless pressure type lug connectors approved for copper or aluminum conductors; equip with copper bus bars, full-sized neutral bar where indicated, with bolt-on type heavy-duty, quick-make, quick-break, single-pole or multi-pole circuit- breakers, as indicated, with toggle handles that indicate when tripped. Multipole breakers shall be provided with a common trip.

Provide suitable lugs on neutral bus for each outgoing feeder required; provide bare uninsulated copper grounding bars suitable for bolting to enclosures.

1. Lighting and Appliance Panelboards shall be equivalent to:

480V

Bolt-on

General Electric AD, AE

Siemens S2

(092036) 26 24 16-2 (Repair AHU O-Club, B462)

Square D NF

Cutler-Hammer PRL2, PRL3

2. Breakers in 480-volt panelboards shall be fully rated and shall have an interrupting capacity of not less than 65,000 amperes symmetrical.

C. Load center construction shall not be acceptable.

D. Lighting and Appliance Panelboard Enclosures: Provide galvanized sheet steel cabinet type enclosures, minimum 20-inches wide and 5-3/4-inches deep, code-gage, minimum 16-gage thickness.

Construct with multiple knockouts and wiring gutters. Provide fronts with adjustable trim clamps, and doors with flush metal locks and keys, all panelboard enclosures keyed alike. Equip with interior circuit-directory frame, and card with clear plastic covering. Provide baked gray enamel finish over a rust inhibitor coating. Design enclosures for recessed or surface-mounting as indicated. Provide enclosures which are fabricated by same manufacturer as panelboards, which mate properly with panelboards to be enclosed and are NEMA rated to suit the atmospheric conditions of the equipment surroundings.

1. Furnish six (6) spare keys for each type of panelboard cabinet lock.

E. Panelboard Accessories: Provide panelboard accessories and devices including, but not necessarily limited to circuit-breakers, trip units, etc., as recommended by manufacturer for ratings and applications indicated.

PART 3 - EXECUTION

3.1 INSPECTION

A. Installer must examine areas and conditions under which panelboards and enclosures are to be installed and notify Contractor in writing of conditions detrimental to proper completion of work. Do not proceed with work until unsatisfactory conditions have been corrected in a manner acceptable to

Installer.

3.2 INSTALLATION OF PANELBOARDS

A. General: Install panelboards and enclosures as indicated, in accordance with manufacturer's written instructions, applicable requirements of NEC Standards and NECA's "Standard of Installation", and in compliance with recognized industry practices to ensure that products fulfill requirements.

B. Coordinate installation of panelboards and enclosures with cable and raceway installation work.

C. Tighten connectors and terminals, including screws and bolts, in accordance with equipment manufacturer's published torque tightening values for equipment connectors. Where manufacturer's torquing requirements are not indicated, tighten connectors and terminals to comply with tightening torques specified in UL Standards 486A and B or manufacturer's torque requirements when more stringent.

D. Anchor enclosures firmly to walls and structural surfaces, ensuring that they are permanently and mechanically secure.

E. Provide properly wired electrical connections within enclosures.

(092036) 26 24 16-3 (Repair AHU O-Club, B462)

F. Provide factory panelboard circuit directory cards upon completion of installation work. Circuit directory cards shall be arranged with even numbered circuits separated by group or card from odd numbered circuits. All circuits, including spares and spaces, shall be labeled. All identification shall be at a minimum typewritten. Hand lettering is not acceptable.

G. All wiring within panelboards shall be arranged in a neat and organized manner.

H. Provide engraved plaque, fasten with mechanical fasteners on each panelboard.

3.3 GROUNDING

A. Provide equipment grounding connections for panelboards as required by NEC and other Division 26

Sections. Tighten connections to comply with tightening torques specified in UL Standards 486A and B to assure permanent and effective grounds.

3.4 FIELD QUALITY CONTROL

A. Prior to energization of circuitry, check all accessible connections to manufacturer's tightening torque specifications.

B. Prior to energization of panelboards, check with ground resistance tester phase-to-phase and phase-to-ground insulation resistance levels to ensure requirements are fulfilled.

C. Prior to energization, check panelboards for electrical continuity of circuits and for short-circuits.

D. Subsequent to wire and cable hook-ups, energize panelboards and demonstrate functioning in accordance with requirements. Where necessary, correct malfunctioning units and then retest to demonstrate compliance.

E. After occupancy, measure panelboard loads. Re-connect circuits and balance loads equally across all phases.

END OF SECTION