EX B CONST 05 Operational Readiness Milestone Plan.xlsx

XLSX spreadsheet 43 KB Posted

Attached to
Regional Kitchen Operational Readiness Validation for HIDOE
Solicitation number
B27000433
Issued by
Hawaii

About this file

This file is an Operational Readiness Milestone Plan (CONST-05) developed by the Hawaii State Department of Education for the Regional Kitchen project, which represents the state's transition from centralized food production to a network of finishing kitchens serving approximately 85 schools statewide. The plan translates 17 defined construction milestones into operational actions required to achieve full operational capability by the planning target of June 2027, with Phase I implementation supporting 20 schools in the Leilehua-Mililani-Waialua complex. Critical milestones include obtaining the current construction schedule (CONST-01), approving utility configurations, achieving facility substantial completion, installing and commissioning production equipment, completing required regulatory inspections and occupancy approvals, establishing staffing baselines, conducting mandatory staff training, validating food safety and HACCP systems, freezing menu and production protocols, conducting logistics dry runs, executing integrated production trials, and obtaining integrated operational-readiness approval before Regional Kitchen activation. The plan identifies 14 milestones on the critical path, 3 at-risk or blocked milestones, and designates ownership across Facilities/Construction, Equipment, Operations, Training, Staffing, Food Safety, and Logistics workstreams, with all source planning dates acknowledged as reference points pending receipt of authoritative construction dates from CONST-01.

The milestone plan establishes dependencies between construction completion and operational readiness across multiple workstreams, requiring minimum lead time and buffer protection for equipment installation and commissioning, staff training and rehearsal, regulatory approvals, and food-production trials. Key dependencies include power energization by December 2026 to avoid schedule delays, loading dock and truck interface resolution (specifically addressing RFI 1043 regarding vehicle access compatibility), equipment room layout confirmation before equipment ordering, occupancy and staff access approval to protect the hands-on training window, and inspection approval allowing correction and reinspection time before operational launch. Four Phase I finishing kitchens—Wahiawa Elementary School, Wahiawa Middle School, Iliahi Elementary School, and Leilehua High School—each require customized construction strategies balancing operational continuity during facility modifications, with strategies ranging from advance exterior work to phased school-year construction to temporary storage solutions. The plan references supporting construction files (CONST-01, CONST-02, CONST-03, CONST-04), equipment documentation, training records, food-safety files, menu files, logistics files, and a decision log/risk register, with last review documented as July 22, 2026, and all milestone statuses currently showing as "Not Started" or "Not Confirmed" pending receipt of authoritative construction schedule data.

View the file

Other files

File Type Posted
IFB D27 055 Legal Notice.pdf PDF
EX B EQUIP 04 Finishing Kitchen Equipment Requirement.xlsx XLSX spreadsheet
EX B LOG 01 RK FK Distribution Route Plan.xlsx XLSX spreadsheet
EX B TRN 01 RK FK Training Requirements Matrix.xlsx XLSX spreadsheet
IFB D27 055 Addendum A.pdf PDF
EX B SAFE 03 RK FK Traceability Recall Procedure.docx DOCX document
EX B TRN 02 Training Calendar Provider Implementation Plan.xlsx XLSX spreadsheet
EX B SOP 05 RK FK Emergency Continuity of Operations Procedure.docx DOCX document
EX B MENU 03 RK Standardized Recipe Database.xlsx XLSX spreadsheet
EX B SAFE 02 RK FK Food Safety Log Set.xlsx XLSX spreadsheet
EX B SMW 01 RK FK Smallwares Master Workbook.xlsx XLSX spreadsheet
EX B MENU 02 RK Menu Recipe Production Manager Workbook.xlsx XLSX spreadsheet
EX B LOG 03 FK Receiving Discrepancy Procedure.docx DOCX document
EX B SOP 02 RK FK Opening Readiness Checklist.xlsx XLSX spreadsheet
IFB D27 055 Additional Offer Pages.pdf PDF
IFB D27 055 Solicitation.pdf PDF
EX B PHASE 03 Finishing Kitchen Site Readiness Matrix.xlsx XLSX spreadsheet
EX B TEST 01 RK FK Integrated Pilot Dry Run Plan.xlsx XLSX spreadsheet
EX B SOP 01 RK FK SOP Register.xlsx XLSX spreadsheet
EX B PROC 01 RK Recipe Ingredient Master.xlsx XLSX spreadsheet
EX B SAFE 01 RK FK HACCP Development and Control Framework.xlsx XLSX spreadsheet
EX B Regional Kitchen Materials Index.docx DOCX document
EX B EQUIP 01 Phase 1 Equipment Master.xlsx XLSX spreadsheet
EX B SOP 04 RK FK Core Operational SOP Library.docx DOCX document
EX B LOG 02 RK Loading Dispatch Standard.docx DOCX document
EX B PHASE 01 RK FK Phase Implementation Master.xlsx XLSX spreadsheet
EX B MENU 01 RK Five Week Cycle Menu.xlsx XLSX spreadsheet
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Executive Summary

CONST-05 | Operational Readiness Milestone Snapshot
The first milestone is obtaining CONST-01. Until then, planning dates remain references rather than authoritative commitments.
Defined MilestonesCritical PathNot ConfirmedAt Risk / BlockedComplete
1714300

Operational Milestone Plan

CONST-05 | Regional Kitchen Operational Readiness Milestone Plan
Translates construction milestones into operational actions. Source planning dates are retained for traceability but are not substitutes for CONST-01; replace them with authoritative construction dates when received.
Milestone IDMilestone TypeMilestone / GatePurpose / Exit CriterionSource Planning ReferenceAuthoritative DateForecast DateActual DateStatusCritical PathOwner AreaPredecessor(s)Downstream Work EnabledEvidence / DeliverableGate DecisionDecision Authority / RoleIssue / RiskMitigation / Corrective ActionRelated Binder FilesLast ReviewedSource / ReferenceNotes
MS-001ConstructionCurrent Phase I construction schedule receivedCurrent contractor/FDB schedule is loaded into CONST-01 and critical path is identified.Required before this plan is finalizedNot ConfirmedYesFacilities / ConstructionAll downstream milestone datesCONST-01 current schedulePendingMissing authoritative scheduleInsert current schedule and reconcile every downstream date.CONST-01; CONST-03; CONST-05Turnover Binder Chapter 11
MS-002UtilityApproved power-service configuration frozenFinal electrical service/transformer approach is approved and reflected in current design/schedule.Power identified as schedule-critical; July 2026 source said permanent power was needed by Dec 2026 to avoid delay.Not ConfirmedYesFacilities / ConstructionMS-001Equipment startup, refrigeration, commissioningApproved utility/service recordPendingService redesign / external utility dependencyMaintain utility coordination and elevate schedule impact.CONST-03; CONST-04; EQUIP-01District 17 Project Summary Tracker revised July 22, 2026
MS-003ConstructionFacility substantially completeFacility reaches condition suitable for final systems testing and turnover.Estimated construction completion June 2027 in July project tracker; confirm in CONST-01.Not ConfirmedYesFacilities / ConstructionMS-001; MS-002Final inspections, equipment commissioning, staff accessSubstantial-completion recordPendingConstruction schedule varianceUse current schedule and issue log; do not infer completion.CONST-01; CONST-03; CONST-04District 17 Project Summary Tracker revised July 22, 2026
MS-004EquipmentFacility ready to receive and secure equipment/smallwaresLoading/access/staging/security/storage conditions support safe receipt.Binder requires confirmation before delivery/staging.Not StartedWatchOperationsMS-003Equipment/smallwares delivery and stagingReceiving/staging readiness confirmationPendingSite access/storage not readyCoordinate delivery windows to avoid off-site storage/rehandling.EQUIP-03; SMW-02; SMW-04; CONST-04Turnover Binder Chapter 11
MS-005EquipmentProduction equipment installedRequired Phase I equipment is placed, connected, and ready for startup.After facility/utility readiness.Not StartedYesEquipmentMS-002; MS-003; MS-004Startup, commissioning, trainingInstallation-completion recordPendingUtility/clearance/submittal conflictsComplete equipment-to-drawing reconciliation before final installation.EQUIP-01; EQUIP-02; EQUIP-03; CONST-02Turnover Binder Chapter 11
MS-006EquipmentEquipment startup and commissioning completeCritical equipment passes manufacturer/startup and operational function checks.After equipment installation.Not StartedYesEquipmentMS-005Operator training, food-production trialsCommissioning/startup recordsPendingOpen punch items / failed testsTrack corrections in CONST-04 and equipment files.CONST-04; EQUIP-01; EQUIP-03; MHE-05Turnover Binder Chapter 11
MS-007ConstructionRequired building/fire/utility approvals completeRequired regulatory/life-safety inspection and occupancy prerequisites are satisfied.Before occupancy / routine operations.Not StartedYesFacilities / ConstructionMS-003; MS-006Routine staff access / operational releaseInspection approvals / occupancy evidencePendingInspection deficiency / permit delayMaintain punch list and retest/reinspection dates.CONST-04Turnover Binder Chapter 11
MS-008StaffingOpening staffing baseline executableRequired RK/FK positions, vacancies, onboarding, and coverage plan are sufficient for training and launch.Must align to actual opening schedule.Not StartedYesStaffing / HRMS-001Training, dry runs, first productionStaffing-readiness confirmationPendingRecruitment/classification timingSequence personnel actions to authoritative activation date.STAFF-01; STAFF-04; PHASE-01Turnover Binder continuity plan
MS-009TrainingStaff access available for trainingFacility access is approved and systems are safe/available for hands-on training.After access/life-safety conditions allow.Not StartedWatchTrainingMS-006; MS-007; MS-008Equipment and operating trainingStaff-access release / training schedulePendingConstruction delays compress training windowProtect minimum hands-on training window.CONST-04; TRAIN files; EQUIP-03; MHE-05Turnover Binder Chapter 11
MS-010TrainingRequired role/equipment/food-safety training completePersonnel complete mandatory and role-based training needed for assigned duties.Before integrated dry runs / first production.Not StartedYesTrainingMS-009Operational trials and readiness validationTraining matrix / completion recordsPendingIncomplete qualificationsClose critical training gaps or document controlled conditions.TRAIN files; FOODSAFE files; MHE-05Operational Support Contract training requirements
MS-011Food SafetyHACCP / food-safety system readyRequired plans, SOPs, logs, traceability and corrective-action tools are approved and usable.Before food-production trials.Not StartedYesFood Safety / HACCPMS-006; MS-010Food production trialsApproved HACCP / forms / logsPendingFood-safety documents not operationalizedValidate through simulations and mock recall.FOODSAFE files; SOP filesOperational Support Contract
MS-012OperationsMenu / recipe / production launch baseline frozenApproved menu, validated recipes, count/scaling tools, and source-controlled manager workflow are ready for trial.Before production trials.In ProgressYesMenu / ProductionProduction and purchasing trialsMENU-01 through MENU-06 launch baselinePendingRecipe/workbook changes remainFreeze controlled launch version and archive superseded copies.MENU-01 through MENU-06Turnover Binder menu chapter
MS-013LogisticsDistribution route / receiving dry run completeActual vehicle, dock, route, delivery window, temperature, receiving and return processes are demonstrated.After dock/access and product-handling systems are ready.Not StartedYesLogistics / TransportationMS-004; MS-006; MS-007Integrated RK-to-FK trialDry-run record and corrective actionsPendingDock/RFI/route incompatibilityResolve RFI 1043 and validate actual vehicle assumptions.LOG files; CONST-03; CONST-04Turnover Binder construction/logistics requirements
MS-014OperationsIntegrated RK-to-FK production trial completeProduction, cooling/packaging, loading, transport, FK receiving, rethermalization/finishing, service and food-safety records perform as intended.Operational Support Contract calls for operational simulations/trials when directed and facility conditions permit.Not StartedYesOperationsMS-006; MS-010; MS-011; MS-012; MS-013Final operational-readiness decisionTrial record, issues and correctionsPendingCross-workstream failureRepeat trial after critical corrections.TEST files; MENU files; LOG files; FOODSAFE filesOperational Support Contract
MS-015OperationsIntegrated operational-readiness review completeMajor operating systems are sufficiently complete/aligned and unresolved issues have controlled mitigations.Required prior to Regional Kitchen activation.Not StartedYesLeadershipMS-014First production / activationIntegrated readiness review / approvalPendingResidual critical riskHold launch if critical entry criteria are not met.PHASE-03; CONST-04; TEST files; Risk RegisterOperational Support Contract
MS-016OperationsRegional Kitchen first production / activationAuthorized production begins under the frozen launch baseline.Operational Support Contract planning target: by June 2027; verify against CONST-01/current leadership direction.Not StartedYesOperationsMS-015Routine operations and scale-upLaunch authorization / first production recordPendingSchedule/readiness mismatchDo not launch based on calendar date alone.CONST-05; PHASE-01; TEST filesOperational Support Contract / turnover binder
MS-017OperationsPost-opening stabilization reviewIssues, performance, waste, staffing, quality, routes, inventory and corrective actions are reviewed after launch.30-/90-day post-opening review recommended in continuity plan.Not StartedNoOperationsMS-016Controlled improvement / scale-upPost-opening review and issue logN/AUncontrolled local workaroundsUse controlled change logs and update SOPs/training as needed.Decision Log; Risk Register; SOP filesTurnover Binder continuity plan

Dependency Map

CONST-05 | Construction-to-Operations Dependency Map
Translate construction movement into the workstreams that must move with it.
Construction / Facility EventImmediate Operational DependencyAffected WorkstreamsMinimum Lead / Buffer to ProtectTrigger to RebaselinePrimary Control FileEscalation ThresholdNotes
Construction schedule changeAll downstream datesStaffing; equipment; procurement; training; logistics; menu trials; openingProtect enough time for installation, commissioning, training and dry runsAny material shift to a critical-path milestoneCONST-01 / CONST-05Opening-critical milestone slips or compresses readiness window
Power energization changeEquipment/refrigeration startupEquipment; food safety; training; menu trialsVendor/startup windows plus test timeEnergization forecast changesCONST-03 / CONST-04Threatens commissioning or cold-storage readiness
Loading dock / truck interface changeReceiving and dispatch capabilityLogistics; equipment; distribution dry runsResolve before route validationDock geometry or vehicle assumption changesCONST-03 / LOG filesActual route vehicle cannot safely use dockRFI 1043 is current source example.
Equipment room/layout changeEquipment fit, utilities and workflowEquipment; smallwares; menu; sanitation; staffingBefore order/installationDrawing/RFI/change affects footprint, connection or clearanceCONST-02 / EQUIP-01Required equipment no longer fits or utility unavailable
Occupancy/access delayStaff training and stagingTraining; staffing; equipment; smallwares; operationsProtect hands-on training and rehearsal windowStaff cannot enter as plannedCONST-04 / CONST-05Launch window remains but training window collapses
Inspection failure / conditional approvalOperational releaseFood safety; operations; facilitiesAllow correction/reinspection timeFail/conditional resultCONST-04Critical deficiency unresolved before launch

Initial FK Construction Link

CONST-05 | Initial Finishing Kitchen Construction Link
Source-derived July 2026 strategy for the first four finishing kitchens. Replace/update these assumptions from the current construction record.
SchoolSource Construction StrategyKey Dependency / NeedContinuity ConsiderationCurrent StatusAuthoritative Schedule DateOperational Readiness LinkSource / ReferenceNotes
Wahiawa Elementary SchoolAdvance exterior work where possible; major interior trenching/utility work was considered impractical during normal meal production.Loading dock modifications; security-gate relocation; exterior walk-in work; compressor pad; potential roof/weatherproofing.Source said reach-in refrigeration could support operations while existing walk-in freezer is removed.Not ConfirmedPHASE-03 / EQUIP-04 / LOG filesFinishing Kitchen Construction Strategy, July 2026
Wahiawa Middle SchoolPhased school-year construction considered feasible with dust containment; build new warewashing/dry storage before converting existing dry storage to walk-in cooler/freezer.Warewashing room; dry-storage room; walk-in cooler/freezer; compressor pad.Source said facility could maintain daily kitchen operations during substantial portions of work.Not ConfirmedPHASE-03 / EQUIP-04Finishing Kitchen Construction Strategy, July 2026
Iliahi Elementary SchoolWalk-in cooler/freezer work within existing dry storage.Temporary dry-storage container required because no practical alternate dry-storage location was identified.Temporary storage must preserve food safety, sanitation, product security and operational continuity.Not ConfirmedPHASE-03 / SMW-04Finishing Kitchen Construction Strategy, July 2026
Leilehua High SchoolUse front of dry storage while rear is converted to walk-in cooler/freezer; shift inventory into completed spaces afterward.Walk-in cooler/freezer and exterior compressor pad.Source described relatively minor operational impacts; also identified as a contingency-priority site if summer delays occur.Not ConfirmedPHASE-03 / EQUIP-04Finishing Kitchen Construction Strategy, July 2026

Lists

StatusMilestone TypeCritical PathGate DecisionYes/NoOwner Area
Not StartedConstructionYesPendingYesFacilities / Construction
PlannedUtilityWatchProceedNoOperations
ScheduledProcurementNoProceed with ConditionsProcurement
In ProgressEquipmentHoldEquipment
CompleteStaffingN/AStaffing / HR
At RiskTrainingTraining
BlockedFood SafetyFood Safety / HACCP
Not ConfirmedLogisticsLogistics / Transportation
OperationsMenu / Production
Technology / Data
Leadership
External

File details come from the government source that posted it. Updated .