TRD_F6 Operational Ground Test Facility
View the file
Other files for this federal contract opportunity
Show all 50
Eglin Operations & Maintenance Services (Formerly Eglin Test & Training Complex Technical Services (ETTC-TS) Program) has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Rev E
FA9200-05-C-0001, P00057
Attachment 3
Page F6-1
APPENDIX F6
OPERATIONAL GROUND TEST (OGT) FACILITY
1.0 PURPOSE
2.0
. The primary purpose of the OGT Facility is to conduct ground tests on live precision guided weapons in a simulated operational environment. The test may include temperature and vibration conditioning, seeker guidance HITL, and engine run either individually, simultaneously, or sequentially to determine the weapon’s operational readiness and reliability.
2.1. The OGT Facility is located on TA C-80A, approximately 21 miles northeast of Eglin main base, reached via SRs 20 and 285 and RRs 200 and 201. TA C-80A is approved for testing munitions up to 2,000 pounds NEW.
GENERAL.
2.2. The total-fragment-recovery system (appendix F5) is also located on TA C-80A. It is used infrequently.
3.0
3.1. The Contractor shall operate and maintain the OGT Facility and associated systems and equipment as part of the seven simultaneous operations as specified in PWS paragraph 1.7, including:
CAPABILITIES.
3.1.1. An electromechanical vibration system, including:
1. Vibration unit.
2. Vibration controller.
3. Accelerometers of various types and styles.
4. Vibration test stands, including stingers, fixtures, and miscellaneous items.
3.1.2. Temperature conditioning system, including:
1. Temperature conditioning unit.
2. Insulated ducting.
3. Insulated conditioning chamber.
3.1.3. A cleared space approximately 800 feet by 2000 feet.
3.1.4. A 40-foot by 60-foot test chamber (9460).
3.1.5. A hardened control building (9462).
3.1.6. An underground bunker (9463).
3.1.7. A vehicle shelter (9464).
3.1.8. General test support and data equipment, including:
1. Programmable sequencer/controller unit.
2. Three bay control console including site PA system, radios, fiber optic link, etc.
3. CCTV system including cameras, monitors and display control switcher.
Rev E
FA9200-05-C-0001, P00057
Attachment 3
Page F6-2
4. Low voltage firing system.
5. Aero Plank system.
6. Portable hydraulic power system, including pump, ram, and force link to be utilized for calibrating engine run stands.
7. Engine run stands and miscellaneous items.
8. Various mobile and fixed radios.
9. Electric Field Mill (lightning warning) system.
10. GPS timing system.
3.1.9. Total-fragment-recovery system, including:
1. Two 20-foot-diameter steel water tanks. (E-182)
2. Electric crane.
3. Manual winches.
4. Fragment recovery devices.
3.2. The Contractor shall operate and maintain the OGT Simulation System (appendix D1) IAW tasks and test directives.
3.3. The Contractor shall set up and conduct OGT tests IAW tasks and test directives.
| APPENDIX F6 |
| 1.0 UPURPOSEU. The primary purpose of the OGT Facility is to conduct ground tests on live precision guided weapons in a simulated operational environment. The test may include temperature and vibration conditioning, seeker guidance HITL, and engine run e |
| 2.0 UGENERAL. |
| 2.1. The OGT Facility is located on TA C-80A, approximately 21 miles northeast of Eglin main base, reached via SRs 20 and 285 and RRs 200 and 201. TA C-80A is approved for testing munitions up to 2,000 pounds NEW. |
| 2.2. The total-fragment-recovery system (appendix F5) is also located on TA C-80A. It is used infrequently. |
| 3.0 UCAPABILITIES. |
| 3.1. The Contractor shall operate and maintain the OGT Facility and associated systems and equipment as part of the seven simultaneous operations as specified in PWS paragraph 1.7, including: |
| 3.1.1. An electromechanical vibration system, including: |
| 1. Vibration unit. |
| 2. Vibration controller. |
| 3. Accelerometers of various types and styles. |
| 4. Vibration test stands, including stingers, fixtures, and miscellaneous items. |
| 3.1.2. Temperature conditioning system, including: |
| 1. Temperature conditioning unit. |
| 2. Insulated ducting. |
| 3. Insulated conditioning chamber. |
| 3.1.3. A cleared space approximately 800 feet by 2000 feet. |
| 3.1.4. A 40-foot by 60-foot test chamber (9460). |
| 3.1.5. A hardened control building (9462). |
| 3.1.6. An underground bunker (9463). |
| 3.1.7. A vehicle shelter (9464). |
| 3.1.8. General test support and data equipment, including: |
| 1. Programmable sequencer/controller unit. |
| 2. Three bay control console including site PA system, radios, fiber optic link, etc. |
| 3. CCTV system including cameras, monitors and display control switcher. |
| 4. Low voltage firing system. |
| 5. Aero Plank system. |
| 6. Portable hydraulic power system, including pump, ram, and force link to be utilized for calibrating engine run stands. |
| 7. Engine run stands and miscellaneous items. |
| 8. Various mobile and fixed radios. |
| 9. Electric Field Mill (lightning warning) system. |
| 10. GPS timing system. |
| 3.1.9. Total-fragment-recovery system, including: |
| 1. Two 20-foot-diameter steel water tanks. (E-182) |
| 2. Electric crane. |
| 3. Manual winches. |
| 4. Fragment recovery devices. |
| 3.2. The Contractor shall operate and maintain the OGT Simulation System (appendix D1) IAW tasks and test directives. |
| 3.3. The Contractor shall set up and conduct OGT tests IAW tasks and test directives. |
File details come from the government source that posted it. Updated .