Training Calendar Provider Implementation Plan Summary
This is a Training Implementation Plan (TRN-02) document for the Hawaii State Department of Education's Regional Kitchen Operational Readiness project, developed under IFB D27-055. The plan establishes a comprehensive training calendar and provider framework to qualify staff for the transition from centralized food production to a regional kitchen model serving approximately 85 schools statewide, with initial Phase I implementation targeting 20 schools in the Leilehua-Mililani-Waialua complex by June 2027. The document outlines 14 planned training events across multiple event types including onboarding orientations, classroom instruction, hands-on equipment training, operational practice sessions, and dry-run competency validations. Key training events include Food Safety/HACCP core training (EV-002), Regional Kitchen commercial equipment operation (EV-003), material handling equipment training (EV-004), menu and production tool training (EV-005), receiving and storage procedures (EV-007), dispatch and distribution training (EV-008), finishing kitchen receiving and equipment training (EV-009 and EV-010), traceability and recall tabletops (EV-011), emergency continuity planning (EV-012), and an integrated opening dry run (EV-013). The implementation plan intentionally defers specific dates until construction completion, equipment installation, staffing assignments, and contractor schedules are finalized, with all completion targets remaining dependent upon prerequisite operational readiness gates.
The Training Calendar establishes seven primary training providers: SFSB Internal (existing food-service and operational training), an Operational Support Contractor under executed D27-055 contract, Phase I Equipment Manufacturers/Vendors per awarded equipment contracts, Material Handling Equipment vendors per D27-023 solicitation, Hawaii Department of Health and other public agencies for food-safety training, authorized CPR/First Aid providers for required certifications, and State-approved Supervisors/Qualified Evaluators for competency validation. The plan incorporates eight dependency gates controlling training sequencing to prevent teaching draft procedures prematurely or scheduling hands-on training before actual equipment commissioning. Site activation rollouts are structured in four groups: Launch Phase I Regional Kitchen operations, Initial Phase I Year 1 Finishing Kitchens, Remaining Phase I Year 1 schools, and Phase I Year 2 schools, with training windows and competency sign-offs synchronized to facility readiness, equipment availability, staffing assignments, and approved standard operating procedures. The document emphasizes that provider assignment is evidence-based only, that hands-on competency should occur on real equipment when practicable, and that TRN-04 readiness evidence serves as the definitive validation that assigned staff can independently perform critical operational tasks before operational authorization.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Executive Summary
| TRN-02 | Training Implementation Snapshot | ||||
| Interim schedule/control plan. The calendar intentionally uses dependencies and completion targets rather than inventing dates before the facility, equipment, school-transition and contractor schedules are final. | ||||
| Planned Event Templates | Critical Events | Scheduled | Complete | Blocked Dependency Gates |
| 14 | 11 | 0 | 0 | 0 |
| Implementation Principle |
| 1. Exact dates are intentionally blank until the authoritative construction, equipment, staffing, school-transition and contractor schedules are available. |
| 2. Provider assignment must be evidence-based; listing a possible provider does not create an approval or procurement commitment. |
| 3. Hands-on equipment training and dry-run competency should occur on the real equipment/process when practicable. |
| 4. TRN-04 is the readiness evidence. TRN-02 is only the plan for getting people there. |
Training Calendar
| TRN-02 | Training Calendar / Provider Implementation Plan | ||||||||||||||||||||||
| Calendar shell synchronized to equipment, food-safety, menu, staffing, site-conversion and dry-run dependencies. Exact dates remain blank until authoritative construction/implementation schedules and provider availability are confirmed. | ||||||||||||||||||||||
| Event ID | Training ID | Training / Event | Audience | Event Type | Provider Type | Provider / Instructor | Phase | School / Site | Prerequisite Training | Primary Dependency | Dependency Type | Dependency Ready? | Planned Date | Actual Date | Planned Location | Capacity / Seats | Required Headcount | Completion Target | Priority | Status | Reschedule / Critical-Path Risk | Notes |
| EV-001 | TR-021 | RK/FK Role Transition Orientation | Mixed Audience | Onboarding / Orientation | SFSB Internal | TBD | Launch / Phase I | RK + initial FK sites | Final role/process baseline | Staffing / Assignment | TBD / Validate | TBD | Before role begins | High | Not Planned | Role/process clarity must precede detailed skill qualification. | ||||||
| EV-002 | TR-001/002 | Food Safety / HACCP / Sanitation Core Training | Mixed Audience | Classroom / Brief | TBD / Validate | TBD | Launch / Phase I | RK + initial FK sites | Role orientation | Final approved HACCP/SOP package | Approved SOP / HACCP | TBD / Validate | TBD | Before food handling under RK/FK process | Critical | Not Planned | Do not train final limits/procedures from draft controls. | |||||
| EV-003 | TR-006 | RK Commercial Equipment Vendor Training | RK Production | Hands-On Equipment | Equipment Manufacturer / Vendor | TBD | Launch / Phase I | Regional Kitchen | Food-safety core as applicable | Equipment installed/commissioned | Equipment Installation / Commissioning | TBD / Validate | Regional Kitchen | Before independent equipment operation | Critical | Not Planned | Training too early or before final commissioning reduces usefulness. | |||||
| EV-004 | TR-018/019 | Material Handling Equipment Training | Specialized Operators | Hands-On Equipment | Equipment Manufacturer / Vendor | TBD | Launch / Phase I | Regional Kitchen | Assigned operator / workplace prerequisites | MHE delivery and acceptance | Equipment Delivery | TBD / Validate | Regional Kitchen | Up to 7 for forklift vendor session per current MHE reference | Before equipment placed into State service | Critical | Not Planned | Current MHE reference requires formal, hands-on, supervised practice and equipment-specific evaluation. | ||||
| EV-005 | TR-004/005 | Menu / Recipe / Production Tool Training | RK Managers | Operational Practice | SFSB Internal | TBD | Launch / Phase I | Regional Kitchen | Role orientation | Authoritative menu and manager tool | Menu / Recipe Baseline | TBD / Validate | TBD | Before production pilot | Critical | Not Planned | Train from controlled MENU baseline only. | |||||
| EV-006 | TR-007 | Cooling / Blast-Chilling Process Qualification | RK Production | Operational Practice | Supervisor / Qualified Evaluator | TBD | Launch / Phase I | Regional Kitchen | Food-safety core + equipment training | Approved HACCP + commissioned cooling equipment | Approved SOP / HACCP | TBD / Validate | Regional Kitchen | Before live-style cooling trial | Critical | Not Planned | Should occur on actual equipment/process and feed competency record. | |||||
| EV-007 | TR-009/010 | RK Receiving / Storage / Inventory Training | RK Receiving / Warehouse | Operational Practice | SFSB Internal | TBD | Launch / Phase I | Regional Kitchen | Food-safety core | Receiving/inventory procedure ready | Operational Support Deliverable | TBD / Validate | Regional Kitchen | Before operational receiving trial | High | Not Planned | ||||||
| EV-008 | TR-012/013 | Dispatch / Distribution / Cart Handling Training | RK Dispatch / Logistics | Operational Practice | TBD / Validate | TBD | Launch / Phase I | Regional Kitchen | Food-safety core | LOG procedures + transport model ready | Operational Support Deliverable | TBD / Validate | Regional Kitchen | Before distribution dry run | Critical | Not Planned | ||||||
| EV-009 | TR-009/010/011 | FK Receiving / Inventory / Ordering Training | FK Managers | Operational Practice | TBD / Validate | TBD | PI-Y1 | Initial Phase I Year 1 schools | Food-safety core | Site ready + final receiving/inventory/ordering procedures | Site Construction / Access | TBD / Validate | At site or approved training location | Before first RK-supported delivery | Critical | Not Planned | Sequence by school transition date. | |||||
| EV-010 | TR-006/008 | FK Equipment / Rethermalization Training | FK Workers | Hands-On Equipment | Equipment Manufacturer / Vendor | TBD | PI-Y1 | Initial Phase I Year 1 schools | Food-safety core | FK equipment installed/commissioned | Equipment Installation / Commissioning | TBD / Validate | At finishing kitchen | Before retherm/service dry run | Critical | Not Planned | Use actual equipment when possible. | |||||
| EV-011 | TR-014 | Traceability / Recall / Foodborne Illness Tabletop | Mixed Audience | Dry-Run Competency Event | Supervisor / Qualified Evaluator | TBD | Launch / Phase I | RK + representative FK | Food-safety core | SAFE-03/04/05 ready | Approved SOP / HACCP | TBD / Validate | TBD | Before full implementation | Critical | Not Planned | Should produce SAFE-04 exercise evidence and corrective actions. | |||||
| EV-012 | TR-015 | Emergency / Continuity Tabletop | Mixed Audience | Dry-Run Competency Event | TBD / Validate | TBD | Launch / Phase I | RK + representative FK | Role orientation | Emergency/COOP procedure ready | Operational Support Deliverable | TBD / Validate | TBD | Before opening | Critical | Not Planned | Include logistics/site handoff scenarios applicable to final model. | |||||
| EV-013 | TR-020 | Integrated Opening Dry Run / Independent Competency Validation | Mixed Audience | Dry-Run Competency Event | Supervisor / Qualified Evaluator | TBD | Launch / Phase I | RK + selected opening FK sites | All role-required prerequisite training | Facility/equipment/SOP/menu/logistics ready for realistic simulation | Pilot / Dry Run | TBD / Validate | RK and opening FK sites | Before operational authorization | Critical | Not Planned | This is the final evidence that assigned staff can perform critical tasks, not a demonstration only. | |||||
| EV-014 | TR-017 | CPR / First Aid - Roles Where Required | Mixed Audience | Certification / Credential | Authorized Safety / CPR Provider | TBD | Launch / Phase I | TBD | Final determination of required roles | Staffing / Assignment | TBD / Validate | TBD | Before required assignment | Medium | Not Planned | Conditional requirement only; do not schedule everyone unless policy requires it. |
Provider Register
| TRN-02 | Training Provider Register | ||||||||||||||||
| Provider contact/capability register. A provider appearing here is not automatically approved; contract, procurement, credential, equipment and agency requirements control provider authorization. | ||||||||||||||||
| Provider ID | Provider / Agency | Provider Type | Training Areas | Authorized / Qualified Basis | Primary Contact Role | Contact Information | Equipment / Program Relationship | Available Locations | Lead Time | Max Class Size / Capacity | Materials Provided? | Competency Evaluation Provided? | Certificate / Record Provided? | Current Status | Last Validated | Notes |
| PV-001 | SFSB Internal Training Personnel | SFSB Internal | Existing SFSB food-service, operational and manager training | Confirm current SFSB assignment/capability before scheduling | Existing SFSB program | TBD | TBD | TBD | TBD / Validate | TBD / Validate | TBD / Validate | Not Planned | Coordinate to avoid duplicate programs. | |||
| PV-002 | Operational Support Contractor | Operational Support Contractor | Training matrix development; specialized operational training when directed | Executed D27-055 contract / accepted scope | Regional Kitchen Operational Support | RK / FK / remote as approved | TBD | TBD | Yes | TBD / Validate | Yes | Not Started | Contractor may assist with development/delivery within area of expertise when directed by State. | |||
| PV-003 | Phase I Equipment Manufacturer / Vendor(s) | Equipment Manufacturer / Vendor | Commercial kitchen equipment operation/startup/familiarization | Awarded equipment contract/vendor qualifications | EQUIP-01/03/04 | At installed equipment | Per delivery/startup schedule | TBD | Yes | TBD / Validate | Yes | Not Started | Provider list populated after equipment/vendor awards. | |||
| PV-004 | Material Handling Equipment Vendor / Trainer | Equipment Manufacturer / Vendor | Freezer forklift equipment-specific training; pallet-jack familiarization | D27-023 solicitation/addendum/training controls | MHE-01 through MHE-05 | Regional Kitchen | After delivery / before service | Up to 7 State-designated individuals for current forklift vendor session | Yes | Yes | Yes | Not Planned | Final awarded vendor/trainer to populate after award. | |||
| PV-005 | Hawaiʻi DOH / Other Public Agency Training | Hawaiʻi DOH / Public Agency | Food-safety or related agency training where available/applicable | Current agency program eligibility/availability | Food-safety / public-agency resources | TBD | TBD | TBD | TBD / Validate | TBD / Validate | TBD / Validate | Not Planned | D27-055 requires consideration of available agency-coordinated training. | |||
| PV-006 | Authorized CPR / First Aid Provider | Authorized Safety / CPR Provider | CPR/first aid for roles where required | Current authorized provider / credential standard | Conditional workforce-safety requirement | TBD | TBD | TBD | Yes | Yes | Yes | Not Started | Do not assign to all roles until requirement is confirmed. | |||
| PV-007 | Supervisor / Qualified Evaluator | Supervisor / Qualified Evaluator | Hands-on competency, dry-run observation and independent-performance validation | State-approved evaluator role / accepted contractor training system | TRN-04 / TEST products | RK/FK sites | Aligned to training/dry-run schedule | TBD | No | Yes | Yes | Not Started | Evaluator authority/criteria to be finalized. |
Dependency Gates
| TRN-02 | Training Dependency Gates | ||||||||||
| Training should occur at the right point in the readiness sequence. These gates prevent teaching draft procedures too early or scheduling hands-on training before the actual equipment/site is available. | ||||||||||
| Gate ID | Training / Event | Dependency / Gate | Dependency Type | Why Required | Authoritative Evidence | Ready? | Ready Date | Owner / Role | If Not Ready | Notes |
| DG-001 | Food Safety / HACCP Core | Final approved/accepted HACCP/SOP training basis | Approved SOP / HACCP | Final training must not teach draft critical limits or procedures. | Approved SAFE/SOP package | TBD / Validate | Food Safety / HACCP | Use only orientation-level concepts until approved procedure is ready. | ||
| DG-002 | Commercial Equipment Operation | Equipment delivered, installed and commissioned | Equipment Installation / Commissioning | Hands-on competency depends on the actual installed equipment/configuration. | EQUIP-03 / commissioning evidence | TBD / Validate | Equipment / Operations | Reschedule hands-on qualification; do not substitute classroom-only completion. | ||
| DG-003 | Forklift / Material Handling | Awarded equipment delivered and trainer available | Equipment Delivery | Current material-handling control requires equipment-specific training after delivery and before service. | MHE-05 award/delivery/training record | TBD / Validate | Material Handling / Operations | Keep operator unqualified until required training/evaluation is complete. | ||
| DG-004 | Menu / Recipe / Production Tool Training | Authoritative menu, recipes and manager tool baseline | Menu / Recipe Baseline | Training on a superseded menu/tool creates rework and inconsistent execution. | MENU-01/02/03/05/06 controlled version | TBD / Validate | Menu / Operations | Use controlled latest baseline only. | ||
| DG-005 | FK Receiving / Inventory / Ordering | Accepted procedures and school transition schedule | Operational Support Deliverable | Roles/processes must be clear before managers practice future-state ordering/receiving. | Accepted SOP / OPS deliverable | TBD / Validate | Operations | Use high-level orientation only; schedule practice after process acceptance. | ||
| DG-006 | FK Equipment / Rethermalization | School access plus installed/commissioned equipment | Site Construction / Access | Staff should practice on the actual equipment and workflow close enough to launch for retention. | PHASE-03 / EQUIP-04 / CONST readiness | TBD / Validate | FK Operations / Facilities | Reschedule or use approved equivalent only if competency can be reliably transferred. | ||
| DG-007 | Distribution / Cart Handling | Distribution procedure/route model and transport equipment available | Operational Support Deliverable | Dry-run competency requires realistic route/load/cart controls. | LOG-01 through LOG-05 / accepted contractor procedure | TBD / Validate | Logistics | Do not sign off final competency from classroom instruction alone. | ||
| DG-008 | Integrated Opening Dry Run | All prerequisite training + operational readiness gates met | Pilot / Dry Run | Dry run is the final integrated competency/readiness event. | TEST / CONST / PHASE / TRN readiness evidence | TBD / Validate | Program Leadership | Do not conduct a meaningless demonstration while major prerequisites are absent. |
Site Phase Rollout
| TRN-02 | Site / Phase Training Rollout Control | |||||||||||||
| One row per RK/FK activation group. Populate exact schools/dates from the authoritative phase schedule. This sheet is intentionally not prefilled with stale transition dates. | |||||||||||||
| Rollout ID | Phase | Site / School / Group | Role Groups Required | Planned Activation Date | Training Window Start | Training Window End | Critical Equipment Ready? | Critical SOP/HACCP Ready? | Required Staff Assigned? | Training Complete? | Competency Sign-Off Complete? | Readiness Status | Notes |
| RO-001 | Launch / Phase I | Regional Kitchen | RK Managers; RK Production; RK Receiving/Warehouse; RK Dispatch/Logistics; Specialized Operators | TBD / Validate | TBD / Validate | TBD / Validate | No | No | Not Planned | Populate from CONST-05/PHASE-01 and staffing assignments. | |||
| RO-002 | PI-Y1 | Initial Phase I Year 1 Finishing Kitchens | FK Managers; FK Workers; FK Receiving | TBD / Validate | TBD / Validate | TBD / Validate | No | No | Not Planned | Use PHASE-01/03 to split into exact school activation groups. | |||
| RO-003 | PI-Y1 | Remaining Phase I Year 1 Schools | FK Managers; FK Workers; FK Receiving | TBD / Validate | TBD / Validate | TBD / Validate | No | No | Not Planned | Schedule by State-approved transition sequence. | |||
| RO-004 | PI-Y2 | Phase I Year 2 Schools | FK Managers; FK Workers; FK Receiving | TBD / Validate | TBD / Validate | TBD / Validate | No | No | Not Planned | Future phase; do not assign dates until authoritative schedule is confirmed. |
Planning Rules
| TRN-02 | Scheduling Rules | |||||||
| Source-based scheduling rules used by the turnover plan. These are planning controls, not fixed dates. | |||||||
| Rule | Planning Control | Source Basis | Scheduling Effect | Risk if Ignored | Success Evidence | Owner Area | Notes |
| Train close enough to launch to retain the skill. | Avoid finishing all training too early when staff will not use the task for months. | Turnover binder Chapter 16 | Sequence initial classroom work earlier, hands-on/competency closer to launch. | Skill decay / retraining / false readiness. | Competency validated shortly before operational authorization. | Training / Operations | |
| Do not wait until opening week for critical qualification. | Protect time for remediation, retesting and provider rescheduling. | Turnover binder Chapter 16 | Set completion target before opening gate, not on opening day. | Training becomes critical path with no recovery time. | TRN-04 shows all critical gaps closed or mitigated. | Training / Program Leadership | |
| Coordinate with existing SFSB training. | Use existing programs/resources where they already satisfy the requirement. | D27-055 2.1.4.1.3 | Provider register should identify existing capability before new content is commissioned. | Duplicate/conflicting training and wasted effort. | One controlled requirement mapped to one provider/material set. | Training / SFSB | |
| Align to equipment startup/commissioning. | Hands-on equipment qualification occurs after actual equipment is ready. | D27-055 2.1.4.1.3; MHE-02 | Tie training event to EQUIP/MHE milestone. | Staff trained on wrong configuration or forget before use. | Equipment-specific competency record. | Equipment / Training | |
| Use dry runs as competency events. | Observe independent performance during realistic operating flow. | Turnover binder recommendation 58; D27-055 operational trials | TRN-04 evaluator records link to TEST/LOG/SAFE exercises. | Attendance mistaken for readiness. | Pass/conditional/remediation result by critical task. | Operations / Training | |
| Maintain onboarding/recurring training after launch. | Training system must survive employee turnover and process changes. | Turnover binder recommendation 59 | Calendar includes onboarding/refresher/requalification triggers. | Initial launch package becomes obsolete. | Recurring schedule and current materials index maintained. | Training |
Lists
| Status | Event Type | Provider Type | Priority | Yes/No/TBD | Dependency Type | Phase | Audience |
| Not Planned | Classroom / Brief | SFSB Internal | Critical | Yes | Staffing / Assignment | Launch / Phase I | RK Managers |
| Planned | Hands-On Equipment | Operational Support Contractor | High | No | Equipment Delivery | PI-Y1 | RK Production |
| Provider Confirmed | Operational Practice | Equipment Manufacturer / Vendor | Medium | TBD / Validate | Equipment Installation / Commissioning | PI-Y2 | RK Receiving / Warehouse |
| Scheduled | Dry-Run Competency Event | Hawaiʻi DOH / Public Agency | Low | Approved SOP / HACCP | PII-Y1 | RK Dispatch / Logistics | |
| In Progress | Certification / Credential | Authorized Safety / CPR Provider | Menu / Recipe Baseline | PII-Y2 | FK Managers | ||
| Complete | Refresher / Requalification | Supervisor / Qualified Evaluator | Site Construction / Access | Other | FK Workers | ||
| Reschedule Required | Onboarding / Orientation | External Specialist | Operational Support Deliverable | FK Receiving | |||
| Superseded | TBD / Validate | Pilot / Dry Run | Specialized Operators | ||||
| Other | Mixed Audience |