This is a pre-solicitation notice for an indefinite delivery indefinite quantity contract to provide simplified acquisition of base engineering requirements services at Joint Base Andrews and Joint Base Anacostia Bolling. The Air Force District of Washington plans to issue a solicitation on or around January 27, 2020 seeking a contractor to provide design, management, and completion of construction projects such as carpentry, road repairs, roofing, excavation, electrical, plumbing, and other tasks. The contract will have a five-year base period and two one-year options, with a minimum guaranteed award amount of $2,000. Evaluation criteria will include technical acceptability, past performance, and price/coefficients. The contract has a magnitude between $100-250 million and is an 8(a) competitive small business set-aside for firms in the Mid-Atlantic region. Interested offerors must show bonding capability up to $1 million single project and $30 million in aggregate and register in SAM. A pre-performance conference will be held at Joint Base Andrews upon award. Task order periods may range from 30-365 days, and liquidated damages may apply.
View the file
Other files
Show all 42
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW)
SIMPLIFIED ACQUISITION OF BASE ENGINEERING REQUIREMENTS (SABER)
Joint Base Andrews and Joint Base Anacostia Bolling 16 Jan 2020
ATTACHMENT 14
TABLE OF CONTENTS
1. SCOPE OF WORK 3
1.1. Ordering Procedures 3
1.2. Contractor Coefficient 3
1.3. Applicable Codes, Regulations and Standards 3
1.4. Work Types 5
1.5. Government Furnished Facilities/Utilities 5
2. CONTRACTOR PERSONNEL/PROGRAMS/EQUIPMENT MATERIALS 8
2.1. Personnel 8
2.2. Programs 11
2.3. Equipment, Materials and Training Services 13
3. COMMENCEMENT OF WORK 14
3.1. Project Requirement Types 15
3.2. Commencement Documents 15
3.3. Design Guidance 19
3.4. Design Analysis 28
4. PROSECUTION OF WORK 30
4.1. Liquidated Damages 30
4.2. Prosecution Documents 30
4.3. Hours of Operation 34
4.4. Order of Work 34
4.5. Worksite Standards 35
4.6. Worksite Procedures 41
4.7. Affirmative Procurement 50
5. COMPLETION OF WORK 51
5.1. Final/Beneficial Occupancy Inspections 51
5.2. Completion Documentation 52
5.3. Equipment Training 53
6. SPECIAL PROJECT PROCEDURES ON JBA 54
6.1. Special Provisions for Working on or Near Airfield 54
6.2. Definitions 55
7. Service Delivery Summary 56 Technical Exhibit 1 58 Technical Exhibit 2 64 Technical Exhibit 3 65 Technical Exhibit 4 67 Technical Exhibit 5 69 Technical Exhibit 6 70 Technical Exhibit 7 75 Technical Exhibit 8 78 Technical Exhibit 9 98 Technical Exhibit 10 105 Technical Exhibit 11 117 Technical Exhibit 12 124 Technical Exhibit 13 144 Technical Exhibit 14 152
SCOPE OF WORK. The Simplified Acquisition of Base Engineer Requirements (SABER) contract is to provide a broad range of maintenance, repair, and minor construction work on real property at Joint Base Andrews (JBA) and its mission partner sites Davidsonville, Brandywine and AF Memorial and Joint Base Anacostia Bolling (JBAB) and its tenants. The contractor shall provide all facilities, material, labor, equipment, environmental controls, transportation and supervision necessary to perform the SABER program requirements.
The primary goal of the Civil Engineering Squadrons at JBA and JBAB is swift acquisition of engineering requirements where Contractor responsiveness is paramount. The contractor shall be required to maintain a management office on JBA to perform all general management operations associated with this contract. In accordance with FAR 52.219-14, Limitations on Subcontracting, the prime contractor shall perform at least 15 percent of the cost of the contract with its own employees. If performing construction by special trade contractor work, the prime contractor shall perform at least 25 percent of the cost of the contract with its own employees. In both instances, the cost of work performed shall not include additional material costs not included in RS Means. All project time and schedules for this contract are calculated and represented as calendar days. [NOTE: the attached Technical Exhibits (TE’s) are mandatory and considered part of this Scope of Work].
1.1. .ORDERING PROCEDURES: The Procuring Contracting Officer (PCO) resides at JBA and both
JBA and JBAB will have contracting officers, who reside in each bases respective contracting squadrons, who will execute task orders (TO’s) against this contract and they will be referred to as Task Order Contracting Officers (TO CO’s). During the contract period, the Government will identify required construction projects. Once the TO CO notifies the Contractor of an existing requirement, the Contractor shall expeditiously prepare a proposal within 10 calendar days. TO’s will include projects from up to 35% design through construction completion. TO’s will include, but are not limited to, minor construction, and interior/exterior remodeling, renovation, and repairs. Project disciplines may include, but not be limited to, one or more of the following: structural, architectural, mechanical, plumbing, communications, intrusion/detection, audio/visual systems, and electrical disciplines, petroleum/oil/lubricants systems, asphalt and concrete pavements, masonry, various roofing systems, earthworks and landscaping, aerial and underground utilities, power and heat generation. Each base will administer and provide oversight of their respective projects and TO’s. Before implementing any change that will result in an increase/decrease in contract price, the contractor shall submit to the TO CO a price proposal within 10 calendar days following receipt of the change by the contractor. The TO CO and the contractor shall negotiate the change into the TO under the provisions of FAR 52.243-4;
“Changes”. Failure of the contractor to submit a price proposal within 30 calendar days following receipt of the change, entitles the Government to performance according to such change performance according to such change at no increase in contract TO price (unless the time requirement is waived by the Contracting Officer TO CO according to paragraph (e) of the changes clause).
1.2. CONTRACTOR COEFFICIENT. In each TO, the contractor shall provide to the Government certain labor, equipment, materials, and rentals/fees that are considered field overhead and therefore part of the contractor’s coefficient. Those requirements/responsibilities are identified throughout this SOW.
(NOTE: Where notification of a coefficient requirement/responsibility is stated, all associated sub-paragraphs are also applicable as part of the coefficient. Other coefficient statements may be found in these sub-paragraphs referring to additional requirement/ responsibilities.)
1.3. APPLICABLE CODES, REGULATIONS AND STANDARDS. All work under this contract shall comply with the most current local, state, and federal regulations, to include any subsequent updates as they occur. The Codes, Regulations and Standards listed in TE 4 - APPLICABLE CODES, REGULATIONS AND STANDARDS are not all inclusive and do not relieve the Contractor from compliance with any unlisted Code, Regulation, or Standard required under law to perform work on JBA Supplements and/or amendments to listed publications may be issued during the life of the contract. The contractor shall be responsible for obtaining current changes to the publications. These codes shall be followed for all designs, construction, and materials under this contract. If there is a conflict between the codes and/or regulations and this contract, the most stringent requirements shall govern at all times. The Contractor shall maintain a copy of each of these documents available for use during the term of this contract.
1.3.1. STANDARDS. The publications listed below form a part of this SOW to the extent referenced (publications are referred to in the text by basic designation only):
1.3.1.1. CODE OF FEDERAL REGULATIONS (CFR). Occupation, Safety and Health
Administration (OSHA) General Industry Safety and Health Standards (29 CFR 1910), Publication V2206, OSHA Construction Industry Standards (29 CFR 1926). One source of these regulations is OSHA Publication 2207, which includes a combination of both 1910 and 1926 as they relate to construction safety and health. They are for sale by the Superintendent of Documents, U.S. Government Internet site:
www.access.gpo.gov/nara/cfrcfr-retrieve.html
1.3.1.2. FEDERAL STANDARD (FED. STD.).
1.3.1.2.1. FEDERAL STANDARD 313, MATERIAL SAFETY DATA SHEET
(MSDS). For each TO issued against this contract, the Contractor shall for all required MSDSs, prepare and submit one copy to Hazardous Materials (HAZMAT Pharmacy) and three copies to the TO CO IAW the Safety and Health Requirements Manual, EM 385-1-1.
1.3.1.2.2. ASBESTOS CONTAINING MATERIALS / CLASS 1 OZONE
DEPLETING CHEMICAL COMPOUNDS. Use of asbestos containing materials or any Class 1 ozone depleting chemical compounds is prohibited.
1.3.1.2.3. DEFINITION OF HAZARDOUS MATERIALS. Refer to hazardous and toxic materials/substances included in Subparts H and Z of 29 CFR 1910 and to others as additionally defined in Fed. Std. 313. Those most commonly encountered include asbestos, lead-based paint, polychlorinated biphenyls (PCBs), explosives and radioactive material, but may include others. The most likely products to contain asbestos are sprayed-on fireproofing, insulation, boiler lagging, pipe coverings, and vinyl floor tile and/or its associated mastic.
1.3.1.3. CORPS OF ENGINEERS MANUAL, EM 385-1-1, SAFETY AND HEALTH
REQUIREMENTS MANUAL. The Contractor shall comply with all pertinent provisions of the most current version of the Corps of Engineers Manual, EM 385-1-1, Safety and Health Requirements Manual. The Contractor shall provide copies to the Government IAW paragraph 2.3.2.3.4. The Contractor, as well as all subcontractors, is responsible for compliance with the provisions of this manual.
1.3.2. ACRONYMS. A list of acronyms is provided in TE 3 - LIST OF ACRONYMS.
http://www.access.gpo.gov/nara/cfrcfr-retrieve.html
1.4. WORK TYPES.
1.4.1. STANDARD HOURS. Defined as the period from 7:00 a.m. to 5:00 p.m. (0700 hrs. to
1700 hrs.), Monday through Friday, excluding Federal holidays. All work shall be performed during this period unless otherwise authorized and approved by the TO CO.
Access to work sites may be restricted during this period due to mission requirements or unless otherwise specified in the TO. Due to the sensitivity and varied operations on base, the TO CO may impose quiet hours during special functions. Any “quiet hours” that result in delay of work as determined by the TO CO and in accordance with FAR 52.242-14, shall be reviewed and handled on a case-by-case basis.
1.4.2. NON-STANDARD HOURS. Defined as any period outside of Standard Work. Only work specified by the TO CO, prior to issuance of a TO, or subsequent modification that identifies work requiring non-standard work hours, shall be multiplied by the non-standard coefficient. In the event that non- standard hours were not included in the original TO or any subsequent modifications and work is deemed necessary during these hours, the contractor shall submit a written request for approval to the TO CO at least five workdays in advance.
No work shall commence nor will the TO be modified to include the non- standard coefficient until approval has been received from the TO CO.
1.4.3. SECURE AREAS. Defined as any work performed in an area with restricted access. Areas include, but are not limited to, JBA flight line area. Secure areas on JBAB will be identified after contract award. Only work specified by the TO CO, prior to issuance of a TO, or subsequent modification that identifies work in a secure area, shall be multiplied by the secure area coefficient. In the event that secure area coefficients were not included in the original TO or any subsequent modifications and work is deemed necessary in these areas, the contractor shall submit a written request for approval to the TO CO at least five workdays in advance. No work shall commence nor will the TO be modified to include the secure area coefficient until approval has been received from the TO CO.
1.5. GOVERNMENT FURNISHED FACILITIES/UTILITIES.
1.5.1. OFFICE FACILITIES
1.5.1.1.OFFICE FACILITIES ON JBA. The contractor will be provided space at an on-base location to conduct their activities supporting this contract. The contractor will be required to provide a mobile office trailer as a base of operations for the management of the requirements. The Government currently provides a fenced storage area for SABER and other civil engineering functions. The area includes a 40’ x 40’ reserved space for the SABER contractor’s mobile office trailer. The Government reserves the right, to require the contractor to relocate to another on-base location one time during the contract performance at contractor expense. Potable water and sanitary sewer service is currently available at this site. The contractor is responsible for the connection and removal of all temporary utility connections. All equipment/materials/supplies required to administrate this contract shall be at the contractor’s expense. All Government provided facilities shall be utilized only for the purpose of this contract, or as authorized by the PCO. The contractor shall perform housekeeping of the facilities to include, but not limited to sweeping, mopping, dusting, waste disposal, grass cutting, weed control, snow/ice removal and other operations necessary to present a neat appearance at all times, or as otherwise directed by the PCO. The contractor shall anchor the building securely and install appropriate skirting, provide safe and proper entrances and exits, and ensure the building conforms to the Americans with Disabilities Act (ADA, Title III, Public Accommodations). In the event of a fire or any damage to the building, the contractor shall notify the Base Civil Engineer Squadron immediately. The contractor is responsible for insuring his/her own contents. The government shall not be liable for any loss or damage to the contractor’s property, including stock, or for expenses incidental to such loss or damage. All labor, equipment, materials and rentals/fees required to perform all housekeeping, vegetation maintenance, and snow/ice removal shall be at no additional cost to the Government and is considered field overhead; therefore part of the Contractor’s coefficient.
1.5.1.2. OFFICE FACILITIES ON JBAB. TBD after contract award.
1.5.2. PERMANENT STORAGE AREA
1.5.2.1. PERMANENT STORAGE AREA ON JBA. The government will provide a lot 120 feet by 75 feet on JBA for the contractor to use for open storage. The contractor shall enclose the area with an 8-foot high security fence (Attleboro, brown, metal fence) matching the base architectural standards. The contractor shall maintain the fence in a serviceable condition at all times and keep the fence line clear of weeds and trash. The contractor shall keep the storage area neat, orderly, and clear of all debris. Also, the contractor shall not allow trash or other debris to scatter from this area by wind or other means. The contractor shall not store any item or material in this area that is not directly related to the contractor’s operations under the terms of this contract. The storage area is subject to no notice base environmental, and/or state inspections for proper storage of Hazardous Materials. The area is also subject to inspection by the SABER inspector, the base fire department and the safety office for general housekeeping and fire/safety hazards. The contractor shall correct all written violations identified through these inspections within 48 hours of receipt of their findings. The contractor is responsible for any fines or penalties imposed by the state for violations resulting from these inspections.
Upon completion of this contract, the contractor shall clean the open storage area and ensure it is free of any trash or debris prior to release of final payment. Any modifications/improvements to the area shall remain the property of the government. In the event of a fire or any damage to this area, the contractor shall immediately notify the Base Civil Engineer Squadron. Security shall be the responsibility of the contractor as well as responsibility for insuring his/her own contents. The government shall not be liable for any loss or damage to the contractor’s property, including stock, or for expenses incidental to such loss or damage. The contractor shall maintain the Permanent Storage Area IAW paragraph 4.5 and restore the area IAW paragraph 4.6.8. prior to the end of the contract period, or as directed by the PCO.
1.5.2.2. PERMANENT STORAGE AREA ON JBAB. TBD after contract award.
1.5.3. CONTRACTOR IDENTIFICAION SIGNS. The contractor may erect a sign for his/her office and/or storage area(s). The sign(s) shall be in compliance with base requirements and color scheme and approved by the respective Base Civil Engineer before being erected.
1.5.4. GOVERNMENT FURNISHED SERVICES.
1.5.4.1. UTILITIES AT CONTRACTOR’s OFFICE SPACE. The government will furnish utility services IAW para. 1.4. The contractor shall provide gas and electrical meters connected to the modular building or trailer for the purpose of reimbursing the government for the quantities consumed by the contractor. Utility services shall be charged to the contractor at the Non-federal reimbursable rate IAW AFI 32-1061, Providing Utilities to US Air Force Installations.
1.5.4.2. UTILITIES AT JOB SITES. If available, the government will also provide utilities (electricity and water) at any construction site. Utility services furnished to the contractor by the government from the government’s existing system outlets and supplies will be at no cost to the contractor. When required, the government will furnish the contractor water from a fire hydrant designated by the TO CO, with the coordination of the respective base fire department. The contractor shall provide and install a gate valve and provide a hydrant wrench. The contractor shall be liable for any damage caused to government property resulting from improper operation of the fire hydrant(s).
The government will not provide utilities at the contractor’s open storage area.
1.5.4.3. INSECT AND RODENT CONTROL. The government will provide insect and rodent control for all government-furnished facilities. When the contractor detects an insect or rodent problem, he/she shall notify the appropriate facility inspector for entomology services. The contractor will provide insect and rodent control for all contractor facilities and construction sites.
1.5.4.4. SECURITY POLICE AND FIRE PROTECTION. The government will provide security police and fire protection to the extent necessary to ensure a secure and safe installation. In return for these services, the contractor shall adhere to the security and fire directives, instructions, and policies for each base.
1.5.4.5. EMERGENCY USE OF AIR FORCE MEDICAL FACILITY. The Malcolm Grow Military Treatment Facility on JBA will provide only life-threatening emergency medical treatment to employees of the Contractor for injuries incurred while working on the installation. The Contractor shall reimburse the USAF for treatment provided at the current reimbursement rate for non-beneficiaries IAW AFR 168-7. The Contractor shall provide the USAF with the name of a physician and/or hospital to which injured personnel can be transferred for further treatment and care after receiving initial emergency treatment. Thereafter, the employee’s physician shall provide all follow-on care at no cost to the government. The government will provide ambulance and emergency medical services on a cost reimbursable basis. At present, it is unknown what services may or may not be provided at JBAB. This will be determined and revised after contract award.
1.5.5. CONTRACTOR FURNISHED SERVICES.
1.5.5.1. TELEPHONE SERVICES. The government will not provide telephone service to the contractor. All communications equipment, connections, and services shall be at the contractor’s expense.
1.5.5.2. REFUSE COLLECTION. The contractor will provide refuse collection services for their assigned contractor facilities. The contractor is responsible for disposing of construction debris and contractor-generated refuse from construction sites safely and IAW JBA and JBAB policy.
1.5.5.3. GROUNDS MAINTENANCE. The contractor will provide al grounds maintenance in the space provided for the contractor’s office facilities. This will include at a minimum maintaining the grass between 2” and 4” in height.
2. CONTRACTOR PERSONNEL/PROGRAMS/EQUIPMENT MATERIALS. The Contractor shall not employ persons for work on this contract if such employee is identified by the PCO as a potential threat to the health, safety, security, general well-being, or operational mission of the installation and its population.
Where reading, understanding, and discussing safety and environmental warnings are an integral part of a contract employee’s duties, that contract employee shall be able to comprehend and communicate (read/write/speak) the English language. Speaking skills are not required in the event that a Contractor employee is hearing impaired.
2.1. PERSONNEL.
2.1.1. PROGRAM MANAGER (PM). The Contractor shall provide at minimum, one qualified full-time PM who will be responsible for the performance of all aspects of the work performed under this contract. The PM must hold a Degree and have a minimum of 5+ years of construction management experience. Roles and responsibilities include, overseeing the development and execution of large projects, called programs. Program Managers also act as a liaison between the individuals working on the program and key stakeholders. The PM shall be located on JBA. An alternate shall be identified for use when the PM is not available due to scheduled or unscheduled absence. Under no circumstance will a designated full-time PM be assigned as an alternate PM at another location. The Contractor shall submit a detailed resume for the PMs and alternate(s) to the PCO for approval prior to assumption of duties. Any subsequent replacement of the PM shall follow the same procedures as stated above. The PM and designated alternate(s) shall have a minimum of 5 years’ experience with programs of similar size and scope for the base they are being recommended for. The name of the PM and alternate(s) shall be designated in writing to the PCO prior to the Pre-Performance Conference (PPC). The PM and alternate(s) must be able to comprehend and communicate (read/write/speak) the English language.
2.1.1.1. AVAILABILTY. The PM shall be directly available to the PCO and/or TO CO, as applicable, and/or the Civil Engineering SABER CHIEF (SC) during standard hours, as defined in para. 1.3.1., to meet and discuss contract issues. During non-standard hours, as defined in para 1.3.2., the PM shall be available within 4 hours to meet on JBA or JBAB with Government personnel (as authorized by the PCO) to discuss contract issues.
2.1.1.2. AUTHORITY. The PM (or alternate(s) in the absence of the PM) shall have full authority to act for the Contractor on all matters relating to daily operation of this contract. The PM shall have the authority to obligate the company in any aspect of this contract regarding negotiations and TO’s as a minimum and shall have the authority to hire subcontractors as required.
2.1.2. PROGRAM MANAGEMENT STAFF (PMS). At a minimum, the PMS shall possess all engineering disciplines and support positions of administration, quality control, safety, Computer Aided Drafting and Design (CADD), field supervision and financial management experience. All personnel performing these functions shall maintain all appropriate and applicable federal, state and local certifications as required.
2.1.2.1. PROJECT STAFF. The Contractor shall designate in writing to the CO, the assigned
Project Manager and Construction Manager for each project and any changes in personnel IAW FAR 52.236-6 “Superintendence by the Contractor”. Project managers must hold a degree, have a minimum of 5+ years of construction experience, and MDE Green Card Training. Project Managers, are responsible for ensuring that every aspect of the program is completed on time and within budget. They are responsible to assign milestones, develop reporting processes and ensure that every team has what they need to complete their project. They will develop and design the project goals and success markers, determine how success will be measured and tracked. Project Managers also act as a liaison between the project team and upper level management. Construction Managers must have a minimum of 5+ years construction experience. Construction Managers are responsible for managing project job sites for both new construction and remodeling task orders. Construction managers oversee construction schedules for construction crew and ensure all projects are fully staffed. Provide temporary laborers to contribute to each project and ensure project supplies, materials, arrive and are correct for the duration of the project. Manage and oversee subcontractors and vendors to ensure quality standards are met, as well as ensure safety guidelines are followed on all job sites. Additionally, provide constant communication with the Government representative and clients through the entire life and end of the project.
2.1.2.2. QUALITY CONTROL MANAGER (QCM). The contractor shall have on staff a minimum of one individual identified as the QCM,. The QCM must be Quality Control Manager Qualified and have MDE Green Card Training. The QCM will be responsible for ensuring their employer's products meet acceptable quality standards. They will perform quality assurance and quality control as needed for all task orders in order make certain that all work is performed efficiently, coordinate employee efforts, and facilitate communications between management as needed. Additionally, they will be responsible to devise ways of improving the project process to ensure we meet the customer and government requirements. and will execute a Quality Control Program IAW paragraph
2.2.1. of the SOW.
2.1.2.3. GOVERNMENT EMPLOYEES. The Contractor shall not employ any person(s) who is an employee of the United States Government, if employing that person would create a conflict of interest, or the appearance of a conflict of interest. Additionally, the Contractor shall not employ any person who is an employee of the Department of the Air Force, either military or civilian, unless such person seeks and receives approval according to DOD 5500.7-R, Joint Ethics Regulations (JER). The Contractor shall not employ any person who is an employee of the Department of the Air Force if such employment would be contrary to the policies in AFI 64-106, Air Force Industrial Labor Relations Activities.
2.1.2.3.1. MILITARY PERSONNEL. The Contractor is cautioned that off-duty active military personnel hired under this contract may be subject to permanent change of station, change in duty hours, or deployment. All active military personnel hired shall have a signed Air Force Form 3902, Off-Duty Employment from their respective JA office authorizing the employment.
Military Reservists and National Guard members may be subject to recall to active duty. The abrupt absence of these personnel could adversely affect the Contractor’s ability to perform; however, their absence at any time shall not constitute an excuse for non-performance under this contract.
2.1.3. SUBCONTRACTORS. The PM and PMS shall have the ability to manage and control multiple subcontractors at multiple work sites. The PM shall provide a completed Statement of Prime Contractor (SF 1413) to the PCO within 14 calendar days after any subcontractor award regardless of tier IAW FAR 52-222-11. All subcontractors shall comply with appearance requirements as stated in paragraph 2.1.5.1.
2.1.4. PROFESSIONAL/TECHNICIAN/CRAFTSMAN QUALIFICATIONS. The PM shall ensure all employees, to include subcontractor employees, have valid licensing/ certifications to accomplish applicable contract requirements before starting work under this contract. They must also be in compliance with all federal, state, and local regulations and environmental requirements or laws, and be qualified, competent, and capable of handling all assigned tasks. The qualifications listed in 2.1.4.1 through 2.1.4.5 are not all inclusive.
2.1.4.1. PROFESSIONAL ENGINEER CERTIFICATION. For designs requiring
Professional Engineer (PE) certification, the PE shall provide documentation to assure that qualifications are met.
2.1.4.2. TECHNICAL COMPETENCE. All Project Managers, Quality Control Managers and Project Superintendents shall have a minimum of five years of experience performing in a function directly related to the required position. All non-professional and/or technician project managers shall have relevant experience in the discipline in which they are functioning.
2.1.4.3. MOTOR VEHICLES. Personnel operating motor vehicles on base roadways must possess a valid driver’s license for the vehicles they operate. Any vehicle driven on base must be registered and insured commensurate with the applicable installations policies.
2.1.4.4. CROSS-CONNECTION/BACK FLOW PREVENTION. District of Columbia and Maryland licenses are required for certified cross-connection and back flow prevention device testing and installation of all anti-siphons or back flow prevention units on all applicable plumbing applications at JBA and JBAB respectively. The Contractor shall make these licenses available for Government inspection, upon request, for each individual that performs this task.
2.1.4.5. HERBICIDES/PESTICIDES. Any personnel that apply herbicides/pesticides shall have a current Commercial DC or Maryland Applicator’s License for JBA and JBAB respectively. Upon request, the Contractor shall make the licenses for each individual that performs this task available for inspection by the Government.
2.1.5. PERSONNEL APPERANCES/IDENTIFICATION
2.1.5.1. APPEARANCE. All Contractor personnel shall present a neat appearance, and shall not wear clothing that depicts any symbol, logo or language deemed racial, lewd or offensive. Contractor personnel shall utilize proper safety equipment/clothing at all times IAW all applicable OSHA standards. All Contractor personnel shall wear proper attire at all times.
2.1.5.2. CONTRACTOR AND SUBCONTRACTOR EMPLOYEE IDENTIFICATION
BADGES (EIB). The Contractor shall provide each prime contractor employee with an EIB. On JBA the information on this badge shall include the title “SABER CONTRACT JBA”, the prime Contractor’s name, the individual’s name, and a passport sized photograph of the individual. On JBAB, the information on this badge shall include the title “SABER CONTRACT JBAB”, the prime Contractor’s name, the individual’s name, and a passport sized photograph of the individual. The Contractor shall have EIB’s completed prior to the contract start date. New employees shall have completed badges prior to performing work under this contract. EIB’s shall be worn or attached to an outer garment at all times. All badges worn within secure or restricted areas shall be secured to each individual using a plastic armband or a nylon/cotton cord. Military issued security line badges or Government issued identification cards (i.e. DD FORM 2) shall not be utilized as a substitute for the EIB’s and will be displayed in addition to the required EIB’s. In addition, the contractor will be responsible for maintaining one list containing all authorized personnel that have received EIB’s and this list will be submitted to the PCO upon commencement of the contract and at any time during the life of the contract when changes are made to the list. All labor, equipment, materials and rentals/fees required to provide the Contractor and Subcontractor Employee Identification Badge (EIB) shall be at no additional cost to the Government and considered field overhead; therefore part of the Contractor’s coefficient.
SUBCONTRACTOR EIB.
2.1.5.2.1. SUBCONTRACTOR EIB. The Contractor shall provide generic
EIB’s including the prime Contractor’s name, the individual’s name, and a passport sized photograph of the individual. The EIB shall read “Subcontractor to (Name of SABER Contractor)” and the SABER contractor office phone number.
2.2. PROGRAMS.
2.2.1. QUALITY CONTROL PROGRAM. All labor, equipment, materials and rentals/fees required to provide the Quality Control Program shall be at no additional cost to the Government and is
2.2.1.1. QUALITY CONTROL PLAN. IAW FAR 52-246-12, “Inspection of Construction” the Contractor shall provide a Quality Control Plan (QCP) prior to award that contains, as a minimum, the items listed in paragraph 2.2.1.1.1. The QCP shall become a compliance document for all work accomplished under all TOs. Any subsequent modifications shall be submitted to the CO for acceptance before implementation. The PCO reserves the right to request modifications to the QCP if it does not prove effective, and may take actions to remove the acting Quality Control Manager (QCM) if deemed necessary.
2.2.1.1.1. MINIMUM REQUIREMENTS. The QC Plan shall include, as a minimum, the following to cover all construction operations, both on site and off site, including work by subcontractors, fabricators, suppliers, and purchasing agents.
2.2.1.1.2. A description of the quality control organization, including a chart showing lines of authority. As a minimum, the staff shall include a QCM whose responsibility is to implement the QC plan.
2.2.1.1.3. The name, qualifications (in resume format), duties, responsibilities, and authorities of each person assigned a QC function.
2.2.1.1.4. A copy of the letter to the QCM signed by an authorized official of the firm which describes the responsibilities and delegates sufficient authorities to adequately perform the functions of the QCM, including authority to stop work which is not in compliance with the contract. The QCM shall issue letters of direction to all other various quality control representatives outlining duties, authorities, and responsibilities. Copies of these letters will also be furnished to the Government.
2.2.1.1.5. Procedures for scheduling, reviewing, certifying, and managing submittals, including those of subcontracts, off site fabricators, suppliers, and purchasing agents.
2.2.1.1.6. Procedures for tracking preparatory, initial, and follow-up control phases and control, verification, and acceptance test including documentation.
2.2.1.1.7. Procedures for tracking construction deficiencies from identification through acceptable corrective action. These procedures will establish verification that identified deficiencies have been corrected.
2.2.1.1.8. Reporting procedures, including proposed reporting formats.
2.2.2. HEALTH AND SAFETY PROGRAMS. All labor, equipment, materials and rentals/fees required to provide the Health and SAFETY Programs shall be at no additional cost to the Government and is considered field overhead; therefore part of the Contractor’s coefficient.
2.2.2.1. NON-COMPLIANCE ACTIONS. The CO will notify the Contractor of any noncompliance of health or safety requirements, and the required action to be taken (notification delivered to the Contractor representative at the worksite shall be deemed sufficient). The Contractor shall take immediate corrective action to rectify all violations.
If the Contractor fails or refuses to promptly comply, the CO may issue a Stop Work Order ceasing all, or part of the work, until satisfactory corrective action has been taken.
The Contractor shall not attempt to claim costs, damages or time extensions due to Stop Work Orders based on non-compliance with health or safety requirements.
2.2.2.2. RECORDS/NOTIFICATION. The Contractor shall maintain accurate records, and shall submit a report to the CO in letter form that includes the following: all exposure data, accidents resulting in death, traumatic injury, occupational disease, and damage to property, materials, supplies and equipment incident to work performed under this contract.
The contractor shall report, within one hour by telephoning the CO, all available data relating to each instance of a mishap involving government property. During non-standard hours, the contractor shall notify the security police. The contractor shall immediately secure and impound the mishap scene, wreckage, and mishap documentation until released by the investigation safety officer. The safety officer will accomplish this release through the CO. The contractor, and all related subcontractors within his/her control, shall support the government, as it requires, in any mishap or hazard investigation. This support shall include technical assistance as well as access to undelivered internal contractor data.
2.2.2.2.1. Date and time of occurrence.
2.2.2.2.2. Place of occurrence.
2.2.2.2.3. List of personnel directly involved.
2.2.2.2.4. Narrative description of the accident that includes a chronological order of the accident and circumstances.
2.3. EQUIPMENT, MATERIALS AND TRAINING SERVICES. All labor, equipment, materials and rentals/fees necessary for all contractor required, and contractor provided equipment, materials and services to the Government shall be at no additional cost to the Government and is considered field overhead; therefore part of the Contractor’s coefficient.
2.3.1. CONTRACTOR REQUIRED EQUIPMENT, MATERIALS, AND SERVICES. The contractor shall maintain, throughout the life of the contract, all equipment, phone and e-mail services in sufficient quantity for its staff to comply with the contract requirements, and that is compatible with the contractor provided equipment, materials and services that the contractor is required to provide to the Government.
2.3.2. CONTRACTOR PROVIDED MATERIALS TO THE GOVERNMENT. All contractor-provided materials listed below (software and books), shall become the property of the Government. The contractor shall replace any whole or portion of the items listed below when upgrades are necessary as directed by the PCO.
2.3.2.1. TECHNICAL LIBRARY. The contractor shall, within 60 calendar days after contract award, provide four (4) copies of the following manuals/codes and shall provide all current updates as published. All labor, equipment, materials, and rentals/fees required to provide the technical library is considered field overhead; therefore part of the Contractor’s coefficient. One set of each of the manuals/codes shall be distributed to each contracting office and one to each civil engineering office unless stated otherwise.
2.3.2.1.1. R.S. MeansTM Estimating Guides. As stated in paragraph 3.2.1.3.
2.3.2.1.2. R.S. MeansTM Estimating Handbook.
2.3.2.1.3. R.S. MeansTM Illustrated Construction Dictionary.
2.3.2.1.4. Microsoft Project to include Training.
2.3.2.1.5. National Electric Code Handbook (One (1) copy for each CE)
2.3.2.1.6. EM 385-1-1 Safety Health requirements Manual. May be obtained from the
Government Printing Office, Washington D.C. 20402. The Contractor is responsible for compliance with the provisions of this manual, to include subcontractors. http://www.usace.army.mil/publications/eng-manuals/em385-1- 1/toc.htm (Do not provide a copy to the government.)
2.3.2.1.7. National Electric Code. (One (1) copy for each CE)
2.3.2.1.8. Uniform Plumbing Code. (One (1) copy for each CE)
http://www.usace.army.mil/publications/eng-manuals/em385-1-1/toc.htm http://www.usace.army.mil/publications/eng-manuals/em385-1-1/toc.htm
2.3.2.1.9. Uniform Building Code. (One (1) copy for each CE)
2.3.2.2. SOFTWARE PROGRAMS/LICENSES/UPGRADES. The contractor shall, within 60 calendar days after contract award, provide, install and troubleshoot the following most current versions of software to JBA and JBAB CE and shall provide upgrades as published within 60 days after release. The number of licenses required is listed after each software program. All labor, equipment, materials, and rentals/fees required to provide software, is
2.3.2.2.1. e4Clicks Project Estimator most current version ™ (e4clicks) software to include:
(10 licenses for each CE)
2.3.2.2.2. R.S. Means ™ Facilities Cost Data module (in bare cost format).
2.3.2.2.3. R.S. Means ™ Repair & Remodeling Cost Data module.
2.3.2.2.4. R.S. Means ™ Assemblies Cost Data module.
2.3.2.2.5. AutoCAD ™ for Windows operating systems. (4 licenses)
2.3.2.2.6. Construction Criteria Base ™ (One (1) copy for each CE).
2.3.3. CONTRACTOR PROVIDED TRAINING SERVICES TO THE GOVERNMENT.
2.3.3.1. SOFTWARE TRAINING. The contractor shall provide the following training at time of contract award and annual refresher training (two (2) days routine and one (1) day advanced training) for assigned SABER personnel, not to exceed 22 persons per class, when requested (annually) by the government.
2.3.3.1.1. e4Clicks Project Estimator current version ™ Program Training Provided by the publisher.
2.3.3.1.2. R.S. Means ™ Estimating Guide Training. Provided by the publisher.
3. COMMENCEMENT OF WORK. The contractor shall be capable of executing task orders within sixty
(60) calendar days after contract award. The contractor shall be fully operational with all required facilities, staff and automated data processing (ADP) capability within ninety (90) calendar days after award. The cost of mobilization is part of the contractor’s coefficient. For each project, the Contractor will receive a formal request for proposal (RFP)/Statement of Work (SOW) Package. All Government requests will include a work request number, project title, conceptual scope of work, and will state any known special instructions or conditions that may exist. The Contractor shall attend a Pre-Proposal Site Visit to introduce and familiarize the Contractor with the projected work requested. Subsequently, the Contractor shall prepare and submit for review a corresponding Contractor Statement of Work (SOW) Package (see paragraph 3.2.1). To facilitate and expedite year-end or emergency requirements, the Government reserves the right to solicit proposals from the contractor in advance of funding. The contractor shall provide such proposals at no additional charge to or obligation by the Government. Solicitations issued in advance of funding will be so annotated. When requested, the Contractor will have access to all currently available Records and As-Built drawings located at JBA CES, 1349 Fetchet Ave, JBAand JBAB Civil Engineering Squadron (location TBD), as required for development of the Contractor’s proposal. Field verification of all measurements and existing conditions is required before Contractor submittals to ensure an accurate scope and cost. The Contractor shall be responsible for identifying tasks, refining quantities, preparing design calculations, pricing any Non-Priced Items (NPI) or tasks, preparing required design drawings, developing performance times, and submitting a formal proposal in the prescribed format. The Government will respond to any questions the Contractor may have regarding the work, and the Contractor shall submit the proposal to the TO CO. Following Government technical review of the proposal, the TO CO will conduct negotiations with the Contractor, and CES representatives and any other persons deemed necessary, for resolving any variations involving price, time, quantities, and any other relevant items. Following Government acceptance of the negotiated and/or revised proposals, the TO CO will prepare and issue a TO and a Notice to Proceed (NTP) directing the Contractor to begin work within a specified period acceptable to the TO CO based on mission requirements. The contractor shall commence any mobilization and familiarization activities prior to actual work on individual task orders. Acceptance of each task order constitutes the Notice to Proceed for that order. Work shall begin within the number of days specified in the task order, and in compliance with the AF FORM 3064 submitted at the pre-construction conference.
3.1. PROJECT REQUIREMENT TYPES. The two types of project requirements are routine and
Emergency. Either of these types of projects may be required at any time during the length of this contract. The Government is responsible for determination of project requirement type.
3.1.1. ROUTINE REQUIREMENT. Within three calendar days of project notification, unless otherwise directed by the TO CO, the PM shall attend a Pre-Proposal Site Visit (Job Walk) to clarify any project requirements, and/or further define the project scope of work. The Contractor’s proposal shall be submitted to the TO CO within 10 calendar days after the Pre-Proposal Site Visit for non-complex work and 14 calendar days after the Site Visit for complex work as determined by the Government, unless otherwise directed by the TO CO.
3.1.2. EMERGENCY REQUIREMENT. In the event of an emergency requirement, the PMs Response time will be directed by the CO. The PM or authorized representative shall attend a Pre- Proposal Site Visit (Job Walk) to clarify any project requirements, and/or further define the project scope of work within one (1) hour, or as directed. The Contractor’s proposal shall be submitted IAW paragraph 3.2.1, or as directed by the CO.
3.2. COMMENCEMENT DOCUMENTS. Contractor design documents shall be developed so that a distinction is made between items that are associated with each classification of work (i.e. Demolition, Minor Construction, Repair, and Additives). Categories of work notes shall be noted throughout the contract documents to clearly distinguish between works that are Demolition (D), Minor Construction (MC), or Repair (R) and further delineate any items that are Additive Bid Items (reflected as “Option #”) and shall be accounted for and priced separately in the cost proposal. Additive Bid Items shall be priced separately. The concept of the SABER program provides for 35% design level effort. All labor, equipment, materials and rentals/fees required to provide all commencement documents shall be at no additional cost to the Government and are considered field overhead; therefore part of the Contractor’s coefficient.
3.2.1. SOW PACKAGE. The Contractor shall submit for Government review, three copies (may be submitted electronically via e-mail as directed by the TO CO), and one electronic CD-ROM formatted SOW Package presenting the Contractor’s offer within the timeframe as specified by the TO CO. The Contractor’s design shall be IAW paragraph 3.3. The format shall be IAW TE-5 - SOW PACKAGE FORMAT. When the Contractor desires to offer alternatives, or Value Engineering Proposals, the contractor’s SOW package proposal shall: clearly state and identify alternatives proposed; their segregated associative costs; a delineation of impacted line items; and advantages and disadvantages for Government evaluation. The Contractor shall provide support, verification and justified reasoning behind their proposal to alter the Government’s RFP.
3.2.1.1. SPECIFICATIONS. The Contractor shall develop project specifications in Construction Specification Institute (CSI) format utilizing the current edition of the U. S. Army Corps of Engineers Guide Specifications (CEGS). Specifications shall be developed using the latest version of Microsoft Word ™ utilized by the government. As a minimum, applicable CEGS sections and paragraphs shall be listed along with the specific requirements of the TO.
3.2.1.2. COST ESTIMATES. Cost estimates shall be calculated using the approved software program IAW paragraph 2.3.2.3.1; based upon current RS Means ™ Cost Data bare costs data; and reflect the Washington DC City Cost Index.
3.2.1.3. ESTIMATING GUIDES. The following RS Means ™ Cost Data Estimating Guides shall be authorized:
Assemblies Cost Data Interior Cost Data Building Construction Light Commercial Concrete and Masonry Mechanical Electrical Plumbing Facilities Maintenance and Repair Repair and Remodeling Heavy Construction
3.2.1.4. UNAUTHORIZED SECTIONS. RS Means line items from Division 1 in its entirety except Section 01500, Temporary Facilities and Controls and Section 01590, Equipment Rental, is considered field overhead; therefore part of the Contractor’s coefficient.
3.2.1.5. PRE-PRICED DATA (PPD) AND NON-PRICED ITEMS(NPI). All line items in R.S.
Means TM Estimating Guides are considered PPD. When a component, work element, or system does not exist as PPD, it will be considered as a NPI. If the contractor’s TO proposal includes any non-priced items, those items shall be separately identified and priced. Proposed NPI prices must be documented by supporting information as specified below:
1. A minimum of three (3) competitive contractor quotes, which shall include materials(s) description with unit price and installation, labor cost showing labor classification, hourly rate, and number of hours anticipated for each workman, etc.
2. A complete breakout of material, labor and other direct cost required to complete the specified work items. Cost shall be segregated and proposed on AF Form 3052 “Construction Cost Breakdown”, or other format approved by the TO CO. Any item of work not found in the R.S. Means TM Cost Database but required under an individual TO shall be negotiated by the TO CO. The negotiated price of an NPI will be based on costs to include material, equipment, labor and subcontractor’s indirect expenses such as overhead, profit, labor burden, etc. Coefficients will not be applied to NPI’s. Non-priced items once negotiated and used in a Task Order will be added to the NPI roster maintained by the contractor (see paragraph 3.2.1.3.3).
3.2.1.6. NPI ROSTER. The Contractor shall maintain a roster of all NPI’s utilized during the base period of performance to establish a secured cost basis for these items in subsequent project requests. NPI’s included in this roster shall be valid during the current period of performance. NPI’s established on the NPI Roster shall be re-validated during the exercise of the next option period.
3.2.1.7. APPLICABILITY OF MINIMUM AND MAXIMUM VALUES. When RS Means ™ Cost Data Line Items reflect a maximum or minimum, the average of these two values shall be used.
3.2.1.8. PROJECT DRAWINGS. The Government will indicate which drawings are necessary for each individual project. All project drawings shall be generated utilizing Computer Aided Drafting and Design (CADD) software compatible to the latest edition utilized by the government (most current version of AutoCAD ™). All project drawings, dimensioning and symbols shall conform to the current edition of Architectural Graphics Standards, the Tri- Service Spatial Architectural/Engineering/Construction (A/E/C) Computer-Aided Design and Drafting (CADD) Standards, government CADD Standards. The Contractor shall include in the SOW Package for Government approval the following drawings, as required on each project request:
Title Sheet Finish Schedules Existing Site Plans Window and Door Schedules Final Site Plans Mechanical Plans and equipment Schedules Grading Plans Mechanical Equipment Diagrams Underground Utility Plan and Profiles Plumbing and HVAC Riser Diagrams Falsework…