Attachment_10_-_SEED_Project_WORK_TIME_ANALYSIS.pdf
PDF 176 KB Posted
- Attached to
- Simplified Acquisition Base Engineer Requirements (SABER) IDIQ Federal contract opportunity
- Solicitation number
- FA441719RA002
About this file
This document provides a work time analysis for a project to replace condensing units at three buildings at Hurlburt Field, Florida. The analysis estimates the calendar days required to complete six tasks associated with the project: mobilization, submittals/approval, securing materials/equipment, performing all work, correcting punch list items, and other testing/authorization. The total estimated calendar time to complete the project is 141 days.
The related federal contract opportunity is a Simplified Acquisition Base Engineer Requirements Indefinite Delivery Indefinite Quantity contract at Hurlburt Field, Florida. The solicitation was issued by the Department of the Air Force Special Operations Command on February 7, 2019.
Attachment 10
View the file
Other files for this federal contract opportunity
Show all 39
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WORKING TIME ANALYSIS
PROJECT: Replace Condensing Units TLF, Bldgs. 90372, 90374 & 90375 ESTIMATOR: Jim Radford, 884-4551
ITEM NO: DESCRIPTION ALLOWABLE CALENDAR DAYS
1. Mobilization 1
2. Make Req'd Submittals/Approval 14
3. Secure Material/Equipment 42
4. Perform All Work 84
5. Correct Punch List ltems 0
6. Other (Testing/Authorization) 0
TOTAL ALLOWABLE CONTRACT TIME 141