EXHIBIT E - Past Performance Questionnaire 36C24221R0008.docx

DOCX document 127 KB Posted

Attached to
Y1DA--36C24221R0008 is in replacement of 36C24220R0115 630-17-101 REPLACE COOLING TOWERS MANHATTAN 630-16-101 Replace Chillers Ph. II
Solicitation number
36C24221R0008
Issued by

About this file

This notice solicits proposals for a service-disabled veteran owned small business set-aside contract to replace cooling towers and chillers at the New York Harbor Healthcare System Manhattan Campus. The scope of work involves selective demolition, supply and installation of new steel dunnage, cooling towers, piping, valves, outdoor lighting and electrical equipment. It also includes selective demolition, supply and installation of new concrete pads, centrifugal chillers, piping, valves and electrical equipment. The cost estimate range is $5 million to $10 million. The period of performance is 800 calendar days from notice to proceed. Proposals are due in hard copy by the date specified in the solicitation, which will be released on or about October 29, 2020. Respondents must be registered in SAM, D&B, and VIP and verified as a SDVOSB by the time of submission. The point of contact is Sharon Pierce at the email provided.

View the file

Other files

File Type Posted
36C24221R0008 0008.docx DOCX document
36C24221R0008 0007.docx DOCX document
36C24221R0008 0006.docx DOCX document
36C24221R0008 0005.docx DOCX document
NY 20210003 01-01-2021.pdf PDF
36C24221R0008 0004.docx DOCX document
Replace Cooling Towers Structural Drawings 630-17-101.pdf PDF
36C24221R0008 0003.docx DOCX document
36C24221R0008 0002.docx DOCX document
Replace Chillers Ph. II 630-16-101 Drawings Part 1.pdf PDF
Replace Chillers Ph. II 630-16-101 Specs Part 2.pdf PDF
Replace Chillers Ph. II 630-16-101 Specs Part I.pdf PDF
Replace Chillers Ph. II 630-16-101 Drawings Part 2.pdf PDF
Replace Cooling Towers 630-17-101 Drawings Part 1.pdf PDF
Replace Cooling Towers 630-17-101 Specs Part 2.pdf PDF
Replace Cooling Towers 630-17-101 Drawings Part 3.pdf PDF
Replace Cooling Towers 630-17-101 Drawings Part 2.pdf PDF
36C24221R0008 0001.docx DOCX document
Replace Cooling Towers 630-17-101 Specs Part 1.pdf PDF
Replace Cooling Towers 630-17-101 Drawings Part 4.pdf PDF
EXHIBIT D - Sample Transmittal Letter for Past Performance Evaluation Questionnaire 36C24221R0008.docx DOCX document
36C24221R0008.docx DOCX document
EXHIBIT B - Subcontractor Information and Consent Form 36C24221R0008.docx DOCX document
EXHIBIT C - Calculation of Self-Performed Work 36C24221R0008.docx DOCX document
EXHIBIT A - Past Performance Relevancy Questionnaire 36C24221R0008.docx DOCX document
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NETWORK CONTRACTING OFFICE 2

Albany/Bath/Bronx/Canandaigua/Northport/Syracuse Medical Centers Hudson Valley/New Jersey/New York Harbor Healthcare Systems WNY Upstate New York Healthcare System

Past Performance Questionnaire for: 36C24221R0008 Replace Cooling Towers/Chillers Ph. II

INSTRUCTIONS TO OFFEROR

Complete the CONTRACTOR INFORMATION section, below (type answers into light blue shaded boxes). Save the document. Send an electronic or hard copy print of the form to each of your reference contacts, asking them to please complete the form and submit it according to the instructions, below.

Company Name

Street Address

Point of Contact (POC)

City

POC Phone Number

State

Reference Project Title

Zip Code

Contract Period of Performance (start to finish):

Email

Contract Number

Contract Dollar Value

Description of Work

Role of Contractor on This Project (check appropriate box)
|_| Prime Contractor |_| Sub-contractor |_| Key Personnel

INSTRUCTIONS TO REFERENCE CONTACT

The contractor named above is submitting a proposal for a United States Department of Veterans Affairs contract, and has sent this form to you as a past performance reference contact. Please complete the following pages in full (all areas shaded in light yellow, below). Once completed, please send the form to the Contracting Officer via postal mail or email directly to:

Department of Veterans Affairs James J. Peters VA Medical Center ATTN: Sharon Pierce/ 36C24221R0008 130 W. Kingsbridge Road Bronx, NY 10468 Email address: Sharon.Pierce@va.gov

Please return the completed form ASAP, but no later than 2:00 pm local time, December 1, 2020.

If you have any questions, please contact the Contracting Officer: Sharon.Pierce@va.gov.

RESPONDENT INFORMATION [completed by Reference Contact]

Company Name

Street Address

POC Name

City

Phone Number

State

Email

Zip Code

PERFORMANCE INFORMATION: Choose the number on the scale of 0 (Neutral) to 5 (Exceptional) that most accurately describes the contractor’s performance or situation. PLEASE PROVIDE AN EXPLANATION FOR THE OVERALL RATING in the Remarks section, below.

0
1
2
3
4
5
NEUTRAL
UNACCEPTABLE
MARGINAL
ACCEPTABLE
VERY GOOD
OUTSTANDING
No record of past performance, or not applicable or the record is inconclusive.
Performance did not meet most contractual requirements. There were serious problems and the contractor’s corrective actions were ineffective.
Performance did not meet some contractual requirements. There were problems, some of a serious nature, for which corrective action was only marginally effective.
Performance met most contractual requirements. There were some minor problems and corrective actions taken by the contractor were satisfactory.
Performance met all contract requirements and exceeded some to the government’s benefit. There were a few minor problems, which the contractor resolved in a timely, effective manner.
Performance exceeded all contract requirements. There were no problems.
The Contractor …
0
1
2
3
4
5

QUALITY – MANAGEMENT & WORKMANSHIP

1.
Provided experienced managers and supervisors with the technical and administrative abilities needed to meet contract requirements.
|_|
|_|
|_|
|_|
|_|
|_|
2.
Demonstrated ability to hire, maintain, and replace, if necessary, qualified construction personnel during the contract period.
|_|
|_|
|_|
|_|
|_|
|_|
3.
Provided and followed approved quality control plan and/or inspection procedures to meet contract requirements.
|_|
|_|
|_|
|_|
|_|
|_|
4.
Corrected deficiencies in timely manner and pursuant to their quality control procedures.
|_|
|_|
|_|
|_|
|_|
|_|
5.
Submittals clearly identified the proposed item IAW the specifications and drawings.
|_|
|_|
|_|
|_|
|_|
|_|
6.
Suggested alternative approaches to problems.
|_|
|_|
|_|
|_|
|_|
|_|

TIMELINESS AND ADHERENCE TO SCHEDULE

0
1
2
3
4
5
7.
Contractor provided timely notices of possible delays/schedule revisions.

REMARKS:

|_|
|_|
|_|
|_|
|_|
|_|
8.
Timeliness in submitting submittals and reports and responding to agency inquiries, RFP's, etc.
|_|
|_|
|_|
|_|
|_|
|_|
9.
Developed realistic and met approved progress schedules.
|_|
|_|
|_|
|_|
|_|
|_|

BUSINESS PRACTICES/CUSTOMER RELATIONSHIP AND ABILITY TO PERFORM

10.
Displayed initiative to solve problems.
|_|
|_|
|_|
|_|
|_|
|_|
11.
How well did the contractor work independent of Government guidance, oversight and assistance?
|_|
|_|
|_|
|_|
|_|
|_|
12.
Subcontractors / tradesmen were adequately managed and coordinated. Explain any subcontracting issues (positive or negative) that impacted the performance of your contract(s).
|_|
|_|
|_|
|_|
|_|
|_|
13.
For contract changes, contractor provided timely and realistic change order proposals.
|_|
|_|
|_|
|_|
|_|
|_|

COMPLIANCE & SAFETY

0
1
2
3
4
5
14.
Reports (i.e., daily, test, logs) / records were submitted completely and accurately satisfy the requirement.
|_|
|_|
|_|
|_|
|_|
|_|
15.
Applicable to Federal Contracts –Contractor complied with applicable Federal Laws and Regulations such as Construction Wage Rate Requirements – timely payrolls and compliance; Drug-Free Workplace; Environmental Regulations and Use of Recovered Materials; Executive Order 13101 Greening the Government.
|_|
|_|
|_|
|_|
|_|
|_|
16.
Contractor’s safety program was in compliance with federal regulations. Contractor implemented and followed their safety plan and ran a “safe jobsite”.
|_|
|_|
|_|
|_|
|_|
|_|

INFECTION CONTROL

17.
Contractor had an Infection Control Process in place and complied with agency Infection Control Requirements.
|_|
|_|
|_|
|_|
|_|
|_|

OVERALL CUSTOMER SATISFACTION

18.
Demonstrated reasonableness in modifications cost proposal.
|_|
|_|
|_|
|_|
|_|
|_|
19.
Was the contractor ever issued a cure or show cause notice under the referenced contract? If yes, explain outcome in “remarks.”
|_|
YES
|_|
NO
20.
Would you award another contract to this contractor? If not, please explain in “remarks.”
|_|
YES
|_|
NO
OVERALL PERFORMANCE RATING:
|_|
|_|
|_|
|_|
|_|
|_|

REMARKS (Please use as much space as is needed – the box will expand as you type).

I hereby certify that the information that I have reported above is accurate to the best of my knowledge.

Printed Name

E-mail address

Business Title

Signature

Date image1.PNG

File details come from the government source that posted it. Updated .