ELibrary 19-Discovery AO 2019 Work Plan S-346-Redacted.pdf
PDF 868 KB Posted
- Attached to
- NRESS III RFP 80HQTR26R0002
- Solicitation number
- 80HQTR26R0002
About this file
This document is a NASA Research and Education Support Services (NRESS) Work Plan for the 2019 Discovery Program Announcement of Opportunity (AO). Arctic Slope Technical Services, Inc. will support NASA's Science Mission Directorate in managing the solicitation process for the Discovery Program, with a performance period from April 19, 2019 through January 31, 2020. Key responsibilities include publishing the AO on NSPIRES, supporting a pre-proposal meeting, managing Notices of Intent (NOIs) and proposal submissions, coordinating scientific and technical monitoring committee (TMC) reviews, organizing panel reviews, and supporting selection committee meetings.
The work plan outlines a detailed timeline with critical dates, including NOI due date of 4/30/19, proposal due date of 7/1/19, and expected panel dates in September 2019. The contractor will handle multiple administrative and logistical tasks such as setting up electronic submission systems, screening proposals for compliance, coordinating reviewer assignments, preparing evaluation forms, managing conflict of interest reports, and providing support for various NASA review committees. The solicitation is expected to receive approximately 35 proposals, with 70 total panelists (65 non-government) across 6 panels, culminating in a selection meeting in December 2019.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Work Plan S-346: Discovery AO Page 2 of 8 Pages
• Staff a Help Desk to assist proposers to access NSPIRES, and guide PIs through the system to enable them to enter their NOI data.
• Provide NOI log to NASA.
• Respond to requests for additional information from proposers. Solicitation-specific queries will be directed to the appropriate NASA Manager.
• Set up NSPIRES to enable proposers to electronically submit proposals directly to the database.
• Proposals are automatically numbered and coded by the database.
• Staff a Help Desk to assist proposers to access NSPIRES, and guide PIs through the system to enable them to enter their proposal data.
• Allow for repeated revisions of proposals up to the deadline for receipt of proposals.
• Provide NASA HQ with sets of CDs of the proposals and Excel files of all abstracts and logs of proposers, titles, requested budgets, etc.
• Provide proposals to Langley Export Administrator for export control review.
• Ensure that TMC reviewers have signed Non-Disclosure Forms via NSPIRES and advise SOMA of status.
• Screen incoming proposals to determine administrative compliance with solicitation requirements.
• Use electronic redaction to edit out any ITAR-sensitive information as required.
• Assist in preparation of Evaluation Forms and instructions to all reviewers.
• Receive review assignments for science reviewers and enter into the NSPIRES database to provide access to the proposal review form for reviewers.
• Prepare a conflict of interest report for Program Manager that identifies any conflicts between reviewers and proposal PI, Co-I, Collaborators, and/or institution.
• Set up NSPIRES for submission of science reviews. Each reviewer will only have access to his/her own review until final, whereupon Primary reviewers will be able to view other final reviews on proposals for which they are primary.
• Arrange and support a pre-review meeting of lead reviewers on the proposals.
• Arrange a science review and provide on-site equipment and staff to support the review.
• Provide reviewers with soft copy of reviews from NSPIRES written prior to the meeting. External reviews will not be made anonymous.
• Provide NASA with panel proceedings, as required.
• Provide NASA with a binder of final Panel Evaluation Forms (and softcopy) and other reports, as required.
• Fund the science meeting, and provide travel, per diem, and honoraria at
• Support a TMC review. Fund meeting facilities, including all equipment necessary to run the meeting. Travel, per diem, and honoraria for TMC reviewers will be provided by another contract.
• Prepare TMC, science review, and additional documentation for the Categorization Subcommittee and Steering Committee, and provide Executive Secretary support for these meetings.
• Support preparation for the Selection meeting. Prepare selection letters and associated paperwork.
Page 3 of 8 Pages
• Post the press release announcing the awards on NSPIRES.
The following activities are expected to occur after task end and are not costed.
• Support preparation of materials for debrief sessions.
• Conduct and receive customer surveys from responsible NASA official, peer reviewers, and TMC members.
Deliverables include: NOI Log; Proposal Log; draft evaluation forms; draft reviewer instructions; logistics and on-site support for the review panel; travel report; final Panel Evaluation Forms; electronic selection and procurement materials via NSPIRES;
abstracts posted on NSPIRES; and honoraria, travel and per diem.
Performance Schedule
The following performance schedule and Work Plan milestones are proposed:
Activity 1: Support for the Discovery19 AO
4/1/19 Publish AO on NSPIRES 4/26/19 Support pre-proposal meeting 4/30/19 NOIs due 5/3/19 Confirm NOI Log for NASA (no later than) 6/10/19 NASA Langley finalizes TMC reviewers (tentative) 6/17/19 TMC reviewers access NSPIRES to confirm NDAs 6/21/19 NRESS confirms TMC NDAs for NASA Langley 7/1/19 Proposals Due 7/5/19 Confirm Proposal log for NASA; CDs distributed to NASA HQ & NASA Langley 8/5/19 NASA finalizes science reviewers and assignments for NRESS (tentative) September, 2019 TMC Review September, 2019 Science Panel Review October, 2019 Categorization SubCommittee book materials to NRESS October, 2019 Categorization SubCommittee books distributed October, 2019 Categorization Subcommittee October, 2019 Steering Committee book materials to NRESS October, 2019 Steering Books distributed October, 2019 Steering Committee December, 2019 Selection Committee book materials to NRESS December, 2019 Selection books distributed January, 2020 Selection Meeting January, 2020 Post press release The final milestones remain after 1/31/20.
Jan-March, 2020 Support debrief documentation, as requested
Reporting
Page 6 of 8 Pages
Attachment 1 SMD NRA Support Work Plan
S-346
This Work Plan authorizes the NASA Research and Education Support Services (NRESS) contractor to support activities related to the Dsicovery Program, as stated in the attachment for the Science Mission Directorate (SMD). This Work Plan covers activities, and specialized reporting requirements as stipulated in Section A - Performance Requirements. Work and costs directly associated with any other Work Plan is not covered by this Work Plan.
The period of performance for this Work Plan is April 19, 2019 through January 31, 2020.
A. Performance Requirements
This Work Plan invokes the following WBS Sections:
WBS 1.0 Research Announcement and Solicitation Planning and Support
Applies – All Sections AS REQUIRED
WBS 2.0 Notice of Intent to Propose
WBS 3.0 Proposal Documents, Panel, Review, and Selection Decision Support
Applies – All Sections AS REQUIRED
WBS 4.0 Panel and Peer Review Planning, Operations, Logistics, and Close-Out
Applies – All Sections AS REQUIRED
WBS 5.0 Programmatic Documentation, Analytics, and Reporting
Applies – All Sections AS REQUIRED
WBS 6.0 Process or Systems Improvements and User Acceptance
Page 7 of 8 Pages
Requirements for delivery of specific items:
• At least two weeks prior to each panel meeting, provide the following to the appropriate NASA Program Official: 1) a spreadsheet of proposals to be considered,
2) list of approved reviewer assignments.
• Electronic versions of preliminary critiques are to be made available to the appropriate NASA program official within calendar days of completion of a review panel meeting.
• Procurement packages containing a copy of the NRA, AO, or CAN, cover page, original proposals, and copies of selection letters, to be delivered to the Headquarters Program Official for grant processing within workdays after selection letters have been mailed.
B. Reporting Requirements
The following reporting requirements are for the overall contract. All other reporting requirements will be specified in other Work Plans.
• Performance Reporting (to Customer Performance Monitor)
• Ad hoc reporting
This request requires a report from the contractor naming each individual traveler, stating the purpose of their travel (e.g., AIAA conference), and with a breakdown of estimated costs for each traveler, e.g., for airfare, per diem, etc. This report is to be provided to NASA before the travel occurs and must be approved by a civil servant that will serve as the authorization necessary for “invitational travel orders.” This report can be provided by email to the Program Manager and should be approved via return email to the contractor. Updates and changes to the report can be communicated also via email to the Program Manager. This report will be due at least three weeks before the travel is to commence.
C. Performance Schedule (Tentative)
Program
NOI
Due Date
Proposal Due Date # Proposals Panel Dates # Panelists # Panels
Discovery19 4/30/
19 7/1/19 35 September, 2019 70 (65 non govt) 6 TMC* September, 2019 Categorization* October, 2019 Steering* October, 2019 Selection* December, 2019
Page 8 of 8 Pages
* These activities are NASA HQ meetings that will only require minimal support (note-taking, document prep, etc.) and will not require travel support or event logistical support.