SABER_Site_Visit_Minutes_21_July_15.docx

DOCX document 92 KB Posted

Attached to
Simplified Acquisition of Base Engineering Requirements (SABER) - FA2860-15-R-0008
Solicitation number
FA2860-15-R-0008
Issued by

About this file

JBA SABER Site Visit Minutes for 21 July 2015

View the file

Other files

File Type Posted
FA2860-15-R-0008_P0012_SABER_Solicitation_Amendment.doc DOC document
Attachment_6_Price_Evaluation_Worksheet.xlsx XLSX spreadsheet
FA2860-15-R-0008_P0009_SABER_Solicitation.doc DOC document
FA2860-15-R-0008_P0007_SABER_Solicitation.doc DOC document
Questions_Part_2_FA2860-15-R-0008.pdf PDF
Questions_Sol__No__FA2860-15-R-0008_13_Aug_15.pdf PDF
JBA_Tax_Exempt_Certificate.pdf PDF
FA2860-15-R-0008_P0006_SABER_Solicitation.doc DOC document
Questions_Sol__No__FA2860-15-R-0008_13_Aug_2015.pdf PDF
AF_66_Submittal_Sheet_for_AJXF_14-1584.xlsx XLSX spreadsheet
JBA_Architectural_and_Interior_Design_Standards.pdf PDF
FA2860-15-R-0008_P0005_Time_Ext.doc DOC document
Questions_and_Answers_as_of_29_July_15.pdf PDF
Water_Fountain_Near_TAC_Fit.jpg JPG image
FA2860-15-R-0008_P0004_SABER_Solicitation.doc DOC document
JBA_SABER_Sign_In_Sheet_PDF.pdf PDF
Elec_Panel_Pix_3.jpg JPG image
Elec_Panel_Pix_2.jpg JPG image
HVAC_System_Floor_Plan_Building_1444.pdf PDF
Repair_HVAC_System_Floor_Plan_Building_1444.pdf PDF
Water_Fountain_Near_Front_Desk.jpg JPG image
Elec_Panel_Pix_1.jpg JPG image
Bldg_1444_Floor_Drawing.pdf PDF
Mechanical_Drawing_Bldg_1444.pdf PDF
TAC_Fitness_Bldg_1445.pdf PDF
HVAC_System_Floor_Plan_Building_1444__Demo.pdf PDF
FA2860-15-R-0008_P00001_SABER_Solicitation.doc DOC document
Price_Evaluation_Worksheet_Attachment_6.xls XLS spreadsheet
Heavy_MD150035_MD35.pdf PDF
FA2860-15-R-0008_SABER_Solicitation_for_JBA_MD.doc DOC document
Residential_MD150081_MD81.docx DOCX document
AF_Form_66_SABER.xls XLS spreadsheet
Highway_MD150100_MD100.pdf PDF
Building_MD150058_MD58.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

11TH CONTRACTING SQUADRON (AFDW)

JOINT BASE ANDREWS, MARYLAND 20762

22 July 15

MEMORANDUM FOR ALL OFFERORS

FROM: 11th Contracting Squadron/LGCAA 1349 Lutman Drive Joint Base Andrews, MD 20762-7001

SUBJECT: Solicitation FA2860-15-R-0008, Simplified Acquisition of Base Engineering Requirements (SABER), Pre-Proposal and Site Visit Minutes for AJXF 14-1584, Renovate West Fitness Center, Joint Base Andrews, MD

1. The Joint Base Andrews SABER pre-proposal conference and site visit for subject project was held 21 July 2015. The attendees met at the JBA visitor’s center by 1000hrs (EST) to sign in then were escorted and or proceeded to the West Fitness Center.

2. At the fitness center, company representatives gathered into the bleacher area. At this time, three sets of drawings were provided to each company in attendance. After quick introductions of the 11CONS and 11CES government SABER team to the attendees, small groups were sent in to view the men’s and woman’s locker room area where the saunas were located.

3. After company representatives toured both locker rooms, everyone gathered in front of the gymnasium to view/walk from the vestibule into the main floor through the hallways, into the TAC fitness area then back to the gymnasium bleachers.

4. Company representatives were reminded throughout the site visit to submit their questions NLT 28 July 15 to MSgt Conway and myself as outlined on the solicitation.

5. Questions that were asked and responded to/on site were:

Q. Where are the electrical panels for the vestibule lighting and what fuse size is required?

A. Panels are located towards rear of the fitness center; there are three (3) panels available That can support a 40 amp fuse. (See attached photos) Q. What is the distance from the front vestibule to the nearest electrical panel(s)?

A. Estimated distance is 400-450 feet.

Q. Are as built drawings available?

A. We’ll research and provide via amendment when located. (See attached as built drawings provided).

Q. A question arose about current coefficients of the existing SABER contractors and if they can be provided.

A. The coefficients of the incumbent SABER companies Blazer-Candace JV and NICC JV are considered proprietary information and cannot be released.

Q. Can drawings provided at this site visit be electronically provided?

A. Yes, on the next amendment they will be provided (see attached).

Q. Will the solicitation due date be extended if answers submitted by 28 July 15 are not provided in a timely manner?

A. A determination will made by the Contracting Officer, Mr. Krisko based on response time involved with Government personnel.

6. All attendees gathered in the gymnasium bleachers and were thanked for their time/interest in the JBA SABER solicitation. All were reminded the terms and conditions of the solicitation and specifications remain unchanged unless amended and any questions or clarifications that arose as a result of the site visit must be submitted via email NLT 28 July 2015.

ANTHONY J. WEEDIN
Contract Specialist

SEAN M. KRISKO

Contracting Officer

Attachments:

1. Sign-in Sheets

2. As Built Drawings (3)

3. Electrical Panel Photos