This notice describes a federal solicitation for replacement of cooling towers and chillers at a Department of Veterans Affairs medical center. The solicitation seeks to replace existing cooling towers and perform selective demolition and installation of new towers, piping, valves, lighting and electrical equipment. It also aims to replace chillers by performing selective demolition of chiller plant equipment and installation of new concrete pads, centrifugal chillers, piping, valves and electrical systems. Offerors must be registered in BetaSAM, D&B, and VIP databases and verified as a Service-Disabled Veteran Owned Small Business. The period of performance is 800 calendar days from notice to proceed. The response due date is included in the solicitation to be released on October 29, 2020. Hard copy submissions are required and must be received at the address in the solicitation by the stated due date and time.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7.
ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF
PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE
OF YOUR
ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERE
D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED
STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF
CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF
SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 02-05-2021 630-17-101/16-101 36C242 Department of Veterans Affairs Network Contracting Office 2 James J. Peters VA Medical Center 130 West Kingsbridge Road Bronx NY 10468-3904 36C242 Department of Veterans Affairs James J. Peters VA Medical Center Network Contracting Office 2 130 West Kingsbridge Road Bronx NY 10468-3904 To all Offerors/Bidders
36C24221R0008 11-18-2020
X X
Replace Cooling Towers 630-17-101 Replace Chillers Ph. II 630-16-101 Project Amendment 0008
This amendment is to clarify RFI response. There is no pre-purchased equipment.
SEE ATTACHED
February 9, 2021 2:00PM ET remains the proposal due date and time.
END
Sharon Pierce Contracting Officer
RFI CLARIFICATIONS
COOLING TOWER REPLACEMENT
1. Drawings 5/M500 states CT cell basins to be connected by flumes. This is not available. Manufacturer as well as drawing M103 suggest equalizer line is to be used. No equalizer line is shown on drawing M-102, please indicate equalizer line sizing, material and indicate if any valves are required. Response: Flume is not necessary if equalizer line is being used. Equalizer line size is shown on the piping diagram on sheet m400
1. 8” Condenser Water Bypass indicated on flow diagram M400 is not shown on M102-M103 Piping drawings. Please indicate location for bypass. Control points list suggest this may be a 3 way control valve, please clarify and state whether this will be a full line size (24”) 3 way valve or an 8 inch 2-way modulating valve across the CWR & S main. Response: The condenser water bypass piping should be installed indoors in the mechanical room under the chiller project and connection points and location should be coordinated with the chiller plant drawings. Bypass line size should be 8” with two-way modulating valve.
1. Drawing 2/M103 Structural Steel for Tower already appears to be in conflict with 10” CWS branches from tower to main. Please review and advise if this would result in raising tower support steel height, or other method to avoid piping conflict. Response: There is no conflict with the structure.
1. Drawing 2/M103 indicates manual shut off valves for each cell on CWR and CWS and automatic control valve on CWR only. Flow diagram on drawing M400 CWR automated valve is shown and noted also, but it is not clear if there an automated control valve for the 10 inch CWS branch to each cell on that drawing and it is not shown on sheet M102 or M103 section. Response: There should be an automated control valve on the CWS pipe as well.
1. The flow diagram on Drawing M400 does not indicate 24” automated shut off valves shown on Drawing M102 please confirm these are to be included or can an automated valve schedule be generated similar to chiller replacement valve schedule. BAE Response: These are to be included as shown.
1. On drawing M400 flow diagram it appears as if manual shut off valves are located in the CWS and CWR mains between tower cells CT-1B and CT-1C and Tower Cells CT-2B and CT-2C. These valves do not appear in drawing M-102. Please advise if they are required. BAE Response: There is no shut-off valve in these location. Key note 3 calls it a drain hose.
Chiller Replacement Project
1. Please clarify valving for each chiller. Using drawing MP-101 and M-504 it appears that at each chiller it appears that on the CWS and CHR legs to each chiller there will be 1 manual shut off valve only, and on the CHS & CWR legs it appears there will be a manual shut off valve, followed by an automated valve, followed by another shut off valve on each leg. The flow diagram M-502 indicates only one manual shut off valve on each chiller leg and one automated valve for CHS and CWR. The detail 3/M-503 does not correspond to either of the previous described arrangements either. The valves are correctly indicated on drawing M502. Drawing M504 shows the same valving, although the relative position of the automated and manual valves are reversed.
1. What is the size of the existing pressure relief vent line we are to tie the 3 new chiller relief lines into? Please confirm a new wall penetration is not required for additional venting. The handling of the refrigerant vent lines is indicated on Drawing M503, Note 2. A new wall penetration is not required.