19A_-_Cost_Estimate_Breakdown,_VNVP_141207_(10187)_-_Blank.pdf

PDF 257 KB Posted

Attached to
Sheppard/Altus AFB Multiple Award Construction Contract (MACC) - FA3020-18-R-0008
Solicitation number
FA3020-18-R-0008
Issued by

About this file

19A - Sheppard/Altus MACC Cost Estimate Breakdown, VNVP 141207 (PDF)

View the file

Other files

File Type Posted
FA3020-18-R-0008_-_Amend_7.pdf PDF
31_-_Responses_to_Contractor_Questions_Amend_7.pdf PDF
FA3020-18-R-0008_-_Amend_6.pdf PDF
30_-_Responses_to_Contractor_Questions_Amend_6.pdf PDF
FA3020-18-R-0008_-_Amend_5.pdf PDF
29_-_Responses_to_Contractor_Questions_Amend_5.pdf PDF
FA3020-18-R-0008_-_Amend_3.pdf PDF
28_-_Responses_to_Contractor_Questions_Amend_4.pdf PDF
FA3020-18-R-0008_-_Amend_4.pdf PDF
18A_-_Cost_Estimate_Breakdown,_VNVP_141207_(10187)_-_Blank.xlsx XLSX spreadsheet
13A_-Statement_of_Work,_VNVP_141207.pdf PDF
26_-_Site_Visit_Sign_In_Sheets.pdf PDF
25_-_Site_Visit_Informational_Slides.pdf PDF
27_-_Response_to_Contractor_Question_Amend_3.pdf PDF
24_-_Response_to_Contractor_Question_Amend_2.pdf PDF
FA3020-18-R-0008_-_Amend_2.pdf PDF
22_-_Map_from_Missile_Gate_to_Bldg_1662.pdf PDF
FA3020-18-R-0008_Amend_1.pdf PDF
23_-_Map_from_Main_Gate_to_Bldg_1662.pdf PDF
18_-_Cost_Estimate_Breakdown,_VNVP_141207_(10187)_-_Blank.xlsx XLSX spreadsheet
21_-_Sample_Project_Specific_Clauses.pdf PDF
11_-_Disclosure_of_Lobbying_Activities,_SF_LLL.pdf PDF
17_-_List_of_Material_Submittals,_VNVP_141207.pdf PDF
14_-_Drawings,_141207_Rpr_Trng_Fclty_B10187_[24x36_FBPO].dwf DWF file
12_-_Past_and_Present_Performance_Questionnaire_Sheet.pdf PDF
1_-_General_Requirements.pdf PDF
20_-_Blank_Schedule_B,_VNVP_141207.pdf PDF
15_-_Drawings,_141207_Rpr_Trng_Fclty_B10187_[24x36_FBPO].pdf PDF
9_-_WD_-_TX180299_-_Grayson_Building.pdf PDF
10_-_Base_Pass_Form_151.pdf PDF
4_-_WD_-_OK180070_-_Tillman_Building.pdf PDF
8_-_WD_-_TX180085_-_Grayson_Heavy.pdf PDF
5_-_WD_-_TX180012_-_Wichita_Cty_Heavy-Hwy.pdf PDF
19_-_Cost_Estimate_Breakdown,_VNVP_141207_(10187)_-_Blank.pdf PDF
6_-_WD_-_TX180326_-_Wichita_Cty_Bldg.pdf PDF
16_-_List_of_Material_Submittals,_VNVP_141207.xlsx XLSX spreadsheet
13_-Statement_of_Work,_VNVP_141207.pdf PDF
3_-_WD_-_OK180036_-_Tillman_Heavy.pdf PDF
7_-_WD_-_TX180035_-_Grayson_Highway.pdf PDF
2_-_WD_-_OK180018_-_Tillman_Highway.pdf PDF
Sheppard_AFB_MACC_Solicitation_-FA3020-18-R-0008.pdf PDF
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Summary

UNIT

PRICE

TOTAL

MATERIAL

COST

UNIT

PRICE

TOTAL

LABOR COST

UNIT

PRICE

TOTAL

EQUIPMENT

COST

1 General Conditions - See attached breakout -$ 2 Civil - See attached breakout -$ 3 Architectural - See attached breakout -$ 4 Mechanical - See attached breakout -$ 5 Communications - See attached breakout -$ 6 Electrical - See attached breakout -$ 7 -$ 9 Subtotal -$

10 Bond % 11 -$

**The above Line items are only recommendations and should be added and deleted as needed**

Sub-Total General Contractor Overhead & Profit @ %

Total

CONSTRUCTION COST ESTIMATE DATE:

CONTRACTOR: ADDRESS:

CONTRACT FOR (word to be performed): Repair Tech Training Facility, B10187 PROPOSED TOTAL CONTRACT PRICE: -$

LABOR COST EQUIPMENT COST

OTHER

DIRECT

COSTS

LINE TOTAL

PURCHASE REQUEST NUMBER: PROJECT NUMBER: VNVP 141207 WORK LOCATION: Sheppard AFB, TX

LINE NO. Summary UNIT OF

MEASURE QUANTITY

MATERIAL COST

General Conditions

UNIT PRICE

TOTAL

MATERIAL

COST

UNIT PRICE TOTAL

LABOR COST

UNIT

PRICE

TOTAL

EQUIPMENT

COST

1 Mobilization/demobilization LOT -$ -$ -$ -$

2 30 CY dumpster weekly rental (7 Ton), 1 dump per week WK -$ -$ -$ -$

3 Dump charges TON -$ -$ -$ -$ 4 Cleanup (daily and final) LOT -$ -$ -$ -$ 5 Temporary Sanitation WK -$ -$ -$ -$ 6 Project Manager Week -$ -$ -$ -$ 7 Superintendent Week -$ -$ -$ -$ 8 General Conditions Sub-Total -$

**The above Line items are only recommendations and should be added and deleted as needed**

CONSTRUCTION COST ESTIMATE DATE:

CONTRACTOR: ADDRESS:

CONTRACT FOR (word to be performed): Repair Tech Training Facility, B10187 PROPOSED TOTAL CONTRACT PRICE:

OTHER

DIRECT

COSTS

LINE TOTAL

PURCHASE REQUEST NUMBER: PROJECT NUMBER: VNVP 141207 WORK LOCATION: Sheppard AFB, TX

LINE NO. General Conditions UNIT OF

MATERIAL COST LABOR COST EQUIPMENT COST

Civil

TOTAL

MATERIAL

COST

UNIT PRICE TOTAL LABOR

COST UNIT PRICE

TOTAL

EQUIPMENT

COST

1 Clean, remove and dispose fuel tank complete LS -$ -$ -$ -$

2 Demo and dispose concrete rentention structure complete. LS -$ -$ -$ -$

3 Remove HDPE liner beneath concrete and test for hydrocarbons LS -$ -$ -$ -$

4 Remove fence posts and concrete footings LS -$ -$ -$ -$

5 Demo and dispose building CF -$ -$ -$ -$ 6 Remove weeds and vegitation SF -$ -$ -$ -$ 7 Remove fence, gate and posts LS -$ -$ -$ -$ 8 Demo and dispose concrete slabs SF -$ -$ -$ -$ 9 Testing LOT -$ -$ -$ -$

10 Surveying LS -$ -$ -$ -$ 11 New reinforced concrete pads LS -$ -$ -$ -$ 12 Backfill & grade concrete demo SF -$ -$ -$ -$ 13 Grade gravel SF -$ -$ -$ -$ 14 Plug site conduit LS -$ -$ -$ -$ 15 New gates complete LS -$ -$ -$ -$ 16 New fence posts in concrete LS -$ -$ -$ -$ 17 Install salvaged chain link fabric LS -$ -$ -$ -$ 18 New barbed wire assembly LS -$ -$ -$ -$ 19 New corner post fence assembly LS -$ -$ -$ -$ 20 Subtotal -$ 21 Prime Contractor Overhead % 22 Subtotal -$ 23 Prime Contractor Profit % 24 Subtotal -$ 25 Bond % 26 Total -$

**The above Line items are only recommendations and should be added and deleted as needed**

CONSTRUCTION COST ESTIMATE DATE:

CONTRACTOR: ADDRESS:

CONTRACT FOR (word to be performed): Repair Tech Training Facility, B10187 PROPOSED TOTAL CONTRACT PRICE:

OTHER

DIRECT COSTS LINE TOTAL

PURCHASE REQUEST NUMBER: PROJECT NUMBER: VNVP 141207 WORK LOCATION: Sheppard AFB, TX

LINE NO. CIVIL UNIT OF

MATERIAL COST LABOR COST EQUIPMENT COST

Architectural

TOTAL

MATERIAL

COST

UNIT PRICE TOTAL LABOR

COST UNIT PRICE

TOTAL

EQUIPMENT

COST

1 Remove existing VCT floor tile, clean and prep floor. SF -$ -$ -$ -$

Pre-engineered steel trusses with 24 ga standing seam metal roof, misc. roof structure and trim

LS -$ -$ -$ -$

3 Scarify concrete and apply bonding agent for new curb SF -$ -$ -$ -$

4 Drill reinforced concrete slab up to 6" thick EA -$ -$ -$ -$

5 1/2" diam. concrete chemical anchors EA -$ -$ -$ 6 Reinforced concrete curb LF -$ -$ -$ -$

7 16 ga 3 5/8" Metal studs, 16" o.c. plus misc framing and sill anchoring LF -$ -$ -$ -$

8 R-13 un-faced batt insulation SF -$ -$ -$ -$ 9 R38 craft faced batt insulation SF -$ -$ -$ -$

10 5/8" thick gyp bd, with tape & bed and level 5 skim coat SF -$ -$ -$ -$

Paint walls complete including surface prep, primer and 2 coats of paint on drywall with roller

SF -$ -$ -$ -$

12 Add 10% for light texture % -$ -$ -$ -$ 13 VCT 12"x12", 1/8" Thick Marbleized SF -$ -$ -$ -$

14 Resiliant Base, Rubber or Vinyl 4" high LF -$ -$ -$ -$

15 Gyp sheathing SF -$ -$ -$ -$ 16 Modular brick veneer SF -$ -$ -$ -$ 17 Rowlock LF -$ -$ -$ -$ 18 Brick ties EA -$ -$ -$ -$ 19 1/2" AC Grade Plywood SF -$ -$ -$ -$ 20 1" Drainable PM class EIFS SF -$ -$ -$ -$ 21 Heavy duty mesh reinf. Add SF -$ -$ -$ -$ 22 EIFS Control Joint LF -$ -$ -$ -$ 23 Spray applied moisture barrier SF -$ -$ -$ -$ 24 Flashing SF -$ -$ -$ -$ 25 Sealant LF -$ -$ -$ -$ 26 3ft x 7ft HM door frame EA -$ -$ -$ -$ 27 3ft x 7ft HM doors EA -$ -$ -$ -$ 28 Door Hardware Set -$ -$ -$ -$

CONSTRUCTION COST ESTIMATE DATE:

CONTRACTOR: ADDRESS:

CONTRACT FOR (word to be performed): Repair Tech Training Facility, B10187 PROPOSED TOTAL CONTRACT PRICE:

PURCHASE REQUEST NUMBER: PROJECT NUMBER: VNVP 141207 WORK LOCATION: Sheppard AFB, TX

LINE NO. ARCHITECTURAL UNIT OF

MEASURE QUANTITY

MATERIAL COST LABOR COST EQUIPMENT COST

OTHER

DIRECT COSTS LINE TOTAL

Architectural

29 Paint new HM door, flush both sides including frame LS -$ -$ -$ -$

30 Paint plywood SF -$ -$ -$ -$ 31 Gutter, eave type, 26 ga, prefinished LF -$ -$ -$ -$ 32 Downspouts LF -$ -$ -$ -$ 33 Concrete splash blocks EA -$ -$ -$ 34 Aluminum building number sign EA -$ -$ -$ -$

35 3x6 anod. aluminum window with Low-E glass EA -$ -$ -$ -$

36 3x4 anod. aluminum window with Low-E glass EA -$ -$ -$ -$

37 New suspended gyp bd ceiling assembly SF -$ -$ -$ -$

38 Tape, bed ceiling gyp bd walls with level 5 skim coat SF -$ -$ -$ -$

39 New ceiling access door EA -$ -$ -$ -$

Paint ceilings complete including surface prep, primer and 2 coats of paint on drywall with roller

SF -$ -$ -$ -$

41 Add 10% for light texture % -$ -$ -$ -$ 42 Subtotal -$ 43 Prime Contractor Overhead % 44 Subtotal -$ 45 Prime Contractor Profit % 46 Subtotal -$ 47 Bond % 48 Total -$

**The above Line items are only recommendations and should be added and deleted as needed**

Mechanical

TOTAL

MATERIAL

COST

UNIT PRICE TOTAL LABOR

COST UNIT PRICE

TOTAL

EQUIPMENT

COST

1 Install Ductless HVAC System EA -$ -$ -$ -$ 2 Install Exhaust Fan EA -$ -$ -$ -$ 3 Install Exhaust Fan Chimney EA -$ -$ -$ -$ 4 Install Return Air Grill w/filter EA -$ -$ -$ -$ 5 -$ -$ -$ -$ 6 -$ -$ -$ -$ 7 -$ -$ -$ -$ 8 -$ -$ -$ -$ 9 -$ -$ -$ -$

10 -$ -$ -$ -$ 11 -$ -$ -$ -$ 12 -$ -$ -$ -$ 13 -$ -$ -$ -$ 14 -$ -$ -$ -$ 15 Prime Contractor Overhead % -$ 16 Prime Contractor Profit % -$ 17 Bond % -$ 18 Total -$

**The above Line items are only recommendations and should be added and deleted as needed**

CONSTRUCTION COST ESTIMATE DATE:

CONTRACTOR: ADDRESS:

CONTRACT FOR (word to be performed): Repair Training Facility, B10187 PROPOSED TOTAL CONTRACT PRICE:

PURCHASE REQUEST NUMBER: PROJECT NUMBER: VNVP 141207 WORK LOCATION: Sheppard AFB, TX

LINE NO. MECHANICAL UNIT OF

MEASURE QUANTITY

MATERIAL COST LABOR COST EQUIPMENT COST

OTHER

DIRECT COSTS LINE TOTAL

Communications

TOTAL

MATERIAL

COST

UNIT PRICE TOTAL LABOR

COST UNIT PRICE

TOTAL

EQUIPMENT

COST

1 Data/Voice Drops LS -$ -$ -$ -$ 2 Directional Boring LF -$ -$ -$ -$ 3 New Hand Holes LS -$ -$ -$ -$

Wall Mount Cabinet LS -$ -$ -$ -$ 4 Labeling LS -$ -$ -$ -$ 5 Major Splices LS -$ -$ -$ -$ 6 SMFO Cable LF -$ -$ -$ -$ 7 Georextile Inner Duct (Maxcell) LF -$ -$ -$ -$ 8 Conduit LF -$ -$ -$ -$ 9 Trenching /Backfill LF -$ -$ -$ -$ 10 Testing LS -$ -$ -$ -$

11 Mic Materials (patch pannels, FO pannels) LS -$ -$ -$ -$

12 Subtotal -$ 13 Prime Contractor Overhead % 14 Subtotal -$ 15 Prime Contractor Profit % 16 Subtotal -$ 17 Bond % 18 Total -$

**The above Line items are only recommendations and should be added and deleted as needed**

CONSTRUCTION COST ESTIMATE DATE:

CONTRACTOR: ADDRESS:

CONTRACT FOR: Repair Tech Training Facility, B10187 PROPOSED TOTAL CONTRACT PRICE:

PURCHASE REQUEST NUMBER: PROJECT NUMBER: VNVP 141207 WORK LOCATION: Sheppard AFB, TX

LINE NO. COMMUNICATIONS UNIT OF

MEASURE QUANTITY

MATERIAL COST LABOR COST EQUIPMENT COST

OTHER

DIRECT

COSTS

LINE TOTAL

Electrical

TOTAL

MATERIAL

COST

UNIT PRICE TOTAL LABOR

COST UNIT PRICE

TOTAL

EQUIPMENT

COST

1 Electrical demolition & cleanup LS -$ -$ -$ -$

2 Electrical panelboards, complete install. (incl. main & branch CBs for active exterior circuit reconnections ) EA -$ -$ -$ -$

3 Electrical racks EA -$ -$ -$ -$ 4 SE & exterior circuit mods (incl. any trenching, excavation, backfilling, etc.) LS -$ -$ -$ -$ 5 Ground rods, cadwelds, etc. LS -$ -$ -$ -$ 6 All new 20A, 120V receptacles, complete install. EA -$ -$ -$ -$ 7 LED fixtures, interior EA -$ -$ -$ -$ 8 LED fixtures, exterior EA -$ -$ -$ -$ 9 New occupancy sensors EA -$ -$ -$ -$ 10 New wall switch+dimmers EA -$ -$ -$ -$ 11 New wall switches EA -$ -$ -$ -$ 12 Structural support (outlet boxes, hangers, etc.) SF -$ -$ -$ -$ 13 Lighting wiring (conduit, conductors, etc.) SF -$ -$ -$ -$ 14 HVAC unit installation, complete (including wires, conduits, etc.) EA -$ -$ -$ -$ 15 LV testing, complete LS -$ -$ -$ -$ 16 Labeling, complete LS -$ -$ -$ -$ 17 Superintendent LS -$ -$ -$ -$ 18 Contractor Overhead % -$ 19 Contractor Profit % -$ 20 Bond % -$

21 Totals -$ -$ -$ -$

**The above Line items are only recommendations and should be added and deleted as needed**

CONSTRUCTION COST ESTIMATE DATE:

CONTRACTOR: ADDRESS:

CONTRACT FOR: Repair Tech Training Facility, B10187 PROPOSED TOTAL CONTRACT PRICE:

PURCHASE REQUEST NUMBER: PROJECT NUMBER: VNVP 141207 WORK LOCATION: Sheppard AFB, TX

LINE NO. ELECTRICAL UNIT OF

MEASURE QUANTITY

MATERIAL COST LABOR COST EQUIPMENT COST

OTHER

DIRECT

COSTS

LINE TOTAL

File details come from the government source that posted it.