Consolidation D-F CNECTS_Finalized_Redacted.pdf

PDF 9 MB Posted

Attached to
Communications, Network, Engineering, Cybersecurity, and Information Technology Services (CNECTS), aka "Connects"
Solicitation number
FA251827RCNECTS
Issued by

About this file

This is a Determination and Findings (D&F) document for the consolidation of four separate U.S. Air Force contracts into a single Communications, Network, Engineering, Cybersecurity, and Information Technology Services (CNECTS) contract for the 21st Communications Squadron.

The consolidation encompasses four existing contracts: Base Operating Support–Information Technology (BOS-IT) at Peterson Space Force Base and Schriever Space Force Base; Cheyenne Mountain SFS 21 Communications Contract; Wing Information & Communications Support (WICS) at Schriever Space Force Base; and Plans and Programs Engineering Design Support (PEDS). These contracts currently support operations, maintenance, and logistics of information systems infrastructure across Peterson SFB, Schriever SFB, and Cheyenne Mountain Space Force Station. Required services include hardware and software maintenance, network and system administration, help desk support, communications focal point services, cybersecurity monitoring, and disaster recovery planning. The consolidated contract will be classified under NAICS code 517810 (All Other Telecommunications) with an estimated combined annual value of approximately $30 million. The consolidation is projected to generate measurable substantial monetary savings of at least $5 million annually through elimination of duplicative costs, reduced indirect costs and profit, contract access fee savings, administrative efficiencies, and workforce realignment. The government anticipates awarding the consolidated contract as a 100% competitive 8(a) set-aside to maintain small business participation while achieving mission effectiveness and cost savings. Market research identified 16 small businesses and 8 large businesses capable of performing the consolidated requirements, with strong small business interest demonstrated in RFI responses.

View the file

Other files

File Type Posted
CNECTS _Questions_Answers_ 15 Oct 26.pdf PDF
Tentative Schedule_15 Oct 2026_table.pdf PDF
CNECTS CSO Final Draft v1.0.docx DOCX document
CNECTS Teaming-Partnering Interest Spreadsheet v3.xlsx XLSX spreadsheet
CNECTS Teaming-Partnering Interest Spreadsheet v2.xlsx XLSX spreadsheet
Virtual Industry Day Slides_19 Aug 26.pdf PDF
SAIO CNECTS Virtual Industry Day_Transcript.docx DOCX document
CNECTS Teaming -Partnering Interest Spreadsheet.xlsx XLSX spreadsheet
CNECTS Virtual Industry Day Presentation 19 Aug 26.pptx PPTX presentation
CNECTS _Questions_Answers_ 01 May 2026.pdf PDF
PEDS PWS_22 Apr 22 Final_Posting Ready.docx DOCX document
Welcome to CNECTS Industry Day Slides v2.pdf PDF
CNECTS CSO Draft_3-27-2026.pdf PDF
WBS Matrix_updated 3-26-2026.xlsx XLSX spreadsheet
Draft CNECCTS AOI-2026-004 _PEDS.pdf PDF
4. PEDS PWS_22 Apr 22 Final.docx DOCX document
Draft CNECCTS AOI-2026-002 _NISSC.pdf PDF
Draft CNECCTS AOI-2026-001 _BOS-IT.pdf PDF
Draft CNECCTS AOI-2026-003 _WICS II.pdf PDF
RFI 2 Commerciality_ BIM_ CMMC.pdf PDF
CNECTS RFI 3 - INDUSTRY DAY NOTICE.pdf PDF
5. CNECTS Requirements and Legacy Contract Differences.docx DOCX document
4. RFI- Commerciality_ BIM_ CMMC_ DRAFT.docx DOCX document
6. Requirements Matrix for RFI 2.xlsx XLSX spreadsheet
1. BOS-IT PWS - 7 Oct 24 (2).docx DOCX document
0. CNECTS RFI #1, Consolidation - 31 Jul 25.docx DOCX document
4. PEDS PWS - 22 Apr 22.docx DOCX document
1a. Giant Voice PWS - 5 Feb 25.docx DOCX document
3. WICS II PWS (21 CS rqts only) - 31 Jul 25.docx DOCX document
2. Cheyenne Mountain SFS 21 CS Communications Contract - 31 Jul 25.docx DOCX document
1. BOS-IT PWS - 7 Oct 24.docx DOCX document
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEMPER VENATOR

Cheyenne Mountain SFS 21 CS Communications and PEDS separate.”

Of the firms that did recommend alternatives, the alternatives included either a lesser degree of consolidation, or a multiple-award IDIQ. For the reasons described in this paragraph and paragraph 5.a.iv below, neither alternative is considered feasible.

Based on the RFI responses, all options for a lesser degree of consolidation do not appear to have any substantive impact (positive or negative) on small business participation in this effort. The only apparent impact is the magnitude of the savings to the government in terms of monetary benefits and efficiencies gained. Thus, the only de facto viable options are either full consolidation or no consolidation.

iv) Multiple-award IDIQ. A multiple-award IDIQ would allow the Government to award multiple contracts to meet the overall CNECTS requirement. However, multiple awards under an IDIQ are only appropriate when the requirement meets the conditions in FAR 16.504(c)(1)(ii), including ensuring that the projected task orders are not so integrally related that only a single contractor can reasonably perform the work. Rather, a single award providing additional benefits not available under multiple awards as noted in FAR 16.504(c)(ii)B(B), (B) The contracting officer must not use the multiple award approach if-

(1) Only one contractor is capable of providing performance at the level of quality required because the supplies or services are unique or highly specialized;

(2) Based on the contracting officer’s knowledge of the market, more favorable terms and conditions, including pricing, will be provided if a single award is made;

(3) The expected cost of administration of multiple contracts outweighs the expected benefits of making multiple awards;

(4) The projected task orders are so integrally related that only a single contractor can reasonably perform the work;

(5) The total estimated value of the contract is at or below the simplified acquisition threshold; or

(6) Multiple awards would not be in the best interests of the Government.

(C) The contracting officer must document the decision whether or not to use multiple awards in the acquisition plan or contract file. The contracting officer may determine that a class of acquisitions is not appropriate for multiple awards (see subpart 1.7).

For this consolidated requirement, it realistically only makes sense for a single contractor to perform the work. The scope of the requirements overlap and are integrated with each other, both across requirements and across locations. For example, the Communications Focal Point (CFP) requirement spans across all installations and touches virtually every other requirement area. The CFP is the central hub to which all help tickets come in, and from there, depending on the nature of the problem, are either delegated to the other work centers, or handled immediately by the CFP tech.

Therefore, it would be impractical to split this requirement either by location or function.

If a different contractor did this at each location, it would neutralize the consolidation savings and benefits. If one contractor executed this function, but other contractors did other functions the CFP relies on, artificial seams would be created, and accountability