SECTION 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
1. CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
1.1 Contractor’s staging area requirements shall be discussed for each Task Order with the Government representative.
1.2 The Contractor is responsible for security of their own property and security of Government property when construction activities affect existing security measures.
1.3 The Contractor shall provide and maintain portable toilet facilities as required at the site for the use of Contractor and subcontractor personnel, as required by the EM 385-1-1. The units shall be emptied and cleaned at least once a week, or more often if required by the Contracting Officer. The doors to the unit shall be self-closing. Additionally, the toilet units shall be located out of public view as the site allows.
2. AVAILABILITY AND USE OF UTILITY SERVICES AT PROJECT/JOB SITE
2.1 Temporary Utilities. Provide temporary utilities required for construction when not available through the Government. Materials may be new or used, must be adequate for the required usage, not create unsafe conditions, and not violate applicable codes and standards.
2.2 Any utility outages, including but not limited to, electrical, mechanical, fire protection and plumbing systems, shall be coordinated at least 14 calendar days prior to proposed outages. Coordination will be documented on the appropriate outage request form (separate document for utilities and fire protection systems). Outages shall be scheduled to minimize interruptions to normal using agency operations.
2.3 Temporary Water Connection. Subject to available supply, the Government will make available to Contractor, from existing outlets and supplies, reasonable amounts of potable water without charge. Contractor shall reasonably conserve potable water furnished. Contractor, at its own expense, shall install and maintain necessary temporary connections, approved backflow devices, and distribution lines and shall remove the connections and lines prior to final acceptance of construction. All connections must be coordinated through American Water (AW) and DPW Utilities Branch.
2.4 Permanent Water or Sanitary Sewer Connections: The construction Contractor shall coordinate with AW for all exterior water and civil work within the project construction perimeter. Per Army directive memo for utilities privatization, AW shall perform all civil and water work related to the exterior water system outside and inside of the project construction perimeter up to the Point of Demarcation for their system. In all situations, AW shall procure and install water and sanitary sewer components that are separable from the rest of the site work and connect to the point of demarcation (POD). AW’s construction will be awarded through a modification to the water and wastewater systems privatization contract with Defense Logistics Agency (DLA). JBLM PW Utilities Branch will be responsible for all AW modifications with the point of contact Ms. Royanna Jackson 253-966-3282, royanna.e.jackson.civ@army.mil.
2.5 For all water and wastewater related work performed by the Contractor, inspection and acceptance by AW is required prior to Government acceptance. Acceptance through the Government will not occur without AW’s concurrence. AW requirements will govern the installation of the water or sanitary sewer service and Contractor must follow AW standards and requirements.
2.6 Cross Connections, Hydrants, Water System demolition shall be coordinated with AW.
2.7 Temporary Power Connections. Subject to available supply, the Government, without charge, shall make reasonable amounts of electric current available to the Contractor for performing work at the work area. The Contractor shall conserve electric current furnished. The Contractor at their own expense shall coordinate with the electrical system owner, City Light & Power (CLP), for temporary electrical connections.
2.8 Permanent Power Connections: The construction Contractor shall coordinate with CLP for all exterior electrical civil work within the project construction perimeter. Per Army directive memo for utilities privatization, CLP shall perform all civil and electrical work related to exterior electrical system outside of the project construction perimeter. In all situations, CLP shall procure and install electrical components that are separable from the rest of the site electrical system, make final terminations, and connect to the point of demarcation (POD). CLP’s construction will be awarded through a modification to the electrical distribution system privatization contract with Defense Logistics Agency (DLA). JBLM PW Utilities Branch will be responsible for all CLP modifications with the point of contact Ms. Royanna Jackson 253-966-3282, royanna.e.jackson.civ@army.mil.
2.9 For all power related work performed by the Contractor, inspection and acceptance by CLP is required prior to Government acceptance. Acceptance through the Government will not occur without CLP’s concurrence. CLP requirements will govern the installation of the electrical service and Contractor must follow CLP standards and requirements.
2.10 Temporary Power and Lighting. The Contractor shall provide construction power facilities in accordance with the safety requirements of the National Electric Code NFPA No. 70 and the SAFETY AND HEALTH REQUIREMENTS MANUAL EM 385-1-1. The Contractor, or its delegated subcontractor, shall enforce the safety requirements of electrical extensions for the work of subcontractor. Work shall be accomplished by journeyman electricians.
2.11 Construction Equipment. In addition to the requirements of SAFETY AND HEALTH REQUIREMENTS MANUAL, EM 385-1-1, temporary wiring conductors installed for operation of construction tools and equipment shall be either Type TW or THW contained in metal raceways, or shall be hard usage or extra hard usage multiconductor cord. Temporary wiring shall be secured above the ground or floor and shall not present an obstacle to persons or equipment. Open wiring may only be used outside of buildings, and then only in accordance with the provisions of the National Electric Code.
2.12 Obstruction Lighting of Cranes. Provide a minimum of 2 aviation red or high intensity white obstruction lights on temporary structures (including cranes) over 100 feet above ground level. Light construction and installation must comply with FAA AC 70/7460-1. Lights must be operational during periods of reduced visibility, darkness, and as directed by the Contracting Officer
2.13 Fire Protection. During the construction period, the Contractor shall provide fire extinguishers in accordance with the safety requirements of the SAFETY AND HEALTH REQUIREMENTS MANUAL, EM 385-1-1. The Contractor shall remove the fire extinguishers at the completion of construction. Provide temporary fire protection equipment for the protection of personnel and property during construction. Remove debris and flammable materials daily to minimize potential hazards.
3. HOUSEKEEPING AND CLEANUP
3.1 Remove construction debris, waste materials, packaging material and the like from the work site daily. Any dirt or mud which is tracked onto paved or surfaced roadways must be cleaned away. Store within the fenced area described above or at the supplemental storage area any materials resulting from demolition activities which are salvageable. Neatly stack stored materials not in trailers, whether new or salvaged.
4. EXCAVATION
4.1 Digging Permit. Before performing any onsite excavation on Joint Base Lewis-McChord, Contractor shall obtain a digging permit. The digging permit can be obtained at Directorate of Public Works, For more information, see the Public Works Digging Permit Desk web site at the following URL: https://home.army.mil/lewis-mcchord/index.php/my-Joint-Base-Lewis-Mcchord/all-services/directorate-public-works/dig-permits.
-- End of Section -- 01 50 00 - 2