This is a pricing template for the Resilient Missile Warning Tracking (RMWT) Low Earth Orbit (LEO) Ground Entry Points (GEPs) contract under solicitation FA240126R0003, issued by the Space Development Agency (SDA) of the Department of the Air Force. The template, amended November 19, 2026, establishes the structure for offeror pricing submissions across multiple geographical locations (Otis, Fairchild, and Grand Forks) and contract periods. The base Indefinite Delivery/Indefinite Quantity (IDIQ) contract runs from March 31, 2027 to September 30, 2031, with an additional option period from October 1, 2031 to September 30, 2035. Task Order 1 pricing covers individual site implementation from March 31, 2027 through September 30, 2031 with four option years.
Pricing requirements include Firm-Fixed-Price (FFP) labor CLINs for Labor Development and Integration (CLIN 0001/2001-5001), Labor Maintenance (CLIN 0002/2002-5002), and Civil Engineering (CLIN 0003/2003-5003), plus Material CLINs (0004/2004-5004) on an FFP basis. Cost Reimbursable (CR) Other Direct Costs (ODCs) and Travel are Not-to-Exceed with fixed ceilings: base ODCs of $1,500,000 and option ODCs of $500,000 for the IDIQ, and base ODCs of $300,000 with varying option amounts ($25,000-$15,000) for Task Order 1 at each location. Offerors must provide separate unit costs for CONUS and OCONUS deployments and are required to price material line items including concrete pads, equipment shelters, trenching, power systems, RF antennas, optical terminals, security systems, and trade labor on a unit-quantity-of-one basis. The government will evaluate pricing using an undisclosed shielded Total Evaluated Price (TEP) model with proprietary weighting factors. Offerors must certify pricing completeness, eliminate cost duplication across pricing locations, and document all assumptions and geographic bounding conditions in the template.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IDIQ
| Version Number | Date | Comment |
| 1.0 | 18 September 2026 | RFP Release Version |
| 1.1 | 19 November 2026 | RFP Amendment #1 |
| 1. The "Company Name" should be reflected in Cell B17. | ||
| 2. Fill in ONLY the yellow cells below. | ||
| 3. This template should automatically calculate all costs by summing as appropriate. | ||
| 4. The Offeror is responsible for the accuracy of the price template. | ||
| 5. The Total Evaluated Price (TEP) shall be included in Price volume of the proposal (Volume IV). | ||
| 6. Both the Other Direct Cost (ODC) CLINs and Travel CLINs are Not to Exceed (NTE) and are included as part of the TEP. | ||
| 7. Base period CLIN 0004 will have a shielded TEP for quantity | ||
| 8. The price for the IDIQ base period (31 March 2027 - 30 Sep 2031) and option period (1 Oct 2031 - 30 Sep 2035) shall include all costs to meet Labor Development and Integration, Labor Maintenance, Civil Engineering, and Material. | ||
| 9. Rows 21 - 26 are IDIQ values and are not expected to change based on location. Location specific information will be filled out using the location specific tabs. | ||
| 10. Values in rows 28 & 29 will be calculated by the government using a shielded TEP. See note #3 in the Material tab for additional details |
| _________ Price Summary | |||||
| (Company Name) | |||||
| RMWT LEO GEPs | |||||
| CLIN Description | CLIN | CLIN Type | Total Price | ||
| (Otis) | Total Price (Fairchild) | Total Price (Grand Forks) |
| RMWT LEO GEPs (Labor Development and Integration) Base Period | 0001 | FFP | |||
| RMWT LEO GEPs (Labor Maintenance) Base Period | 0002 | FFP | |||
| RMWT LEO GEPs (Civil Engineering) Base Period | 0003 | FFP | |||
| RMWT LEO GEPs (Labor Development and Integration) Option Period | 1001 | FFP | |||
| RMWT LEO GEPs (Labor Maintenance) Option Period | 1002 | FFP | |||
| RMWT LEO GEPs (Civil Engineering) Option Period | 1003 | FFP | |||
| Labor TOTAL | $0.00 | $0.00 | $0.00 | ||
| RMWT LEO GEPs (Material) Base Period | 0004 | FFP | |||
| RMWT LEO GEPs (Material) Option Period | 1004 | FFP | TBD | TBD | TBD |
| Material TOTAL | $0.00 | $0.00 | $0.00 | ||
| ODCs - Base Period | 0005 | CR | $1,500,000.00 | $1,500,000.00 | $1,500,000.00 |
| ODCs - Option Period | 1005 | CR | $500,000.00 | $500,000.00 | $500,000.00 |
| ODC TOTAL | $2,000,000.00 | $2,000,000.00 | $2,000,000.00 | ||
| Travel - Base Period | 0006 | CR | $1,400,000.00 | $1,400,000.00 | $1,400,000.00 |
| Travel - Option Period | 1006 | CR | $750,000.00 | $750,000.00 | $750,000.00 |
| Travel TOTAL | Cost Reimb | Cost Reimb | $2,150,000.00 | $2,150,000.00 | $2,150,000.00 |
| GFP Base Period | |||||
| GFP Option Period | |||||
| GFP Total | $0.00 | $0.00 | $0.00 |
Total IDIQ Price (excluding TO#1) $4,150,000.00 $4,150,000.00 $4,150,000.00
| Task Order 1 Price | $807,500.00 | $807,500.00 | $807,500.00 | ||
| Cost Reimb | Cost Reimb | Cost Reimb | Cost Reimb | Cost Reimb | |
| Total Evaluated Price (TEP) | Cost Reimb | Cost Reimb | $4,957,500.00 | $4,957,500.00 | $4,957,500.00 |
| Page 1 of 1 | |||||
| *Note - Please do not change any of the values that have been provided, input proposed prices in the yellow cells only on this tab. |
Material
| Instructions to Offerors: |
| 1. Firm-Fixed-Price (FFP): All pricing entered in this template must be Firm-Fixed-Price (FFP). |
| 2. Geographical Breakout: Offerors must provide separate FFP Unit Costs for CONUS (Continental United States) and OCONUS (Outside Continental United States) deployments. |
| 3. For the purposes of proposal evaluation, the Government will utilize a Shielded Total Evaluated Price (TEP) mechanism. The estimated quantities and weighting factors used in the TEP calculation are proprietary to the Government and will not be disclosed to offerors. Accordingly, offerors must submit pricing based on a Unit Quantity of One (1) for equipment or One (1) Lot / Per Site for services, unless otherwise specified. Offerors shall submit pricing restricted to the Base Period of the IDIQ. |
The proposed unit prices will be evaluated using the Government's undisclosed model. This Pricing Matrix will be incorporated into the resulting IDIQ contract.
| 4. Baseline Configuration: For Item 1.0 (Overall Integration), base your FFP estimate on a standard baseline site configuration consisting of two (2) ~5 to 6.5m dual-band S/Ka RF antennas and two (2) Optical Ground Terminals. | ||
| 5. Prices are for one year only | ||
| 6. Column N: Assumptions & Bounding Conditions: You must explicitly detail any assumptions, exclusions, or geographic bounding conditions (especially for OCONUS) used to calculate your FFP unit costs in the provided column. | ||
| Year 1 | ||
| 31 Mar 2027 – 30 Sep 2027 | Year 1 | |
| 31 Mar 2027 – 30 Sep 2027 | Year 2 | |
| 01 Oct 2027 – 30 Sep 2028 | Year 2 | |
| 01 Oct 2027 – 30 Sep 2028 | Year 3 | |
| 01 Oct 2028 – 30 Sep 2029 | Year 3 | |
| 01 Oct 2028 – 30 Sep 2029 | Year 4 | |
| 01 Oct 2029 – 30 Sep 2030 | Year 4 | |
| 01 Oct 2029 – 30 Sep 2030 | Year 5 | |
| 01 Oct 2030 – 30 Sep 2031 | Year 5 |
01 Oct 2030 – 30 Sep 2031
| Item # | Description of Cost Component | Unit of Measure (UoM) | FFP Unit Cost CONUS ($) | FFP Unit Cost OCONUS ($) | FFP Unit Cost CONUS ($) | FFP Unit Cost OCONUS ($) | FFP Unit Cost CONUS ($) | FFP Unit Cost OCONUS ($) | FFP Unit Cost CONUS ($) | FFP Unit Cost OCONUS ($) | FFP Unit Cost CONUS ($) | FFP Unit Cost OCONUS ($) | Offeror Assumptions / Bounding Conditions (Specify CONUS vs OCONUS if different) |
| 2 | Specific High-Cost Items Breakout (include additonal rows as needed) | ||||||||||||
| 2.1 | Concrete pad for ~5 to ~6.5m RF antenna (~20x20ft or per design) | Each | |||||||||||
| 2.2 | Concrete pad for Optical Ground Terminal (~20x20ft, seismic isolated) | Each | |||||||||||
| 2.2.1 | Rate for Concrete | Per Square Foot, Per Cubic Yard | |||||||||||
| 2.3 | Equipment Shelter Concrete Pad | Each | |||||||||||
| 2.4 | Equipment Shelter (~320 sq ft, prefab or stick-built) | Each | |||||||||||
| 2.4.1 | Equipment Shelter, Purpose-built on site | Cost per sq ft | |||||||||||
| 2.4.2 | Equipment Shelter, pre-fabricated | Cost per sq ft | |||||||||||
| 2.5 | Trenching, general (~0.25 mile, flat terrain, PFAS/water mgmt) | Per 0.25 Mi | |||||||||||
| 2.5.1 | Communications line trenching | Per 0.25 Mi / per linear ft | |||||||||||
| 2.5.2 | Power line trenching | Per 0.25 Mi / per linear ft | |||||||||||
| 2.6 | Uninterrupted Power Supply (UPS) for graceful failover | Each | |||||||||||
| 2.7 | Automatic Transfer Switch (ATS) | Each | |||||||||||
| 2.8 | Generator System (includes tank under 550 gallons) | Each | |||||||||||
| 2.9 | Electrical Transformer | Each | |||||||||||
| 2.10 | Electrical Switch / Junction Box (Base power interface) | Each | |||||||||||
| 2.11 | HVAC System for Equipment Shelter | Per Shelter / Per Cubic ft | |||||||||||
| 2.12 | Dual band S/Ka RF antenna & related equipment | Each | |||||||||||
| 2.13 | Block Upconverter and amplifier or SSPA & Upconverter | Per anntenna (Inlcude S&Ka separately) | |||||||||||
| 2.14 | Spectrum Analyzer | ||||||||||||
| 2.15 | RF Antenna Radome | Each | |||||||||||
| 2.16 | Optical Ground Terminal & related equipment | Each | |||||||||||
| 2.17 | Trades | per hour | |||||||||||
| 2.17.1 | HVAC | per hour | |||||||||||
| 2.17.2 | Electrical | per hour | |||||||||||
| 2.17.3 | Plumbing | per hour | |||||||||||
| 2.17.4 | Fire Code compliance | per hour | |||||||||||
| 2.18 | Fencing Cost | per linear foot | |||||||||||
| 2.19 | Security Components | Each/per system | |||||||||||
| 2.19.1 | Badge readers | each | |||||||||||
| 2.19.2 | Keys/locks | each | |||||||||||
| 2.19.3 | Electronic Access Points | each | |||||||||||
| 2.19.4 | Remote Video Monitoring System | per system / per camera | |||||||||||
| 2.20 | Replacing with new antennas in the current T1 and/or T2 GEP location(s)/pads | Cost per antenna |
TO 01 Otis
| Otis | Instructions to Offerors: |
| 1. The "Company Name" should be reflected in Cell B13. | |
| 2. Fill in ONLY the yellow cells below. | |
| 3. This template should automatically calculate all costs by summing as appropriate. | |
| 4. The Offeror is responsible for the accuracy of the price template. | |
| 5. This Total Price shall be included in Price volume of the proposal (Volume IV). | |
| 6. Both the Other Direct Cost (ODC) CLINs have NTE ceilings | |
| 7. The price for the Base (31 Mar 2027 - 30 Mar 2028), Option Year One (1) (31 Mar 2028 - 30 Mar 2029), Option Year Two (2) (31 Mar 2029 - 30 Mar 2030), Option Year Three (3) (31 Mar 2030 - 30 Mar 2031), Option Four (4) (31 Mar 2031 - 30 Sep 2031). |
Shall include all costs necessary to meet Labor Development and Integration, Labor Maintenance, Civil Engineering, and Material.
*Note - Please do not change any of the values that have been provided, input proposed prices in the yellow cells only on this tab.
| _________ Price Summary | |||
| (Company Name) | |||
| RMWT LEO GEPs | |||
| CLIN Description | CLIN | CLIN Type | Total Price |
| RMWT LEO GEPs (Labor Development and Integration) Base | 0001 | FFP | |
| RMWT LEO GEPs (Labor Development and Integration) OY1 | 2001 | FFP | |
| RMWT LEO GEPs (Labor Development and Integration) OY2 | 3001 | FFP | |
| RMWT LEO GEPs (Labor Development and Integration) OY3 | 4001 | FFP | |
| RMWT LEO GEPs (Labor Development and Integration) OY4 | 5001 | FFP | |
| RMWT LEO GEPs (Labor Maintenance) Base | 0002 | FFP | |
| RMWT LEO GEPs (Labor Maintenance) OY1 | 2002 | FFP | |
| RMWT LEO GEPs (Labor Maintenance) OY2 | 3002 | FFP | |
| RMWT LEO GEPs (Labor Maintenance) OY3 | 4002 | FFP | |
| RMWT LEO GEPs (Labor Maintenance) OY4 | 5002 | FFP | |
| RMWT LEO GEPs (Civil Engineering) Base | 0003 | FFP | |
| RMWT LEO GEPs (Civil Engineering) OY1 | 2003 | FFP | |
| RMWT LEO GEPs (Civil Engineering) OY2 | 3003 | FFP | |
| RMWT LEO GEPs (Civil Engineering) OY3 | 4003 | FFP | |
| RMWT LEO GEPs (Civil Engineering) OY4 | 5003 | FFP | |
| Labor TOTAL | $0.00 | ||
| RMWT LEO GEPs (Material) Base | 0004 | FFP | |
| RMWT LEO GEPs (Material) OY1 | 2004 | FFP | |
| RMWT LEO GEPs (Material) OY2 | 3004 | FFP | |
| RMWT LEO GEPs (Material) OY3 | 4004 | FFP | |
| RMWT LEO GEPs (Material) OY4 | 5004 | FFP | |
| Material TOTAL | $0.00 | ||
| ODCs - Base | 0005 | CR | $300,000.00 |
| ODCs - OY1 | 2005 | CR | $25,000.00 |
| ODCs - OY2 | 3005 | CR | $25,000.00 |
| ODCs - OY3 | 4005 | CR | $25,000.00 |
| ODCs - OY4 | 5005 | CR | $15,000.00 |
| ODC TOTAL | $390,000.00 | ||
| Travel - Base | 0006 | CR | $280,000.00 |
| Travel - OY1 | 2006 | CR | $37,500.00 |
| Travel - OY2 | 3006 | CR | $37,500.00 |
| Travel - OY3 | 4006 | CR | $37,500.00 |
| Travel - OY4 | 5006 | CR | $25,000.00 |
| Travel TOTAL | Cost Reimb | Cost Reimb | $417,500.00 |
| GFP Base | |||
| GFP Option | |||
| GFP Total | $0.00 | ||
| Cost Reimb | Cost Reimb | Cost Reimb | |
| Total Price | Cost Reimb | Cost Reimb | $807,500.00 |
| Page 1 of 1 |
TO 01 Fairchild
| Fairchild | Instructions to Offerors: |
| 1. The "Company Name" should be reflected in Cell B13. | |
| 2. Fill in ONLY the yellow cells below. | |
| 3. This template should automatically calculate all costs by summing as appropriate. | |
| 4. The Offeror is responsible for the accuracy of the price template. | |
| 5. This Total Price shall be included in Price volume of the proposal (Volume IV). | |
| 6. Both the Other Direct Cost (ODC) CLINs have NTE ceilings | |
| 7. The price for the Base (31 Mar 2027 - 30 Mar 2028), Option Year One (1) (31 Mar 2028 - 30 Mar 2029), Option Year Two (2) (31 Mar 2029 - 30 Mar 2030), Option Year Three (3) (31 Mar 2030 - 30 Mar 2031), Option Four (4) (31 Mar 2031 - 30 Sep 2031). |
Shall include all costs necessary to meet Labor Development and Integration, Labor Maintenance, Civil Engineering, and Material.
*Note - Please do not change any of the values that have been provided, input proposed prices in the yellow cells only on this tab.
| _________ Price Summary | |||
| (Company Name) | |||
| RMWT LEO GEPs | |||
| CLIN Description | CLIN | CLIN Type | Total Price |
| RMWT LEO GEPs (Labor Development and Integration) Base | 0001 | FFP | |
| RMWT LEO GEPs (Labor Development and Integration) OY1 | 2001 | FFP | |
| RMWT LEO GEPs (Labor Development and Integration) OY2 | 3001 | FFP | |
| RMWT LEO GEPs (Labor Development and Integration) OY3 | 4001 | FFP | |
| RMWT LEO GEPs (Labor Development and Integration) O4 | 5001 | FFP | |
| RMWT LEO GEPs (Labor Maintenance) Base | 0002 | FFP | |
| RMWT LEO GEPs (Labor Maintenance) OY1 | 2002 | FFP | |
| RMWT LEO GEPs (Labor Maintenance) OY2 | 3002 | FFP | |
| RMWT LEO GEPs (Labor Maintenance) OY3 | 4002 | FFP | |
| RMWT LEO GEPs (Labor Maintenance) O4 | 5002 | FFP | |
| RMWT LEO GEPs (Civil Engineering) Base | 0003 | FFP | |
| RMWT LEO GEPs (Civil Engineering) OY1 | 2003 | FFP | |
| RMWT LEO GEPs (Civil Engineering) OY2 | 3003 | FFP | |
| RMWT LEO GEPs (Civil Engineering) OY3 | 4003 | FFP | |
| RMWT LEO GEPs (Civil Engineering) O4 | 5003 | FFP | |
| Labor TOTAL | $0.00 | ||
| RMWT LEO GEPs (Material) Base | 0004 | FFP | |
| RMWT LEO GEPs (Material) OY1 | 2004 | FFP | |
| RMWT LEO GEPs (Material) OY2 | 3004 | FFP | |
| RMWT LEO GEPs (Material) OY3 | 4004 | FFP | |
| RMWT LEO GEPs (Material) O4 | 5004 | FFP | |
| Material TOTAL | $0.00 | ||
| ODCs - Base | 0005 | CR | $300,000.00 |
| ODCs - OY1 | 2005 | CR | $25,000.00 |
| ODCs - OY2 | 3005 | CR | $25,000.00 |
| ODCs - OY3 | 4005 | CR | $25,000.00 |
| ODCs - O4 | 5005 | CR | $15,000.00 |
| ODC TOTAL | $390,000.00 | ||
| Travel - Base | 0006 | CR | $280,000.00 |
| Travel - OY1 | 2006 | CR | $37,500.00 |
| Travel - OY2 | 3006 | CR | $37,500.00 |
| Travel - OY3 | 4006 | CR | $37,500.00 |
| Travel - O4 | 5006 | CR | $25,000.00 |
| Travel TOTAL | Cost Reimb | Cost Reimb | $417,500.00 |
| GFP Base | |||
| GFP Option | |||
| GFP Total | $0.00 | ||
| Cost Reimb | Cost Reimb | Cost Reimb | |
| Total Price | Cost Reimb | Cost Reimb | $807,500.00 |
| Page 1 of 1 |
TO 01 Grand Forks
| Grand Forks | Instructions to Offerors: |
| 1. The "Company Name" should be reflected in Cell B13. | |
| 2. Fill in ONLY the yellow cells below. | |
| 3. This template should automatically calculate all costs by summing as appropriate. | |
| 4. The Offeror is responsible for the accuracy of the price template. | |
| 5. This Total Price shall be included in Price volume of the proposal (Volume IV). | |
| 6. Both the Other Direct Cost (ODC) CLINs have NTE ceilings | |
| 7. The price for the Base (31 Mar 2027 - 30 Mar 2028), Option Year One (1) (31 Mar 2028 - 30 Mar 2029), Option Year Two (2) (31 Mar 2029 - 30 Mar 2030), Option Year Three (3) (31 Mar 2030 - 30 Mar 2031), Option Four (4) (31 Mar 2031 - 30 Sep 2031). |
Shall include all costs necessary to meet Labor Development and Integration, Labor Maintenance, Civil Engineering, and Material.
*Note - Please do not change any of the values that have been provided, input proposed prices in the yellow cells only on this tab.
| _________ Price Summary | |||
| (Company Name) | |||
| Contract Number | |||
| CLIN Description | CLIN | CLIN Type | Total Price |
| RMWT LEO GEPs (Labor Development and Integration) Base | 0001 | FFP | |
| RMWT LEO GEPs (Labor Development and Integration) OY1 | 2001 | FFP | |
| RMWT LEO GEPs (Labor Development and Integration) OY2 | 3001 | FFP | |
| RMWT LEO GEPs (Labor Development and Integration) OY3 | 4001 | FFP | |
| RMWT LEO GEPs (Labor Development and Integration) O4 | 5001 | FFP | |
| RMWT LEO GEPs (Labor Maintenance) Base | 0002 | FFP | |
| RMWT LEO GEPs (Labor Maintenance) OY1 | 2002 | FFP | |
| RMWT LEO GEPs (Labor Maintenance) OY2 | 3002 | FFP | |
| RMWT LEO GEPs (Labor Maintenance) OY3 | 4002 | FFP | |
| RMWT LEO GEPs (Labor Maintenance) O4 | 5002 | FFP | |
| RMWT LEO GEPs (Civil Engineering) Base | 0003 | FFP | |
| RMWT LEO GEPs (Civil Engineering) OY1 | 2003 | FFP | |
| RMWT LEO GEPs (Civil Engineering) OY2 | 3003 | FFP | |
| RMWT LEO GEPs (Civil Engineering) OY3 | 4003 | FFP | |
| RMWT LEO GEPs (Civil Engineering) O4 | 5003 | FFP | |
| Labor TOTAL | $0.00 | ||
| RMWT LEO GEPs (Material) Base | 0004 | FFP | |
| RMWT LEO GEPs (Material) OY1 | 2004 | FFP | |
| RMWT LEO GEPs (Material) OY2 | 3004 | FFP | |
| RMWT LEO GEPs (Material) OY3 | 4004 | FFP | |
| RMWT LEO GEPs (Material) O4 | 5004 | FFP | |
| Material TOTAL | $0.00 | ||
| ODCs - Base | 0005 | CR | $300,000.00 |
| ODCs - OY1 | 2005 | CR | $25,000.00 |
| ODCs - OY2 | 3005 | CR | $25,000.00 |
| ODCs - OY3 | 4005 | CR | $25,000.00 |
| ODCs - O4 | 5005 | CR | $15,000.00 |
| ODC TOTAL | $390,000.00 | ||
| Travel - Base | 0006 | CR | $280,000.00 |
| Travel - OY1 | 2006 | CR | $37,500.00 |
| Travel - OY2 | 3006 | CR | $37,500.00 |
| Travel - OY3 | 4006 | CR | $37,500.00 |
| Travel - O4 | 5006 | CR | $25,000.00 |
| Travel TOTAL | Cost Reimb | Cost Reimb | $417,500.00 |
| GFP Base | |||
| GFP Option | |||
| GFP Total | $0.00 | ||
| Cost Reimb | Cost Reimb | Cost Reimb | |
| Total Price | Cost Reimb | Cost Reimb | $807,500.00 |
| Page 1 of 1 |
Material I-E
| Attachment 7.d — Material Inclusions/Exclusions | ||
| Government-provided pricing direction for the Attachment 7.d Material worksheet. This worksheet is not offeror-completed. | ||
| Purpose | State the ancillary material elements included in, excluded from, Government-furnished for, or not required with the Material worksheet FFP unit prices. | |
| Scope limit | Do not use this worksheet to allocate labor or services, including installation, integration, configuration, testing, training, maintenance, warranty-service labor, travel, escort, staging, or logistics support. | |
| Completion | Government completes Column B before release. Use Column C only when an item-specific exception or boundary statement is needed. | |
| Ancillary Material Element | Government Treatment | Government Direction / Boundary / Item-Specific Exception |
| Manufacturer warranty | Included in Material Unit Price | Excludes labor based-pricing including warranty-service labor, removal/reinstallation, testing, travel, and support labor. |
| Initial spares and consumables | Not Required | Spares, when required, will be addressed by relevant task order direction. |
| Item-specific special tools and test equipment | Not Required | Item specific tools and test equipment will not be required in Attachment 7d Material tab pricing. |
| Item-specific documentation, software, firmware, and licenses | Included in Material Unit Price | Manuals, configuration media, embedded software/firmware, and required item-specific licenses are included in Attachment 7d Material tab pricing. Excludes ongoing subscriptions unless expressly stated. |
| Logistics (Packing, freight, and delivery of material) | Excluded—Priced Elsewhere | Packing, freight, and delivery of material is priced separately using the provided ODC plug value. Excludes escort, staging, installation, and all other labor. |
| Material Worksheet Direct Labor | Excluded—Priced Elsewhere | All labor costs affiliated with items in the Attachment 7d Material Worksheet should be captured in the associated labor CLINS (x001-x003) |
| General exclusion: Unless expressly stated above, post-acceptance replenishment, replacement material, technology refresh, and obsolescence management are not included in Material worksheet FFP unit prices. | ||
| Dropdown selections for Column B: Included in Material Unit Price; Excluded—Priced Elsewhere; Government-Furnished; Not Required. Replace all TBD—Government Direction entries before release. |
Pricing Certification
| PRICING CERTIFICATION |
| INSTRUCTIONS: Complete ONLY the yellow cells. Select Yes or No in the dropdown. Do not modify the certification text. |
| Offeror Completion |
| Offeror Name |
| Authorized Representative |
| Title |
| Date |
| Conflict or ambiguity identified in price volume Narrative and Methodology file? |
| Narrative page number(s), if Yes |
| Certification |
| The Offeror certifies that: (1) its proposed Basic IDIQ and TO 1 prices are complete and include all costs necessary to perform the applicable SOW and TRD requirements; (2) it has not knowingly duplicated pricing of the same defined material, labor, installation, integration, test, documentation, warranty, spare, support-equipment, logistics, or other supporting element in more than one proposed pricing location; (3) common Basic IDIQ scope and TO 1-specific incremental scope are priced only in their respective applicable pricing locations; and (4) proposed prices are consistent with the Price Volume, Technical Volume, and Unpriced BOE. |
| Certification Signature |
| Authorized Representative |
| Title |
| Date |
| Yellow cells are offeror-completed. |