This is an Equipment Master spreadsheet and operational readiness validation solicitation for the Hawaii State Department of Education's first regional kitchen facility. The document establishes a Phase 1 equipment control register tracking 40 kitchen equipment lines required for the regional kitchen operation, which will transition centralized food production to finishing kitchens serving approximately 85 schools statewide, with initial Phase 1 implementation supporting 20 schools in the Leilehua-Mililani-Waialua complex by June 2027. The equipment list includes major items such as walk-in coolers and freezers, blast chillers, rotating rack ovens, convection ovens, tilt kettles, cooking equipment, packaging machines, exhaust hoods, fire suppression systems, and mobile transport tables. The sealed bid solicitation (IFB D27-055) requires submission through the Hawaii eProcurement System (HIePRO) with bids due October 14, 2026 at 4:30 p.m. Hawaii Standard Time, with hard copies required within five working days of bid closing. The contract runs from full execution through April 30, 2027, with an option for one additional two-month extension upon mutual written agreement. Addendum A, issued September 21, 2026, provides a State-Furnished Materials Index and references to planning products.
The solicitation encompasses seven fixed-price service line items and one hourly rate item (Item 8) providing up to 120 hours of specialized operational training at the contractor's hourly rate with no minimum guaranteed hours. Service areas include operational process development and continuity of operations, menu and production transition planning, inventory and materials management, training and workforce readiness, Phase I finishing-kitchen operational readiness assessments, food safety and HACCP compliance, and project management support. Offerors must demonstrate three years of experience with large-scale food-service operations producing 1,000+ meals daily, three years with USDA Child Nutrition Programs, three years designing high-volume kitchen workflows, two years with facility start-up and commissioning, two years with food distribution and cold-chain logistics, and five years developing institutional food-service standard operating procedures. Minimum liability insurance requirements are $2,000,000 aggregate commercial general liability and $1,000,000 combined single limit per occurrence, plus $1,000,000 automobile liability coverage. Award goes to the lowest responsive, responsible bidder provided the total does not exceed allotted funds, and the contractor must validate and complete state-developed work rather than recreate existing materials.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Executive Summary
| EQUIP-01 | Phase 1 Equipment Readiness Snapshot | ||||
| The equipment master should answer: is each required item compatible, procured, delivered, installed, commissioned, trained and accepted for use? | ||||
| Equipment Lines | Required Units | Ready | Not Assessed | Open Issues |
| 40 | 65 | 0 | 40 | 0 |
| Control Note |
| 1. Do not mark an equipment line Ready until site compatibility, utilities, installation/startup, training and acceptance are resolved. |
| 2. Use approved submittals/as-built information when available; the RFP cut-sheet book is a baseline, not proof of final installed condition. |
| 3. Track detailed purchasing and delivery activity in EQUIP-03, then summarize readiness here. |
| 4. Keep Finishing Kitchen school-by-school gross and net equipment requirements in EQUIP-04. |
Equipment Master
| EQUIP-01 | Phase 1 Equipment Master | ||||||||||||||||||||||||||||||||||
| Authoritative Phase 1 Regional Kitchen equipment control register. Core equipment data is preloaded from the 9/1/2026 RK/FK Equipment & Smallwares workbook. Utility, procurement, installation, commissioning and acceptance fields require current-source validation. | ||||||||||||||||||||||||||||||||||
| Equipment ID | Location Type | Area / Location | Equipment | Qty Required | Manufacturer | Model | Capacity / Compatibility | Primary Use | Dimensions / Footprint | Electrical | Water | Gas / Steam / Air | Drain / Ventilation | Required Clearance | Cut Sheet Status | Drawing / Utility Coordination | Procurement Status | Vendor / Supplier | PO / Contract Ref | Lead Time | Planned Delivery | Actual Delivery | Staging / Storage Location | Installation Status | Startup / Functional Test | Commissioning Status | Warranty Activated | Manuals Received | Training Complete | Acceptance Complete | Overall Readiness | Current Issue / Dependency | Source / Reference | Last Updated |
| PK-01 | Regional Kitchen | Kitchen Walk-In Cooler | 1 | American Panel | Custom | 140 sq ft; 8'-4" OA height | Storage / staging | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-02 | Regional Kitchen | Unit Cooler (Kitchen Cooler) | 1 | OmniTemp | — | Refrigeration evaporator | Infrastructure | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-03 | Regional Kitchen | Blast Chiller / Shock Freezer | 2 | American Panel | AP20BCF200-3 | 1 mobile rack; 20 x 12x20x2.5 pans or 10 x 18x26 pans; 200 lb chill | Cook-chill | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-04 | Regional Kitchen | Stainless Steel Wall Flashing | 1 | Custom | — | 18 ft | Infrastructure | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-05 | Regional Kitchen | Cook/Chill Control Panel | 1 | Cleveland | HA-DG-CH | Dual remote control center | Cook-chill | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-06 | Regional Kitchen | Tilt Kettle with Agitator | 2 | Cleveland | HAMKDL100TCC | 100 gal; horizontal agitator; 3-in piston valve | Sauces / soups / pasta / bulk cooking | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-07 | Regional Kitchen | Floor Pan with Trough and Grate | 1 | BSI | FT-DP Custom | Floor drain assembly | Sanitation | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-08 | Regional Kitchen | Form/Fill/Seal Packaging Machine | 1 | TUCS | TEVFF-10S | Cook-chill bag packaging | Packaging | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-09 | Regional Kitchen | Tilt Kettle with Agitator | 1 | Cleveland | MKDL60T | 60 gal working capacity; 3-in draw-off | Sauces / dressings / bulk cooking | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP heading says 50 gal; model description says 60 gal | |||||||||
| PK-10 | Regional Kitchen | Hose Reel with Spray | 1 | Fisher | 75395 | 50-ft hose | Sanitation | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-11 | Regional Kitchen | Manual Bagger / Sealer | 1 | Cleveland | CVW4100 | Vertical clipper vacuum packaging system | Packaging | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-12 | Regional Kitchen | Exhaust Hood with Make-Up Air | 1 | Halton | KVE | 18 ft Type I hood | Infrastructure | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-13 | Regional Kitchen | Hand Sink | 2 | Advance Tabco | 7-PS-40 | Wall-mounted | Hygiene | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-14 | Regional Kitchen | Cook/Chill Tank | 1 | Cleveland | HBCC100 | 155 gal water / 100 gal product; includes 10 baskets | Cook-chill | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-15 | Regional Kitchen | Utility Distribution System | 1 | Halton | — | 34 ft ceiling-mounted | Infrastructure | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-16 | Regional Kitchen | Reach-In Freezer | 1 | True | STR1F-1S-HC | Single door | Cold storage | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-17 | Regional Kitchen | Reach-In Refrigerator | 1 | True | STR2R-2S-HC | Double door | Cold storage | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-18 | Regional Kitchen | Wall Shelf | 1 | Custom | — | 8 ft | Storage | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-19 | Regional Kitchen | Worktable | 1 | Custom | — | 8 ft | Prep / packaging | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-20 | Regional Kitchen | Fire Suppression System | 1 | Ansul | R-102 Wet | Hood suppression | Infrastructure | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-21 | Regional Kitchen | Hand Sink | 1 | Advance Tabco | 7-PS-40 | Wall-mounted | Hygiene | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-22 | Regional Kitchen | Rotating Rack Oven | 3 | LBC Bakery | LRO-2G5 | Double rack; up to 40 x 18x26 sheet pans per oven at 3-in spacing | High-volume baking / roasting | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-23 | Regional Kitchen | Convection Oven, Double Stacked | 1 | Blodgett | DFG-200 DBL | 5 x 18x26 pans per deck; 10 total | Baking / roasting | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-24 | Regional Kitchen | Exhaust Hood with Make-Up Air | 1 | Halton | KVE | 17 ft Type I hood | Infrastructure | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-25 | Regional Kitchen | 6-Burner Range with Convection Oven | 1 | Garland | C36-6C | 6 open burners; oven includes 3 racks | Small-batch cooking / backup | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-26 | Regional Kitchen | Tilt Kettle | 1 | Cleveland | KDL40TSH | 40 gal direct steam, tilting | Small-batch sauces / grains | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-27 | Regional Kitchen | Floor Trough and Grate | 1 | Made To Drain | ASDT-3054 | Anti-splash trough | Sanitation | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-28 | Regional Kitchen | Fill Faucet | 1 | Fisher | 75573 | Pot filler | Water delivery | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-29 | Regional Kitchen | Floor Trough and Grate | 1 | Made To Drain | ASDT-3054 | Anti-splash trough | Sanitation | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-30 | Regional Kitchen | Braising Pan / Tilting Skillet | 1 | Cleveland | SGL40T1 | 40 gal; 10-degree tilt cooking | Sauté / braise / ground meat / eggs | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-31 | Regional Kitchen | Fire Suppression System | 1 | Ansul | R-102 Wet | Hood suppression | Infrastructure | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-32 | Regional Kitchen | Stainless Steel Wall Flashing | 1 | Custom Fab | — | 17 ft | Infrastructure | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-33 | Regional Kitchen | Worktable | 1 | Custom Fab | — | 7 ft | Prep / packaging | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-34 | Regional Kitchen | Food Labeler | 1 | API Tech / Zebra | ZT231 | QR / product labels | Packaging / traceability | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-35 | Regional Kitchen | Wall Shelf | 2 | Custom Fab | — | 7 ft | Storage | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-36 | Regional Kitchen | Tray Sealer | 1 | Oliver | 1308-N | 6-8 packages/min; max tray 8.5 x 6.5 x 3.25 in | Packaging | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-37 | Regional Kitchen | Mobile Food Transport Table with Bin | 15 | Form Plastics | Custom / 182615P | Mobile pack-out tables | Pack-out / staging | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-38 | Regional Kitchen | Pick Walk-In Freezer | 1 | American Panel | Custom | 128 sq ft; 8'-4" OA height | Frozen pick / staging | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-39 | Regional Kitchen | Unit Cooler (Pick Freezer) | 1 | OmniTemp | — | Refrigeration evaporator | Infrastructure | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP | |||||||||
| PK-40 | Regional Kitchen | Walk-In Shelving | 6 | Metro | MetroMax Q | Polymer shelving | Storage | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Verify in EQUIP-02 | Available in EQUIP-02 | Not Confirmed | Not Confirmed | Not Confirmed | Not Started | Not Started | No | No | No | No | Not Assessed | EQUIP-02 / Phase 1 RFP |
Commissioning Checklist
| EQUIP-01 | Equipment Commissioning & Acceptance Checklist | ||||||||||||||||||
| Use one row per equipment line as delivery/installation approaches. This checklist does not replace manufacturer startup forms, procurement acceptance, facilities inspections or warranty documentation. | ||||||||||||||||||
| Equipment ID | Equipment | Qty | Delivery Verified | Damage / Shortage Check | Location Verified | Utility Connection Verified | Clearance Verified | Anchoring / Restraint Verified | Startup Completed | Functional Test Passed | Safety / Sanitation Check | Warranty Registered | Manuals / Parts List Received | Operator Training Completed | Maintenance Training Completed | Acceptance Authority | Acceptance Date | Open Punch Item / Notes |
| PK-01 | Kitchen Walk-In Cooler | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-02 | Unit Cooler (Kitchen Cooler) | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-03 | Blast Chiller / Shock Freezer | 2 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-04 | Stainless Steel Wall Flashing | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-05 | Cook/Chill Control Panel | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-06 | Tilt Kettle with Agitator | 2 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-07 | Floor Pan with Trough and Grate | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-08 | Form/Fill/Seal Packaging Machine | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-09 | Tilt Kettle with Agitator | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-10 | Hose Reel with Spray | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-11 | Manual Bagger / Sealer | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-12 | Exhaust Hood with Make-Up Air | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-13 | Hand Sink | 2 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-14 | Cook/Chill Tank | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-15 | Utility Distribution System | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-16 | Reach-In Freezer | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-17 | Reach-In Refrigerator | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-18 | Wall Shelf | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-19 | Worktable | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-20 | Fire Suppression System | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-21 | Hand Sink | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-22 | Rotating Rack Oven | 3 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-23 | Convection Oven, Double Stacked | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-24 | Exhaust Hood with Make-Up Air | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-25 | 6-Burner Range with Convection Oven | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-26 | Tilt Kettle | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-27 | Floor Trough and Grate | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-28 | Fill Faucet | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-29 | Floor Trough and Grate | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-30 | Braising Pan / Tilting Skillet | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-31 | Fire Suppression System | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-32 | Stainless Steel Wall Flashing | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-33 | Worktable | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-34 | Food Labeler | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-35 | Wall Shelf | 2 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-36 | Tray Sealer | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-37 | Mobile Food Transport Table with Bin | 15 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-38 | Pick Walk-In Freezer | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-39 | Unit Cooler (Pick Freezer) | 1 | No | No | No | No | No | No | No | No | No | No | No | No | No | |||
| PK-40 | Walk-In Shelving | 6 | No | No | No | No | No | No | No | No | No | No | No | No | No |
Source & Rules
| EQUIP-01 | Source, Scope & Control Rules | |||||
| The source workbook establishes the equipment baseline; EQUIP-02 remains the technical cut-sheet package. Current drawings, approved submittals, installed conditions and procurement records supersede older planning information when formally validated. | |||||
| Control Area | Source / Basis | Preloaded Here | Must Be Validated | Update Trigger | Rule |
| Equipment baseline | 9/1/2026 RK/FK Equipment & Smallwares workbook - Equipment Register | 40 PK equipment lines, quantities, manufacturer/model, capacity and use | Latest design/installed equipment list | Design/submittal/equipment change | Do not delete old line without documenting replacement or supersession. |
| Technical specifications | EQUIP-02 Equipment Specifications & Cut Sheets | Reference only | Dimensions, utility loads, clearances, installation requirements, current approved submittals | Submittal approval / model substitution | Approved submittal/as-built data takes precedence over old RFP cut sheet. |
| Procurement/readiness | Current procurement, delivery, installation and acceptance records | Control fields provided | Actual PO/contract, lead times, delivery, install, startup, warranty, training, acceptance | Any procurement or field status change | EQUIP-03 is the detailed procurement/delivery tracker; EQUIP-01 carries the authoritative readiness summary. |
| Finishing Kitchen equipment | EQUIP-04 | Not duplicated in the 40-line RK register | School-by-school gross need, existing serviceable assets and net purchase requirement | Site survey / phase change / menu change | Keep FK school requirements in EQUIP-04 and link readiness to PHASE-03. |
Lists
| Status | Yes/No | Location Type | Readiness | Cut Sheet Status |
| Not Confirmed | Yes | Regional Kitchen | Not Assessed | Available in EQUIP-02 |
| Not Started | No | Finishing Kitchen | At Risk | Needs Updated Cut Sheet |
| In Progress | Shared / Support | Conditionally Ready | Approved Submittal Available | |
| Complete | Ready | As-Built / Final Available | ||
| On Hold | Not Required | |||
| Not Required | ||||
| Cancelled |