ESBD_396277_1739554160285_ATTACHMENT G.M - Ellington AFB (EF) Material Equipment.pdf

PDF 63 KB Posted

Attached to
Hush House Transformer Replacement
Solicitation number
TMD25-ANG-WJ-24150007
Issued by
Harris County, Texas

About this file

This document is an Attachment G.M detailing material equipment requirements for Ellington Air Force Base (AFB) in Houston, TX. The document outlines requirements for transportation, handling, storage, protection, product options, and substitutions for materials and equipment used at the facility. No specific quantities, response dates, or term lengths are provided in this attachment.

The document specifies that payment for materials stored on site will only be made when accompanied by an inventory and supplier invoices, with only actual material costs being compensated. Product substitutions must be formally requested during the submittal phase and require thorough documentation including test results and compliance data. The contractor must submit three copies of substitution requests, and if rejected, must supply the originally specified item or an acceptable substitution at no additional cost to the owner. No specific pricing terms, set-asides, or funding amounts are mentioned in the document.

View the file

Other files

File Type Posted
ESBD_396277_1739554274379_ATTACHMENT G.W - Ellington AFB (EF) AF103_REV.pdf PDF
ESBD_396277_1739554263410_ATTACHMENT G.V - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Unmarked Burials.pdf PDF
ESBD_396277_1739554242664_ATTACHMENT G.T - Ellington Field (EF) Post Award Submittals.pdf PDF
ESBD_396277_1739554019240_ATTACHMENT G.B - Ellington Field (EF) Coordination And Meetings.pdf PDF
ESBD_396277_1739554089469_ATTACHMENT G.G - Ellington AFB (EF) Quality Control.pdf PDF
ESBD_396277_1739554294506_ATTACHMENT G.Y - Ellington AFB (EF) Form 17 - Visitor Contractor Pass Request (01OCT23).pdf PDF
ESBD_396277_1739554059288_ATTACHMENT G.F - Ellington Field (EF) EMS Hazardous Material Procedures.pdf PDF
ESBD_396277_1739553617667_ATTACHMENT G.2 Application for Texas Identification Number #_AP_152.pdf PDF
ESBD_396277_1739554039934_ATTACHMENT G.D - Ellington AFB (EF) Field Engineering.pdf PDF
ESBD_396277_1739553555834_TMD25-ANG-WJ-24150007 Hush House Transformer Replacement.pdf PDF
ESBD_396277_1739554191020_ATTACHMENT G.O - Ellington Field (EF) Starting Of Systems.pdf PDF
ESBD_396277_1739553606718_ATTACHMENT G.1 Direct Deposit Authorization Form 74-176 (Rev.9-2121).pdf PDF
ESBD_396277_1739553662987_ATTACHMENT G.6 Preferred ALAMO Transformer Schematic.pdf PDF
ESBD_396277_1739553641492_ATTACHMENT G.4 Mandatory Pricing Schedule.xlsx XLSX spreadsheet
ESBD_396277_1739554009810_ATTACHMENT G.A - Ellington Field (EF) General Requirements.pdf PDF
ESBD_396277_1739554170591_ATTACHMENT G.N - Ellington Field (EF) Manufacturers’ Services.pdf PDF
ESBD_396277_1739553654889_ATTACHMENT G.5 Photo of Hush House Transformer.pdf PDF
ESBD_396277_1739554049653_ATTACHMENT G.E - Ellington Field (EF) Safety Policies And Procedures.pdf PDF
ESBD_396277_1739554232203_ATTACHMENT G.S - Ellington AFB (EF) Substitutions Request Form.pdf PDF
ESBD_396277_1739554211970_ATTACHMENT G.Q - Ellington AFB (EF) Cutting And Patching.pdf PDF
ESBD_396277_1739553997116_ATTACHMENT G.7 Project Map-Hush House Map.pdf PDF
ESBD_396277_1739554129070_ATTACHMENT G.J.1 - Ellington AFB (EF) Maintenance Summary Form.pdf PDF
ESBD_396277_1739554029863_ATTACHMENT G.C - Ellington AFB (EF) Project Coordination.pdf PDF
ESBD_396277_1739554149784_ATTACHMENT G.L - Ellington Field JRB Final Asbestos Abatement Report Template.pdf PDF
ESBD_396277_1739554119567_ATTACHMENT G.J - Ellington Field (EF) Operation And Maintenance Data.pdf PDF
ESBD_396277_1739554079011_ATTACHMENT G.F.2 - Ellington AFB (EF) Contractor Hazardous Material Identification Form Close-Out Procedures.pdf PDF
ESBD_396277_1739553628289_ATTACHMENT G.3 Texas Military Department Standard Terms and Conditions Revision 5.pdf PDF
ESBD_396277_1739554068682_ATTACHMENT G.F.1 - Ellington AFB (EF) Contractor Hazardous Material Usage Data.pdf PDF
ESBD_396277_1739554099531_ATTACHMENT G.H - Ellington Field (EF) EMS Environmental Protection.pdf PDF
ESBD_396277_1739554181602_ATTACHMENT G.N.1 - Ellington Field (EF) Manufacturer’s Certificate Of Proper Installation.pdf PDF
ESBD_396277_1739554252449_ATTACHMENT G.U - Ellington Field (EF) Sustainable Design Requirements.pdf PDF
ESBD_396277_1739554109501_ATTACHMENT G.I - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Cultural Materials.pdf PDF
ESBD_396277_1739554201717_ATTACHMENT G.P - Ellington Field (EF) Contract Closeout.pdf PDF
ESBD_396277_1739554286258_ATTACHMENT G.X - Ellington AFB (EF) AF3000.pdf PDF
ESBD_396277_1739554139903_ATTACHMENT G.K - Ellington AFB (EF) Construction Facilities And Temporary Controls.pdf PDF
ESBD_396277_1739554222221_ATTACHMENT G.R - Ellington Field (EF) EMS Construction Waste Management And Disposal Part 1 - General.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT G.M - ELLINGTON AFB (EF) MATERIAL EQUIPMENT

PART 1 – GENERAL

1. RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and

Supplementary Conditions, apply to this Section.

2. SUMMARY

A. This Section includes:

a. Transportation and handling

b. Storage and protection

c. Product options

d. Substitutions

3. TRANSPORTATION AND HANDLING

A. Transport and handle Products in accordance with manufacturer's instructions.

B. Promptly inspect shipments to ensure that Products comply with requirements, quantities are correct, and Products are undamaged.

C. Provide equipment and personnel to handle Products by methods to prevent soiling, disfigurement, or damage.

4. STORAGE AND PROTECTION

A. Store and protect Products in accordance with manufacturers' instructions, with seals and labels intact and legible.

B. Store sensitive Products in weather tight, climate-controlled enclosures.

C. For exterior storage of fabricated Products, place on sloped supports, above ground.

D. Provide bonded off-site storage and protection when site does not permit on-site storage or protection.

E. Cover Products subject to deterioration with impervious sheet covering. Provide ventilation to avoid condensation or potential degradation of Product.

F. Store loose granular materials on solid flat surfaces in a well-drained area. Prevent mixing with foreign matter.

G. Provide equipment and personnel to store Products by methods to prevent soiling, disfigurement, or damage.

H. Arrange storage of Products to permit access for inspection. Periodically inspect to verify Products are undamaged and are maintained in acceptable condition.

I. Payment for materials stored on site will be made only when the request is accompanied by an inventory of stored materials along with copies of the supplier invoices for the stored materials. Only actual cost of the materials stored will be compensated.

5. PRODUCT OPTIONS

A. Products Specified by Reference Standards or by Description Only: Any Product meeting those standards or description.

B. Products Specified by Naming One or More Manufacturers: Products of manufacturers named and meeting specifications, no options or substitutions allowed.

C. Products Specified by Naming One or More Manufacturers with a Provision for

ELLINGTON FIELD, HOUSTON, TX 21 May 2024

Substitutions: Submit a request for substitution for any manufacturer not named in accordance with the following article.

6. SUBSTITUTIONS

A. Project Manager will consider requests for Substitutions during the submittal phase of the project.

B. Substitutions may be considered when a Product becomes unavailable through no fault of the Contractor.

C. Document each request with complete data substantiating compliance of proposed

Substitution with Contract Documents.

D. A request constitutes a representation that the Contractor:

a. Has investigated proposed Product and determined that it meets or exceeds the quality level of the specified Product.

b. Will provide the same warranty for the Substitution as for the specified

Product.

c. Will coordinate installation and make changes to other Work which may be required for the Work to be complete with no additional cost to Owner.

d. Waives claims for additional costs or time extension which may subsequently become apparent.

E. Substitutions will not be considered when they are indicated or implied on shop drawing or product data submittals, without separate written request, or when acceptance will require revision to the Contract Documents.

F. Substitution Submittal Procedure:

a. Submit three copies of request for Substitution for consideration on

Substitution Request Form attached to this section. Limit each Substitution

Request Form to one proposed Substitution.

b. Submit shop drawings, product data, and certified test results attesting to the proposed Product equivalence.

c. The Project Manager will notify Contractor in writing of decision to accept or reject re- quest.

G. If request for substitution is not accepted by the government, Contractor is responsible for sup- plying item as originally specified or an acceptable substitution without additional cost to the Owner.

File details come from the government source that posted it. Updated .