About this file

This document is a Contract Progress Schedule form with detailed instructions for contractors on how to complete and submit the schedule. The form is designed to track and report the progress of work elements during a contract's performance period, requiring contractors to break down their project into major work elements, assign percentage completion values, and map out planned periodic progress across multiple weeks. Key instructions include:

Contractors must prepare two copies of the progress schedule, listing major work elements (such as excavation, concrete work, carpentry) with their corresponding percentage of total project completion. The form includes columns for tracking planned progress week by week, with the total work percentages required to equal 100%. Contractors are expected to submit the schedule to the Procurement Officer at the specified contract time, update it if contract modifications occur, and provide periodic "Contract Progress Reports" indicating work accomplished for each element. The schedule is critical for contract administration and may be used in connection with partial payment approvals.

View the file

Other files

File Type Posted
36C24826R0039 0006.pdf PDF
36C24826R0039 0005.pdf PDF
36C24826R0039 0005.pdf PDF
36C24826R0039 0004.pdf PDF
AE addendum OneDrive_2026-03-17.zip ZIP file
RFIs Combined 573-21-705 Final.xlsx XLSX spreadsheet
SAM SBA WD FL20260194.pdf PDF
36C24826R0039 0003.pdf PDF
Upgrade MCCs at Building 1 Bid Doc.pdf PDF
05 Updated SOW 573-21-705.docx DOCX document
Site Visit Presentation.pptx PPTX presentation
Site Visit 2 Attendance.pdf PDF
Updated Parking Policy.pdf PDF
RFIs Combined 573-21-705..xlsx XLSX spreadsheet
36C24826R0039 0002.pdf PDF
Site Visit 1 Attendance.pdf PDF
AEI Addendum Sheets.zip ZIP file
Exhibit B LOS Certification.doc DOC document
E-Wing Penthouse Repl MCCs As-Built.JPG JPG image
SAM DBA WD 20260002.pdf PDF
SAM WDDBA ALACHUA FL20260194.pdf PDF
36C24826R0039 0001.pdf PDF
S02 Solicitation 36C24826R0039 Final.pdf PDF
Exhibit F PPQ.docx DOCX document
Exhibit B LOS Certification Solicitation Version.doc DOC document
GNV AHUs 20s- Bid Docs Drawings.pdf PDF
GNV AHUs 20s Bid Doc Specifications.pdf PDF
Exhibit E Performance Relevancy Survey v2.docx DOCX document
Exhibit C EMR.docx DOCX document
Exhibit I Price Matrix.xlsx XLSX spreadsheet
Exhibit G Sub PP Consent.docx DOCX document
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT PROGRESS SCHEDULE

(See Contractor's Instructions on Reverse)

1. CONTRACT NO. 8. PROJECT TITLE 10. APPROVAL RECOMMENDED BY:

DATE SIGNED

PROCUREMENT

2. STARTING DATE

3. COMPLETION DATE 9. SUBMITTED BY:

4. PURCHASE REQUEST NO. DATE SIGNED CONTRACTOR'S NAME (Last, First, Middle Initial)

ADDRESS (Street, City, State, Zip Code)

CONTRACTOR'S SIGNATURE

11. APPROVED BY:

5. PROJECT NO. DATE SIGNED EXECUTIVE DIRECTOR

6. ACTUAL STARTING DATE

7. ACTUAL COMPLETION DATE

LINE

NO

A

WORK ELEMENTS %

C

WEEKS

D E F G H I J K L M N O P Q

Attch: 07

INSTRUCTIONS TO CONTRACTORS

1. Prepare two copies of Progress Schedule, in accordance with these instructions, and submit to the Procurement Officer at the time stated in the contract or as established by the Procurement Officer.

2. Blocks 1, 2, and 3. Enter the contract number, starting date, and completion date as shown on the contract.

3. Block 8. Enter the title of the project as shown on the contract.

4. Block 9. Enter name and address of your firm. The three copies submitted to the contracting officer must be dated and signed by the contractor or an authorized representative of the firm.

5. Lines 1 through 12. Major elements of work (whether unit price or lump sum contract) such as excavation, concrete work, carpentry, engineering, installation of communication electronic facilities, etc., will be shown in Column B in logical sequence and in sufficient detail to identify the element. If the contract calls for more than 11 work elements, additional copies of the progress schedule may be used as a continuation for the work elements.

6. The percentage of each listed work element to the complete job will be shown opposite each element in Column C. As an example, if 3 work elements are shown: excavation, concrete work, and backfill, and it is estimated that excavation is 50% of the total job, concrete 30%, and backfill 20%, these percentages will be shown opposite each element. The total must equal 100%.

7. Columns D through Q will be used to show planned periodic progress, as required by the contracting officer, during the period of the contract. Only the top half of the space under these columns will be used by contractors. Using the example cited above and assuming that the contract period for performance is 8 weeks, and it is planned to accomplish 10% of the excavation work the 1st week and 20% each week until excavation is complete, 10 would be shown in the upper half of Line 1 under Column D, 20 under Column E, and 20 under Column F for a total of 50%. If it is planned to accomplish the concrete work during the 4th, 5th, and 6th weeks in equal amounts, 10 would be entered under Columns G, H, and I on Line 2. Assuming the backfill will be accomplished during the 7th and 8th weeks, 10 would be entered under Columns J and K on Line 3. If the contract extends beyond 14 weeks, additional copies of AF Form 3064 may be used as a continuation of performance record.

8. Total amount of work planned at intervals as shown in Columns D through Q will be totaled and entered in the top half of the space under the appropriate column of Line 12. Again, using the example cited above, the totals under Columns D through K would read 10, 20, 20, 10, 10, 10, 10, 10 for a total of 100%. These totals will be used to plot an overlay graph using Lines 4 through 11, beginning with

Column D and extending to the right the number of columns (weeks) authorized by the contract for performance time.

9. In the event the contract is modified by the Executive Director under terms of the contract, changing the progress of work as originally scheduled, adding or deleting work or changing the original completion date, a revised progress schedule will be prepared and submitted to the contracting officer for approval. In preparing the revised schedule, the amount of work completed will be considered, together with the changed new completion date set forth in the contract modification. Considering these factors, the work under the contract will be rescheduled over the new total performance time in the same manner that the original schedule was prepared. The new completion date will be entered in Block 3. "First Revised Schedule," "Second Revised Schedule," etc., will be entered to the left of the form title. Time of submission of the revised schedule will be determined by the Procurement Officer.

10. At such intervals as may be established by the Procurement Officer, the contractor will submit to the Procurement Officer, "Contract Progress Report," indicating the percentage of work accomplished for each work element during the established reporting period. Accurate reports are of the utmost importance to the contractor and to the Government, since the percentage of completion, or progress, thus reported is used in administration of the contract and may be used in connection with approval of partial payments under the contract. Care should be taken to plan the work in such manner that it can be accomplished as stated in this schedule. If, for any reason, it becomes known that any part of the progress under this contract will be delayed, this fact should be reported to the

Procurement Officer immediately.