This document is a Quality Control specification attachment for work at Ellington Air Force Base (AFB) in Houston, Texas, dated May 21, 2024. The document outlines comprehensive quality control requirements including quality assurance procedures for installation, tolerances, references, mockups, inspection and testing services, and manufacturers' field services and reports. The specification requires contractors to monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship to produce work of specified quality.

The contractor is required to employ and pay for an independent testing firm, which must be pre-approved by the Project Manager, to perform inspections and testing. Test reports must be submitted within 3 working days of each test. The contractor is responsible for all testing costs, including any required retesting due to non-conformance. When specified, material or product suppliers must provide qualified staff to observe site conditions, with observer qualifications submitted 30 days in advance for Project Manager approval. Reports must be submitted in duplicate within 30 days of observation.

View the file

Other files

File Type Posted
ESBD_396277_1739554274379_ATTACHMENT G.W - Ellington AFB (EF) AF103_REV.pdf PDF
ESBD_396277_1739554263410_ATTACHMENT G.V - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Unmarked Burials.pdf PDF
ESBD_396277_1739554242664_ATTACHMENT G.T - Ellington Field (EF) Post Award Submittals.pdf PDF
ESBD_396277_1739554019240_ATTACHMENT G.B - Ellington Field (EF) Coordination And Meetings.pdf PDF
ESBD_396277_1739554294506_ATTACHMENT G.Y - Ellington AFB (EF) Form 17 - Visitor Contractor Pass Request (01OCT23).pdf PDF
ESBD_396277_1739554059288_ATTACHMENT G.F - Ellington Field (EF) EMS Hazardous Material Procedures.pdf PDF
ESBD_396277_1739553617667_ATTACHMENT G.2 Application for Texas Identification Number #_AP_152.pdf PDF
ESBD_396277_1739554039934_ATTACHMENT G.D - Ellington AFB (EF) Field Engineering.pdf PDF
ESBD_396277_1739553555834_TMD25-ANG-WJ-24150007 Hush House Transformer Replacement.pdf PDF
ESBD_396277_1739554191020_ATTACHMENT G.O - Ellington Field (EF) Starting Of Systems.pdf PDF
ESBD_396277_1739553606718_ATTACHMENT G.1 Direct Deposit Authorization Form 74-176 (Rev.9-2121).pdf PDF
ESBD_396277_1739553662987_ATTACHMENT G.6 Preferred ALAMO Transformer Schematic.pdf PDF
ESBD_396277_1739554160285_ATTACHMENT G.M - Ellington AFB (EF) Material Equipment.pdf PDF
ESBD_396277_1739553641492_ATTACHMENT G.4 Mandatory Pricing Schedule.xlsx XLSX spreadsheet
ESBD_396277_1739554009810_ATTACHMENT G.A - Ellington Field (EF) General Requirements.pdf PDF
ESBD_396277_1739554170591_ATTACHMENT G.N - Ellington Field (EF) Manufacturers’ Services.pdf PDF
ESBD_396277_1739553654889_ATTACHMENT G.5 Photo of Hush House Transformer.pdf PDF
ESBD_396277_1739554049653_ATTACHMENT G.E - Ellington Field (EF) Safety Policies And Procedures.pdf PDF
ESBD_396277_1739554232203_ATTACHMENT G.S - Ellington AFB (EF) Substitutions Request Form.pdf PDF
ESBD_396277_1739554211970_ATTACHMENT G.Q - Ellington AFB (EF) Cutting And Patching.pdf PDF
ESBD_396277_1739553997116_ATTACHMENT G.7 Project Map-Hush House Map.pdf PDF
ESBD_396277_1739554129070_ATTACHMENT G.J.1 - Ellington AFB (EF) Maintenance Summary Form.pdf PDF
ESBD_396277_1739554029863_ATTACHMENT G.C - Ellington AFB (EF) Project Coordination.pdf PDF
ESBD_396277_1739554149784_ATTACHMENT G.L - Ellington Field JRB Final Asbestos Abatement Report Template.pdf PDF
ESBD_396277_1739554119567_ATTACHMENT G.J - Ellington Field (EF) Operation And Maintenance Data.pdf PDF
ESBD_396277_1739554079011_ATTACHMENT G.F.2 - Ellington AFB (EF) Contractor Hazardous Material Identification Form Close-Out Procedures.pdf PDF
ESBD_396277_1739553628289_ATTACHMENT G.3 Texas Military Department Standard Terms and Conditions Revision 5.pdf PDF
ESBD_396277_1739554068682_ATTACHMENT G.F.1 - Ellington AFB (EF) Contractor Hazardous Material Usage Data.pdf PDF
ESBD_396277_1739554099531_ATTACHMENT G.H - Ellington Field (EF) EMS Environmental Protection.pdf PDF
ESBD_396277_1739554181602_ATTACHMENT G.N.1 - Ellington Field (EF) Manufacturer’s Certificate Of Proper Installation.pdf PDF
ESBD_396277_1739554252449_ATTACHMENT G.U - Ellington Field (EF) Sustainable Design Requirements.pdf PDF
ESBD_396277_1739554109501_ATTACHMENT G.I - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Cultural Materials.pdf PDF
ESBD_396277_1739554201717_ATTACHMENT G.P - Ellington Field (EF) Contract Closeout.pdf PDF
ESBD_396277_1739554286258_ATTACHMENT G.X - Ellington AFB (EF) AF3000.pdf PDF
ESBD_396277_1739554139903_ATTACHMENT G.K - Ellington AFB (EF) Construction Facilities And Temporary Controls.pdf PDF
ESBD_396277_1739554222221_ATTACHMENT G.R - Ellington Field (EF) EMS Construction Waste Management And Disposal Part 1 - General.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT G.G - ELLINGTON AFB (EF) QUALITY CONTROL

PART 1 – GENERAL

1. SUMMARY

A. This Section includes:

a. Quality assurance – control of installation.

b. Tolerances.

c. References.

d. Mockup.

e. Inspecting and testing laboratory services.

f. Manufacturers’ field services and reports.

2. RELATED SECTIONS

A. Attachment G.T - Ellington AFB (EF) Post Award Submittals: Submission of manufacturers’ instructions and certificates.

B. Attachment G.M - Ellington AFB (EF) Material Equipment.

C. Attachment G.O - Ellington AFB (EF) Starting Of Systems.

3. QUALITY ASSURANCE – CONTROL OF INSTALLATION

A. Monitor quality control over suppliers, manufacturers, Products, services, site conditions, and workmanship, to produce Work of specified quality.

B. Comply with manufacturers' instructions, including each step-in sequence.

C. Should manufacturers' instructions conflict with Contract Documents, request clarification from the Project Manager before proceeding.

D. Comply with specified standards as minimum quality for the Work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.

E. Perform work by persons qualified to produce workmanship of specified quality.

F. Secure Products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, or disfigurement.

4. TOLERANCES

A. Monitor tolerance control of installed Products to produce acceptable Work. Do not permit tolerances to accumulate.

B. Comply with manufacturers' tolerances. Should manufacturers' tolerances conflict with Contract Documents, request clarification from the Project Manager before proceeding.

C. Adjust Products to appropriate dimensions; position before securing Products in place.

5. REFERENCES

A. For Products or workmanship specified by association, trade, or other consensus standards, comply with requirements of the standard, except when more rigid requirements are specified or are required by applicable codes.

B. Conform to reference standard by date of issue current on date of Contract

Documents, except where a specific date is established by code.

C. Obtain copies of standards where required by product specification sections.

ELLINGTON FIELD, HOUSTON, TX 21 May 2024

D. The contractual relationship, duties, and responsibilities of the parties in Contract nor those of the Architect or the Project Manager shall not be altered from the Contract

Documents by mention or inference otherwise in any reference document.

6. INSPECTING AND TESTING LABORATORY SERVICES

A. Contractor shall employ and pay for specified services of an independent firm to perform inspecting and testing. The independent lab shall be approved by the Project

Manager prior to use and should be submitted in sufficient time to eliminate delay.

B. The independent firm will perform inspections, tests, and other services specified in individual specification sections and as required by the Project Manager. Test reports are required to be submitted within 3 working days of each test performed.

C. Inspecting, testing, and source quality control may occur on or off the project site.

Perform off-site inspecting or testing as required by the Project Manager.

D. Reports will be submitted by the independent firm to the Project Manager and the

Contractor, in duplicate, indicating observations and results of tests and indicating compliance or non-compliance with Contract Documents.

E. Cooperate with independent firm; furnish samples of materials, design mix, equipment, tools, storage, safe access, and assistance by incidental labor as requested.

F. Notify the Project Manager and independent firm in writing 24 hours prior to expected time for operations requiring services.

G. Make arrangements with independent firm and pay for additional samples and tests required for Contractor's use.

H. Testing or inspecting does not relieve Contractor to perform Work to contract requirements.

I. Retesting required because of non-conformance to specified requirements shall be performed by the same independent firm on instructions by the Project Manager.

Payment for all testing services (including re-testing) will be the responsibility of the

Contractor.

7. MANUFACTURERS’ FIELD SERVICES AND REPORTS

A. When specified in individual specification sections, require material or Product suppliers or manufacturers to provide qualified staff personnel to observe site conditions, conditions of surfaces and installation, quality of workmanship, start-up of equipment, test, adjust and balance of equipment as applicable, and to initiate instructions when necessary.

B. Submit qualifications of observer to the Project Manager 30 days in advance of required observations. Observer subject to approval of the Project Manager.

C. Report observations and site decisions or instructions given to applicators or installers that are supplemental or contrary to manufacturers' written instructions.

D. Submit report in duplicate within 30 days of observation to Architect for information if applicable.