About this file

This is a field engineering requirements document for Ellington Air Force Base (AFB) in Houston, Texas dated May 21, 2024. The document outlines requirements for contractor-provided field engineering services, including survey work and professional engineering services required for construction. The contractor must retain a Texas-registered surveyor and is responsible for all vertical and horizontal control, field staking methods, and preservation of survey marks and reference points.

The contractor must maintain detailed records and submit surveys showing installations of roadways, drainage, site grading, buried utilities, and manholes at project closeout. A key requirement is the preparation of a GIS electronic map that integrates with the 147 CES Common Installation Picture (CIP) using GPS geospatial data per ANG ETL 19-12 specifications. The contractor must provide complete data points for all constructed features including building corners, valves, manholes, handholes, light poles, fire hydrants, and parking lots to enable comprehensive location tracking by the government.

View the file

Other files

File Type Posted
ESBD_396277_1739554274379_ATTACHMENT G.W - Ellington AFB (EF) AF103_REV.pdf PDF
ESBD_396277_1739554263410_ATTACHMENT G.V - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Unmarked Burials.pdf PDF
ESBD_396277_1739554242664_ATTACHMENT G.T - Ellington Field (EF) Post Award Submittals.pdf PDF
ESBD_396277_1739554019240_ATTACHMENT G.B - Ellington Field (EF) Coordination And Meetings.pdf PDF
ESBD_396277_1739554089469_ATTACHMENT G.G - Ellington AFB (EF) Quality Control.pdf PDF
ESBD_396277_1739554294506_ATTACHMENT G.Y - Ellington AFB (EF) Form 17 - Visitor Contractor Pass Request (01OCT23).pdf PDF
ESBD_396277_1739554059288_ATTACHMENT G.F - Ellington Field (EF) EMS Hazardous Material Procedures.pdf PDF
ESBD_396277_1739553617667_ATTACHMENT G.2 Application for Texas Identification Number #_AP_152.pdf PDF
ESBD_396277_1739553555834_TMD25-ANG-WJ-24150007 Hush House Transformer Replacement.pdf PDF
ESBD_396277_1739554191020_ATTACHMENT G.O - Ellington Field (EF) Starting Of Systems.pdf PDF
ESBD_396277_1739553606718_ATTACHMENT G.1 Direct Deposit Authorization Form 74-176 (Rev.9-2121).pdf PDF
ESBD_396277_1739553662987_ATTACHMENT G.6 Preferred ALAMO Transformer Schematic.pdf PDF
ESBD_396277_1739554160285_ATTACHMENT G.M - Ellington AFB (EF) Material Equipment.pdf PDF
ESBD_396277_1739553641492_ATTACHMENT G.4 Mandatory Pricing Schedule.xlsx XLSX spreadsheet
ESBD_396277_1739554009810_ATTACHMENT G.A - Ellington Field (EF) General Requirements.pdf PDF
ESBD_396277_1739554170591_ATTACHMENT G.N - Ellington Field (EF) Manufacturers’ Services.pdf PDF
ESBD_396277_1739553654889_ATTACHMENT G.5 Photo of Hush House Transformer.pdf PDF
ESBD_396277_1739554049653_ATTACHMENT G.E - Ellington Field (EF) Safety Policies And Procedures.pdf PDF
ESBD_396277_1739554232203_ATTACHMENT G.S - Ellington AFB (EF) Substitutions Request Form.pdf PDF
ESBD_396277_1739554211970_ATTACHMENT G.Q - Ellington AFB (EF) Cutting And Patching.pdf PDF
ESBD_396277_1739553997116_ATTACHMENT G.7 Project Map-Hush House Map.pdf PDF
ESBD_396277_1739554129070_ATTACHMENT G.J.1 - Ellington AFB (EF) Maintenance Summary Form.pdf PDF
ESBD_396277_1739554029863_ATTACHMENT G.C - Ellington AFB (EF) Project Coordination.pdf PDF
ESBD_396277_1739554149784_ATTACHMENT G.L - Ellington Field JRB Final Asbestos Abatement Report Template.pdf PDF
ESBD_396277_1739554119567_ATTACHMENT G.J - Ellington Field (EF) Operation And Maintenance Data.pdf PDF
ESBD_396277_1739554079011_ATTACHMENT G.F.2 - Ellington AFB (EF) Contractor Hazardous Material Identification Form Close-Out Procedures.pdf PDF
ESBD_396277_1739553628289_ATTACHMENT G.3 Texas Military Department Standard Terms and Conditions Revision 5.pdf PDF
ESBD_396277_1739554068682_ATTACHMENT G.F.1 - Ellington AFB (EF) Contractor Hazardous Material Usage Data.pdf PDF
ESBD_396277_1739554099531_ATTACHMENT G.H - Ellington Field (EF) EMS Environmental Protection.pdf PDF
ESBD_396277_1739554181602_ATTACHMENT G.N.1 - Ellington Field (EF) Manufacturer’s Certificate Of Proper Installation.pdf PDF
ESBD_396277_1739554252449_ATTACHMENT G.U - Ellington Field (EF) Sustainable Design Requirements.pdf PDF
ESBD_396277_1739554109501_ATTACHMENT G.I - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Cultural Materials.pdf PDF
ESBD_396277_1739554201717_ATTACHMENT G.P - Ellington Field (EF) Contract Closeout.pdf PDF
ESBD_396277_1739554286258_ATTACHMENT G.X - Ellington AFB (EF) AF3000.pdf PDF
ESBD_396277_1739554139903_ATTACHMENT G.K - Ellington AFB (EF) Construction Facilities And Temporary Controls.pdf PDF
ESBD_396277_1739554222221_ATTACHMENT G.R - Ellington Field (EF) EMS Construction Waste Management And Disposal Part 1 - General.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT G.D - ELLINGTON AFB (EF) FIELD ENGINEERING

PART 1 – GENERAL

1. REQUIREMENTS INCLUDED

A. The Contractor shall provide and pay for field engineering services for:

a. Survey work required in execution of work.

b. Civil, structural, or other professional engineering services specified or required to execute the Contractor’s construction method.

B. The method of field staking for the construction of the work shall be at the option of the Contractor.

C. The accuracy of any method of staking shall be responsibility of the Contractor. All engineering for vertical and horizontal control shall be the responsibility of the

Contractor.

a. The Contractor shall be held responsible for the preservation of all stakes and marks. If any stakes or marks are carelessly or willfully disturbed by the

Contractor, the Contractor shall not proceed with any work until he has re-established such points, marks, lines, and elevations as may be necessary for the prosecution of the work.

b. The Contractor shall retain the services of a competent surveyor, registered in the State of Texas, to lay out the work and maintain a survey during construction. The Contractor shall be solely responsible for proper location of the work.

2. SURVEY REFERENCE POINTS

A. Locate and protect control points prior to starting site work and preserve all permanent reference points during construction.

a. Make no changes or relocations without prior written notice to the Project

Manager.

b. Report to the Project Manager when any reference point is lost or destroyed or requires relocation because of necessary changes in grades or locations.

3. PROTECT SURVEY REQUIREMENTS

A. Establish temporary benchmarks as needed, referenced to data established by survey control points. Record locations with horizontal and vertical data, on Record

Drawings.

B. Establish lines and levels, and locate and lay out, by instrumentation and similar appropriate means:

a. Site improvements, including utility slopes and invert elevations.

b. Batter boards for structures.

c. From time to time, verify layouts by same methods.

4. RECORDS

A. Maintain a complete, accurate log of al control and survey work as it progresses.

B. At Contract closeout, submit a survey of installation of roadways, drainage, site grading, buried utilities, and manholes at the same scale as the Construction

Documents indicating elevations and stationing at 100-foot increments.

ELLINGTON FIELD, HOUSTON, TX 21 May 2024

5. SUBMITTALS

A. On request of the Project Manager, submit documentation to verify accuracy of field engineering work.

B. Submit Drawings showing locations of all pipes and structures constructed. This

Drawing shall be included with the Record Drawings.

6. GEOSPATIAL DATA STANDARD

A. Prepare and furnish geographical Information System (GIS) electronic map of the site and site utilities that integrates into the 147 CES Common Installation Picture (CIP) using Geographical Positioning System (GPS) Geospatial Electronic data per ANG

ETL 19-12, Geographic Information System (GIS) Data Format Specifications Dated

18 November 2019.

B. At the end of the project all data points will need to be provided by the contractor.

Provide all final locations of the corners (outline) of building, valves, manholes, handholes, light poles, fire hydrants, outline of parking lots and other items to provide a complete picture of what has been built and installed. Provide enough data to enable the government to have the location of everything on the project.