ESBD_371089_1723062252989_ATTACHMENT G.B - Ellington Field (EF) Coordination And Meetings.pdf

PDF 56 KB Posted

Attached to
TMD Texas Air National Guard Ellington Field Cable Repair
Solicitation number
TMD24-ANG-WJ-24150009
Issued by
Harris County, Texas

About this file

This document is an attachment related to a state and local contract opportunity for the Texas Military Department (TMD), Texas Air National Guard (ANG) 147th Attack Wing to repair the existing radio frequency (RF) cable at the 35 localizer located at Ellington Field, Building 1452, in Houston, Texas. The project requires manually trenching and removing the previously damaged RF heliax cable and replacing it with 150 linear feet of new cable and conduits. The document outlines coordination, preconstruction, progress, and pre-installation meeting requirements, as well as examination and preparation procedures for the work.

The related state and local contract opportunity is for the TMD Texas Air National Guard Ellington Field Cable Repair project, which is located in Harris County, Texas. The purpose of the project is to repair the existing RF cable at the 35 localizer at Ellington Field.

View the file

Other files

File Type Posted
ESBD_371089_1723062377226_ATTACHMENT G.E - Ellington Field (EF) Safety Policies And Procedures.pdf PDF
ESBD_371089_1723062692834_ATTACHMENT G.I - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Cultural Materials.pdf PDF
ESBD_371089_1723061838423_ATTACHMENT G.1 Direct Deposit Authorization Form.pdf PDF
ESBD_371089_1723062860299_ATTACH~3.PDF PDF
ESBD_371089_1723063388690_AT2598~1.PDF PDF
ESBD_371089_1723062537933_ATTACHMENT G.F.2 - Ellington AFB (EF) Contractor Hazardous Material Identification Form Close-Out Procedures.pdf PDF
ESBD_371089_1723062454062_ATTACHMENT G.F - Ellington Field (EF) EMS Hazardous Material Procedures.pdf PDF
ESBD_371089_1723062521452_ATTACHMENT G.F.1 - Ellington AFB (EF) Contractor Hazardous Material Usage Data.pdf PDF
ESBD_371089_1723062307951_ATTACHMENT G.D - Ellington AFB (EF) Field Engineering.pdf PDF
ESBD_371089_1723061872655_ATTACHMENT G.2 Application for Texas Identification Number.pdf PDF
ESBD_371089_1723062831590_ATTACHMENT G.J.1 - Ellington AFB (EF) Maintenance Summary Form.pdf PDF
ESBD_371089_1723063298033_ATTACH~2.PDF PDF
ESBD_371089_1723061940566_ATTACHMENT G.4 Pricing Schedule.pdf PDF
ESBD_371089_1723062969469_ATTACH~2.PDF PDF
ESBD_371089_1723062990834_ATTACHMENT G.O - Ellington Field (EF) Starting Of Systems.pdf PDF
ESBD_371089_1723061909201_ATTACHMENT G.3 TMD Standard Terms and Conditions.pdf PDF
ESBD_371089_1723062041430_ATTACHMENT G.7 Trench Details.pdf PDF
ESBD_371089_1723063157585_ATTACH~2.PDF PDF
ESBD_371089_1723062600331_ATTACHMENT G.G - Ellington AFB (EF) Quality Control.pdf PDF
ESBD_371089_1723062025654_ATTACHMENT G.6 Four (4) Site Photos.pdf PDF
ESBD_371089_1723654956338_ESBD Addendum 1 - TMD24-ANG-WJ-24150009.pdf PDF
ESBD_371089_1723062100169_ATTACHMENT G.A - Ellington Field (EF) General Requirements.pdf PDF
ESBD_371089_1724098412133_ESBD Addendum 2 - TMD24-ANG-WJ-24150009.pdf PDF
ESBD_371089_1723063316199_ATTACH~3.PDF PDF
ESBD_371089_1723063353258_ATTACHMENT G.W - Ellington AFB (EF) AF103_REV.pdf PDF
ESBD_371089_1723062943009_ATTACHMENT G.N - Ellington Field (EF) Manufacturers’ Services.pdf PDF
ESBD_371089_1723061959244_ATTACHMENT G.5 Photo Overview.pdf PDF
ESBD_371089_1723062876491_ATTACHMENT G.M - Ellington AFB (EF) Material Equipment.pdf PDF
ESBD_371089_1723062848141_ATTACH~2.PDF PDF
ESBD_371089_1723062731760_ATTACHMENT G.J - Ellington Field (EF) Operation And Maintenance Data.pdf PDF
ESBD_371089_1723063286623_ATTACHMENT G.T - Ellington Field (EF) Post Award Submittals.pdf PDF
ESBD_371089_1723062652487_ATTACHMENT G.H - Ellington Field (EF) EMS Environmental Protection.pdf PDF
ESBD_371089_1723062296770_ATTACHMENT G.C - Ellington AFB (EF) Project Coordination.pdf PDF
ESBD_371089_1723061785599_TMD24-ANG-WJ-24150009 Ellington Cable Repair.pdf PDF
ESBD_371089_1723063177299_ATTACHMENT G.S - Ellington AFB (EF) Substitutions Request Form.pdf PDF
ESBD_371089_1723063015395_ATTACHMENT G.P - Ellington Field (EF) Contract Closeout.pdf PDF
ESBD_371089_1723063367434_ATTACHMENT G.X - Ellington AFB (EF) AF3000.pdf PDF
ESBD_371089_1723063135331_ATTACHMENT G.Q - Ellington AFB (EF) Cutting And Patching.pdf PDF
ESBD_371089_1723062848141_ATTACH~2.PDF PDF
ESBD_371089_1723062652487_ATTACHMENT G.H - Ellington Field (EF) EMS Environmental Protection.pdf PDF
ESBD_371089_1723062537933_ATTACHMENT G.F.2 - Ellington AFB (EF) Contractor Hazardous Material Identification Form Close-Out Procedures.pdf PDF
ESBD_371089_1723063316199_ATTACH~3.PDF PDF
ESBD_371089_1723063367434_ATTACHMENT G.X - Ellington AFB (EF) AF3000.pdf PDF
ESBD_371089_1723654956338_ESBD Addendum 1 - TMD24-ANG-WJ-24150009.pdf PDF
ESBD_371089_1723063015395_ATTACHMENT G.P - Ellington Field (EF) Contract Closeout.pdf PDF
ESBD_371089_1723062377226_ATTACHMENT G.E - Ellington Field (EF) Safety Policies And Procedures.pdf PDF
ESBD_371089_1723062990834_ATTACHMENT G.O - Ellington Field (EF) Starting Of Systems.pdf PDF
ESBD_371089_1723063177299_ATTACHMENT G.S - Ellington AFB (EF) Substitutions Request Form.pdf PDF
ESBD_371089_1723062041430_ATTACHMENT G.7 Trench Details.pdf PDF
ESBD_371089_1723062454062_ATTACHMENT G.F - Ellington Field (EF) EMS Hazardous Material Procedures.pdf PDF
Show 40 more

Latest 50 of 77 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT G.B - ELLINGTON AFB (EF) COORDINATION AND

MEETINGS

PART 1 – GENERAL

1. SUMMARY

A. This Section includes:

a. Coordination

b. Preconstruction meeting

c. Progress meetings

d. Pre-installation meetings

e. Examination

f. Preparation

2. COORDINATION

A. Coordinate scheduling, submittals, and Work of the various sections of the Project

Manual to assure efficient and orderly sequence of installation of interdependent construction elements, [with provisions for accommodating items installed later].

B. Verify utility requirements and characteristics of operating equipment are compatible with building utilities. Coordinate work of various sections having interdependent responsibilities for installing, connecting to, and placing in service, such equipment.

C. Coordinate space requirements and installation of mechanical and electrical work which are indicated diagrammatically on Drawings. Follow routing shown for pipes, ducts, and conduit, as closely as practicable; place runs parallel with line of building.

Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs.

D. In finished areas [except as otherwise indicated], conceal pipes, ducts, and wiring within the construction. Coordinate locations of fixtures and outlets with finish elements.

E. Coordinate completion and cleanup of Work of separate sections in preparation for

Substantial Completion.

F. After Owner occupancy of premises, coordinate access to site for correction of defective Work and Work not in accordance with Contract Documents, to minimize disruption of Owner's activities.

3. PRE-CONSTRUCTION MEETING

A. The Project Manager will schedule a meeting after Notice of Award.

B. Agenda:

a. Distribution of Contract Documents

b. Submission of list of Subcontractors, list of Products, schedule of values, and proposed construction schedule.

c. Designation of personnel representing the parties in Contract

d. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures

e. Scheduling

f. Safety plan submittal

ELLINGTON FIELD, HOUSTON, TX 21 May 2024

4. PROGRESS MEETINGS

A. The Contractor will in Coordination with the Project Manager:

a. Schedule and administer meetings throughout progress of the Work at maximum monthly intervals, every 2-weeks is preferred.

b. Make arrangements for meetings, prepare agenda with copies for participants, and preside at meetings.

c. Review coordination with related work

d. Provide written documentation of the meeting minutes for review and acceptance by all present within 3 working days of each meeting.

B. Attendance Required: Job superintendent, major Subcontractors and suppliers, the

Project Manager as appropriate to agenda topics for each meeting.

C. Agenda:

a. Review minutes of previous meetings

b. Review of Work progress

c. Field observations, problems, and decisions

d. Identification of problems which impede planned progress.

e. Review of submittals schedule with emphasis on Critical Path Items and status of submittals

f. Review of off-site fabrication and delivery schedules

g. Maintenance of progress schedule

h. Corrective measures to regain projected schedules.

i. Planned progress during succeeding work period.

j. Coordination of projected progress

k. Maintenance of quality and work standards

l. Effect of proposed changes on progress schedule and coordination

m. Other business relating to Work.

5. PRE-INSTALLATION MEETING

A. When required in individual specification sections, convene a pre-installation meeting at work site prior to commencing work of the section.

B. Require attendance of parties directly affecting, or affected by, work of the

C. specific section.

D. Notify the Project Manager four days in advance of meeting date.

E. Contractor will prepare agenda and preside at meeting:

a. Review conditions of installation, preparation, and installation procedures

b. Provide written documentation of the minutes of the meeting within 3 working days of each meeting.

PART 2 – EXECUTION

1. EXAMINATION

A. Verify that existing site conditions and substrate surfaces are acceptable for subsequent Work. Beginning new Work means acceptance of existing conditions.

B. Verify that existing substrate is capable of structural attachment of new Work being applied or attached.

ELLINGTON FIELD, HOUSTON, TX 21 May 2024

C. Examine and verify specific conditions described in individual specification sections.

D. Verify that utility services are available, of the correct characteristics, and in the correct location.

2. PREPARATION

A. Clean substrate surfaces prior to applying next material or substance.

B. Seal cracks or openings of substrate prior to applying next material or substance.

C. Apply any manufacturer required or recommended substrate primer, sealer, or conditioner prior to applying any new material or substance in contact or bond.