Attachment 7.c. RMWT LEO GEPs Unpriced BOE Template IDIQ Base.xlsx

XLSX spreadsheet 44 KB Posted

Attached to
Request for Proposal (RFP) - Resilient Missile Warning Tracking (RMWT) Low Earth Orbit (LEO) Ground Entry Points (GEPs)
Solicitation number
FA240126R0003
Issued by

About this file

This is an Unpriced Basis of Estimate (BOE) template for an Indefinite Delivery Indefinite Quantity (IDIQ) base contract under solicitation FA240126R0003 for the Resilient Missile Warning Tracking (RMWT) Low Earth Orbit (LEO) Ground Entry Points (GEPs) effort. The template provides standardized instructions and formatting for contractors to submit detailed cost estimates supporting their technical proposals.

The template requires contractors to submit BOE documentation organized by Work Breakdown Structure (WBS), Contract Line Item Numbers (CLINs), and Statement of Work (SOW) paragraphs. Contractors must complete eight information blocks: WBS/CLIN/SOW identification; period of performance and task dates; WBS element descriptions defining scope and relationships; basis of estimate methods (analogy, expert judgment, parametric estimates, or other); detailed method justifications including assumptions and cost drivers; labor information by performing company and labor category; Other Direct Cost (ODC) and material descriptions with references to Bill of Materials (BOM); and ground rules, assumptions, and additional information impacting proposed amounts. The template includes separate tabs for time-phased labor estimates by CLIN and fiscal year (FY27-FY31), unpriced BOMs organized by SOW task with item descriptions and quantities, and travel documentation with detailed itineraries including origin, destination, number of travelers, duration, and costs. The six CLINs addressed are: CLIN 001 (Development Labor), CLIN 002 (Maintenance Labor), CLIN 003 (Civil Engineering), CLIN 004 (Material), CLIN 005 (ODCs), and CLIN 006 (Travel). Contractors must ensure consistency between BOE structures, CLIN structures, subcontractor proposals, and technical proposal descriptions, with all discrepancies explained and reconciled.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BOE Template Instructions

UNCLASSIFIED
Block NumberBlock DescriptionBlock Instructions
ALLBOE TemplateThis is a template and is does not contain all tabs required. Please follow the instructions below.
Block 1WBS, CLIN, SOW Level 3 Number and TitleEnter the CLIN #/Title Associated with the BOE. The BOE shall fully and completely support the CLIN structure contained in the RFP. Any variation between the BOE and CLIN Structure shall be explained in the Contractor's proposal to ensure that the BOE and CLIN Structures are reconcilable. Enter the WBS # and SOW Paragraph(s). In the case of expert judgement the contractor shall provide the credentials of persons providing extimates. In the case of analogy, the contractor shall describe rationale for why the analogous program is appropriate and any factors used in determining estimates.
Block 2Period of Performance and Task Start/StopEnter the start date of the items cited in Block 1, also enter the Period of Performance.
Block 3WBS Element (Level 3/4) DescriptionWBS element descriptions shall identify the WBS element scope, and specific tasks. The WBS element description shall also describe the relationship of this WBS element scope with others in terms of scope (what is in scope of this WBS element and what is not in scope of this WBS element and which related WBS element the other scope is in).
Block 4Basis of Estimate Method(s)Select the BOE method used for the estimated resources necessary to complete the effort used from list provided. The BOE method shall be fully and completely described and justified in Block 5.
Block 5Method JustificationEnter the justification or references for use of the BOE method(s) listed in Block 4. BOE justifications shall include, but is not limited to the Contractor's rationale for using a particular BOE method, related assumptions, and other factors. Parametric cost estimates and/or cost estimating relationships shall be accompanied by a description of the inputs, equations, and/or models along with any unique parameter values. Commercial and/or propriety cost models used to generate a BOE shall be accompanied by a clear and concise description of inputs, parameters, key decision variables, consumption metrics, and common usage, indicating the Contractor's rationale for using the model. When a commercial model is used, include the model name, vendor, and version number. In the case of expert judgment the contractor shall provide the credentials of personnel providing estimates. In the case of analogy, the contractor shall provide rationale for why the analagous program is appropriate and any factors used in determining estimates.
Block 6Labor InformationEnter the name of the company(ies) responsible for performing the work associated with the item(s) cited in Block 1.
Block 7Other Direct Cost (ODC) and/or Material DescriptionEnter a description of ODCs associated with the WBS or SOW task description cited in Block 1. Ensure ODCs are not also included in the indirect expense pools or other cost categories. Enter "N/A" if there are no ODCs associated with the WBS or SOW tasks description cited in Block 1. Enter a description of material costs support the WBS or SOW task description cited in Block 1. Reference the appropriate sections in the BoM. Material cost descriptions shall include direct and indirect material costs.
Block 8Ground Rules, Assumptions, and Additional InformationEnter Ground Rules, Assumptions, and Additional Information having significant impact on proposed amounts. The information shall provide a clear and complete understanding of how the estimate was derived. Narratives may include descriptions of how the BOE was developed, known constraints, range of possible estimates, and confidence levels associated with the final estimate. Include areas such as "ATP" approval dates and delivery schedules; availability of information, hardware, software, facilities, and other resources required of the Government; technical performance parameters; design and development constraints, whether imposed by the Government or self-imposed by the Contractor (e.g. security); and assumptions for key rates and factors. As the Contractor deems necessary, describe resources required by the Government (e.g. GFE and property including estimated cost if required for Contractor's technical approach); and key technical and management requirements driving cost whether imposed by the Government or self-imposed by the Contractor. In general, the Contractor shall describe how each Ground Rule or Assumption impacts the proposed amount and must identify those Ground Rules or Assumptions that may result in increased amounts. Descriptions of tasks and technical approaches contained within the BOE shall be consistent with those included in other portions of the proposal. The Contractor shall provide descriptions that are consistent with those contained within Subcontractor, interdivisional, or vendor proposals; any differences or discrepancies must be identified, described, and resolved. Lastly, this Block is reserved for additional information the Contractor deems necessary to fully describe the BOE.
Time Phased Estimate Tab(s)Time Phased Estimates by CLIN and WBS ElementEnter time phased estimates for each labor CLIN by WBS elements. Time phased tabs shall be consistent with the cost volume time phasing e.g. monthly by GFY.
Travel TabTravelProposed travel shall be supported by trip description, detailed itineraries to include origin, destination, number of travelers, trip duration, airfare, car rental and lodging (IAW Joint Travel Regulations)
BOM TabUnpriced BOMOfferor shall provide an itemized Bill of Materials (BOM) to include item description and quantity. The Offerors BOM shall be proposed by SOW task. The BOM shall describe the material in terms defined by FAR 45.101, such as equipment, material, special test equipment, special tooling and other listing as needed.

BOE Template

Basis of Estimate for FA240126R0003
Section 1: Basis of Estimate Proposal References
Block 1.

WBS: X.X.X:

CLIN Number(s) SOW Paragraph Number(s) Block 2.

Period of Performance:

mm/dd/yyyy-mm/dd/yyyy

Task Start/Task Stop:

mm/dd/yyyy-mm/dd/yyyy

Block 3.

WBS Element Description:

Section 2: Basis of Estimate
Block 4.

Basis of Estimate Method(s)- place an X in the [ ] for method applied. Describe what was used and why this was selected as the appropriate method in the Method Justification Section.

Analogy [ ] Expert Judgement [ ] Parametric Cost Estimate/Cost Estimating Relationship [ ] Other [ ]

Block 5.

Method Justification:

Block 6. Labor Information
Performing CompanyLabor CategoryCLINSOW (Level 3) Reference(s)FY27FY28FY29FY30FY31Total Hours

Block 7.

Other Direct Cost (ODC) and/or Material Description:

Block 8.

Ground Rules, Assumptions and Additional Information:

CLIN Labor Summary

Total Proposed Labor Hours by CLIN and GFY
CLINFY27FY28FY29FY30FY31
CLIN 001 - RMWT LEO GEPs Labor (Development)
CLIN 002 - RMWT LEO GEPs Labor (Maintenance)
CLIN 003 - RMWT LEO GEPs Civil Engineering
CLIN 004 - RMWT LEO GEPs Material
CLIN 005 - RMWT LEO GEPs ODCs
CLIN 006 - RMWT LEO GEPs Travel
Total

CLIN001 Summary

CLIN 001 - RMWT LEO GEPs Labor (Development)
GFYFY 27FY 27FY 27FY 27FY 27FY 27FY 27FY 27FY 27FY 27FY 28FY 28FY 28FY 28FY 28FY 28FY 28FY 28FY 28FY 28FY 28FY 28FY29FY29FY29FY29FY29FY29FY29FY29FY29FY29FY29FY29FY30FY30FY30FY30FY30FY30FY30FY30FY30FY30FY30FY30FY31FY31
Contract PeriodBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBase
Month (if after the first identify the day)DecJanFebMarAprMayJunJulAugSepOctNovDecJanFebMarAprMayJunJulAugSepOctNovDecJanFebMarAprMayJunJulAugSepOctNovDecJanFebMarAprMayJunJulAugSepOctNov
Labor HoursCLIN 1 Summary by CWBS Element
WBS x.x.x
WBS y.y.y
WBS z.z.z

CLIN002 Summary

CLIN 002 - RMWT LEO GEPs Labor (Maintenance)
GFYFY 27FY 27FY 27FY 27FY 27FY 27FY 27FY 27FY 27FY 27FY 28FY 28FY 28FY 28FY 28FY 28FY 28FY 28FY 28FY 28FY 28FY 28FY29FY29FY29FY29FY29FY29FY29FY29FY29FY29FY29FY29FY30FY30FY30FY30FY30FY30FY30FY30FY30FY30FY30FY30FY31FY31
Contract PeriodBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBase
Month (if after the first identify the day)DecJanFebMarAprMayJunJulAugSepOctNovDecJanFebMarAprMayJunJulAugSepOctNovDecJanFebMarAprMayJunJulAugSepOctNovDecJanFebMarAprMayJunJulAugSepOctNov
Labor HoursCLIN 2 Summary by CWBS Element
WBS x.x.x
WBS y.y.y
WBS z.z.z

CLIN003 Summary

CLIN 003 - RMWT LEO GEPs Civil Engineering
GFYFY 27FY 27FY 27FY 27FY 27FY 27FY 27FY 27FY 27FY 27FY 28FY 28FY 28FY 28FY 28FY 28FY 28FY 28FY 28FY 28FY 28FY 28FY29FY29FY29FY29FY29FY29FY29FY29FY29FY29FY29FY29FY30FY30FY30FY30FY30FY30FY30FY30FY30FY30FY30FY30FY31FY31
Contract PeriodBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBase
Month (if after the first identify the day)DecJanFebMarAprMayJunJulAugSepOctNovDecJanFebMarAprMayJunJulAugSepOctNovDecJanFebMarAprMayJunJulAugSepOctNovDecJanFebMarAprMayJunJulAugSepOctNov
Labor HoursCLIN 3 Summary by CWBS Element
WBS x.x.x
WBS y.y.y
WBS z.z.z

CLIN004 CLIN005 Unpriced BOM

Unpriced BOM Template Amplifying CLIN 0004 Material CLIN 0005 Items
WBSMaterial/ItemQuantityPurpose/RationaleOrdering DateDate of Need

CLIN005 Labor Summary

CLIN 005 - RMWT LEO GEPs ODCs Labor
GFYFY 27FY 27FY 27FY 27FY 27FY 27FY 27FY 27FY 27FY 27FY 28FY 28FY 28FY 28FY 28FY 28FY 28FY 28FY 28FY 28FY 28FY 28FY29FY29FY29FY29FY29FY29FY29FY29FY29FY29FY29FY29FY30FY30FY30FY30FY30FY30FY30FY30FY30FY30FY30FY30
Contract PeriodBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBaseBase
Month (if after the first identify the day)DecJanFebMarAprMayJunJulAugSepOctNovDecJanFebMarAprMayJunJulAugSepOctNovDecJanFebMarAprMayJunJulAugSepOctNovDecJanFebMarAprMayJunJulAugSep
Labor HoursCLIN 5 Summary by CWBS Element
WBS x.x.x
WBS y.y.y
WBS z.z.z

CLIN006 Travel

RMWT LEO GEPs Travel Itenerary
Trip DescriptionDestinationGFYDuration (Nights)Number of Travelers