The provided document is a compilation of technical specification sections for earthwork and related construction activities for a Marine Corps Base Camp Lejeune project (P-1574 MRSB Operation Support Facility). The document contains detailed technical specifications for several key construction activities, including:
-
Clearing and Grubbing (Section 31 11 00): Specifies requirements for removing vegetation, trees, stumps, and debris, including herbicide application, soil preparation, and disposal of materials. Contractors must follow strict environmental and regulatory guidelines, including using commercially certified applicators and maintaining detailed pest management records.
-
Excavation and Fill (Section 31 23 00.00 20): Provides comprehensive guidelines for soil excavation, backfilling, compaction, and material testing. Key requirements include soil moisture testing, compaction standards (85-95% depending on location), and strict quality control measures. Off-site soils must be tested for petroleum hydrocarbons, BTEX, PCBs, and hazardous waste characteristics.
-
Additional sections cover geogrid soil stabilization, chemical termite control, and timber pile installation, each with detailed technical requirements for materials, installation methods, testing, and quality control. The specifications are intended to ensure precise construction techniques, environmental compliance, and structural integrity for the Marine Corps facility project.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
P-1574 MRSB OPERATION SUPPORT FACILITY (OSF) 1717488
MCB CAMP LEJEUNE, NC
SECTION 31 11 00
CLEARING AND GRUBBING
11/18
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. DEPARTMENT OF DEFENSE (DOD)
DODI 4150.07 (2019) DOD Pest Management Program
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Herbicide Application Plan
SD-03 Product Data
Tree Wound Paint
Herbicides; G
SD-07 Certificates
Qualifications; G
SD-11 Closeout Submittals
Pest Management Report
1.3 QUALITY CONTROL
1.3.1 Regulatory Requirements
Comply with DODI 4150.07 for requirements on Contractor's licensing, certification, and record keeping. Maintain daily records using the Pest Management Maintenance Record, DD Form 1532-1, or a computer generated equivalent. These forms may be obtained from the main web site:
https://www.acq.osd.mil/eie/afpmb/docs/standardlists/dd1532-1.xlsm .
1.3.2 Qualifications
For the application of herbicides, use the services of an applicator who is commercially certified in the state where the work is to be performed as required by DODI 4150.07 . Submit a copy of the pesticide applicator certificates.
SECTION 31 11 00 Page 1
1.4 DELIVERY, STORAGE, AND HANDLING
Deliver materials to the site, and handle in a manner which will maintain the materials in their original manufactured or fabricated condition until ready for use.
1.4.1 Storage
Storage of herbicides on the installation will not be permitted unless it is written into the contract.
1.4.2 Handling
Handle herbicides in accordance with the manufacturer's label and Safety Data Sheet (SDS), preventing contamination by dirt, water, and organic material. Protect herbicides from weather elements as recommended by the manufacturer's label and SDS. Spill kits must be maintained on herbicide control vehicles. Mixing of herbicides on the installation will not be permited unless it is written into the contract.
PART 2 PRODUCTS
2.1 MATERIALS
2.1.1 Tree Wound Paint
Use bituminous based paint from standard manufacture specially formulated for tree wounds.
2.1.2 Herbicide
Provide herbicides currently registered by the EPA or approved for such use by the appropriate agency of the host county and approved by the Contracting Officer. Select a herbicide that is suitable for the climatic conditions at the project site. Submit manufacturer's label and SDS for herbicides proposed for use.
PART 3 EXECUTION
3.1 PREPARATION
3.1.1 Herbicide Application Plan
Prior to commencing application of herbicide, submit a herbicide application plan with proposed sequence of treatment work including dates and times of application. Include the herbicide trade name, EPA registration number, chemical composition, formulation, application rate of active ingredients, method of application, area or volume treated, and amount applied. Include a copy of the pesticide applicator certificates.
3.1.2 Protection
3.1.2.1 Roads and Walks
Keep roads and walks free of dirt and debris at all times.
SECTION 31 11 00 Page 2
3.1.2.2 Trees, Shrubs, and Existing Facilities
Provide protection in accordance with Section 01 57 13.00 22 EROSION AND
SEDIMENT CONTROL.
3.1.2.3 Utility Lines
Protect existing utility lines that are indicated to remain from damage.
Notify the Contracting Officer immediately of damage to or an encounter with an unknown existing utility line. The Contractor is responsible for the repair of damage to existing utility lines that are indicated or made known to the Contractor prior to start of clearing and grubbing operations. When utility lines which are to be removed are encountered within the area of operations, notify the Contracting Officer in ample time to minimize interruption of the service. Refer to Section 01 30 00 ADMINISTRATIVE REQUIREMENTS and Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS for additional utility protection.
3.2 APPLICATION
3.2.1 Herbicide Application
Adhere to safety precautions as recommended by the manufacturer concerning handling and application of the herbicide.
3.2.1.1 Clean Up, Disposal, And Protection
Once application has been completed, proceed with clean up and protection of the site without delay. Clean the site of all material associated with the treatment measures, according to label instructions, and as indicated. Remove and dispose of excess and waste material off Government property.
3.2.1.1.1 Disposal of Herbicide
Dispose of residual herbicides and containers off Government property, and in accordance with the approved disposal plan, label instructions and EPA requirements.
3.3 CLEARING
Clearing consists of the felling, trimming, and cutting of trees into sections and the satisfactory disposal of the trees and other vegetation designated for removal, including downed timber, snags, brush, and rubbish occurring within the areas to be cleared. Cut off flush with or below the original ground surface trees, stumps, roots, brush, and other vegetation in areas to be cleared, except such trees and vegetation as may be indicated or directed to be left standing. Trim dead branches 1-1/2 inches or more in diameter on trees designated to be left standing within the cleared areas and trim all branches to the heights indicated or directed. Neatly cut close to the bole of the tree or main branches, limbs and branches to be trimmed. Paint, with an approved tree-wound paint, cuts more than 1-1/2 inches in diameter. Apply herbicide in accordance with the manufacturer's label to the top surface of stumps designated not to be removed.
3.3.1 Tree Removal
Where indicated or directed, remove trees and stumps that are designated
SECTION 31 11 00 Page 3 as trees from areas outside those areas designated for clearing and grubbing. This work includes the felling of such trees and the removal of their stumps and roots as specified in paragraph GRUBBING. Dispose of trees as specified in paragraph DISPOSAL OF MATERIALS.
3.3.2 Grubbing
Grubbing consists of the removal and disposal of stumps, roots larger than 3 inches in diameter, and matted roots from the designated grubbing areas. Remove material to be grubbed, together with logs and other organic or metallic debris not suitable for foundation purposes, to a depth of not less than 18 inches below the original surface level of the ground in areas indicated to be grubbed and in areas indicated as construction areas under this contract, such as areas for buildings, and areas to be paved. Fill depressions made by grubbing with suitable material and compact to make the surface conform with the original adjacent surface of the ground.
3.4 DISPOSAL OF MATERIALS
Dispose of excess materials in accordance with the approved solid waste management permit and include those materials in the solid waste management report.
All wood or wood like materials, except for salable timber, remaining from clearing, prunning or grubbing such as limbs, tree tops, roots, stumps, logs, rotten wood, and other similiar materials is the property of the Contractor and dispose of as specified. All non-saleable timber and wood or wood like materials remaining from timber harvesting such as limbs, tree tops, roots, stumps, logs, rotten wood, and other similiar materials is the property of the Contractor and dispose of as specified.
3.5 CLOSEOUT ACTIVITIES
3.5.1 Herbicides
Upon completion of this work, submit the Pest Management Report DD Form 1532, or an equivalent computer product, to the Integrated Pest Management Coordinator. This form identifies the type of operation, brand name and manufacturer of herbicide, formulation, concentration or rate of application used.
-- End of Section --
SECTION 31 11 00 Page 4
SECTION 31 23 00.00 20
EXCAVATION AND FILL
02/ 11, CHG 2: 08/ 15
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
AMERICAN WATER WORKS ASSOCIATION (AWWA)
AWWA C600 (2017) Installation of Ductile-Iron Mains and Their Appurtenances
ASTM INTERNATIONAL (ASTM)
ASTM C33/C33M (2018) Standard Specification for Concrete Aggregates
ASTM C136/C136M (2019) Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates
ASTM D698 (2012; E 2014; E 2015) Laboratory Compaction Characteristics of Soil Using Standard Effort (12,400 ft-lbf/cu. ft.
(600 kN-m/cu. m.))
ASTM D1140 (2017) Standard Test Methods for Determining the Amount of Material Finer than 75-µm (No. 200) Sieve in Soils by Washing
ASTM D1556/D1556M (2015; E 2016) Standard Test Method for Density and Unit Weight of Soil in Place by Sand-Cone Method
ASTM D1557 (2012; E 2015) Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3) (2700 kN-m/m3)
ASTM D2321 (2020) Standard Practice for Underground Installation of Thermoplastic Pipe for Sewers and Other Gravity-Flow Applications
ASTM D2487 (2017; E 2020) Standard Practice for Classification of Soils for Engineering Purposes (Unified Soil Classification System)
ASTM D4318 (2017; E 2018) Standard Test Methods for Liquid Limit, Plastic Limit, and Plasticity Index of Soils
SECTION 31 23 00.00 20 Page 1
ASTM D6938 (2017a) Standard Test Method for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth)
NORTH CAROLINA DEPARTMENT OF TRANSPORTATION (NCDOT)
NCDOT SS (2018) Standard Specifications for Roads and Structures
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety -- Safety and Health Requirements Manual
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
EPA SW-846.3-3 (1999, Third Edition, Update III-A) Test Methods for Evaluating Solid Waste:
Physical/Chemical Methods
1.2 DEFINITIONS
1.2.1 Capillary Water Barrier
A layer of clean, poorly graded crushed rock, stone, or natural sand or gravel having a high porosity which is placed beneath a building slab with or without a vapor barrier to cut off the capillary flow of pore water to the area immediately below a slab.
1.2.2 Degree of Compaction
Degree of compaction is expressed as a percentage of the maximum density obtained by the test procedure presented in ASTM D698, for general soil types, abbreviated as percent laboratory maximum density.
1.2.3 Hard Materials
Weathered rock, dense consolidated deposits, or conglomerate materials which are not included in the definition of "rock" but which usually require the use of heavy excavation equipment, ripper teeth, or jack hammers for removal.
1.2.4 Rock
Solid homogeneous interlocking crystalline material with firmly cemented, laminated, or foliated masses or conglomerate deposits, neither of which can be removed without systematic drilling and blasting, drilling and the use of expansion jacks or feather wedges, or the use of backhoe-mounted pneumatic hole punchers or rock breakers; also large boulders, buried masonry, or concrete other than pavement exceeding 1/2 cubic yard in volume. Removal of hard material will not be considered rock excavation because of intermittent drilling and blasting that is performed merely to increase production.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for
SECTION 31 23 00.00 20 Page 2
Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Shoring and Sheeting Plan
Dewatering work plan
Submit 15 days prior to starting work.
SD-06 Test Reports
Borrow Site Testing; G
Fill and backfill/Structural Fill test
Select material test
Porous fill test for capillary water barrier
Density tests
SD-07 Certificates
Material for Rip-Rap; G
Copies of all laboratory and field test reports within 24 hours of the completion of the test.
1.4 DELIVERY, STORAGE, AND HANDLING
Perform in a manner to prevent contamination or segregation of materials.
1.5 CRITERIA FOR BIDDING
Base bids on the following criteria:
a. Surface elevations are as indicated.
b. Pipes or other artificial obstructions, except those indicated, will not be encountered.
c. Ground water elevations indicated by the boring log were those existing at the time subsurface investigations were made and do not necessarily represent ground water elevation at the time of construction.
d. Material character is indicated by the boring logs.
e. Hard materials and rock will not be encountered.
f. Borrow material is not available at the project site. On-site soil material only meets requirement specified herein for common fill.
g. Blasting will not be permitted. Remove material in an approved manner.
h. Unsuitable soils encountered during excavation must be removed and replaced with structural fill material, as directed by the Contracting
SECTION 31 23 00.00 20 Page 3
Officer. Payment for removal and replacement of unsuitable material with structural fill material must be at the contract unit price per cubic yard, multiplied by the total quantity of cubic yards, as specified in the document titled "Price Schedule". Include in the bid a unit price per unit cubic yard based on the quantity stated in the document titled "Price Schedule". If the Contracting Officer requires an increase or decrease in the quantity of soil removed and replaced with structural fill material the contract price will be adjusted in accordance with the Contract Clause of the contract. The unit price bid will be used for upward or downward adjustment of the quantity subject to provisions of "FAR 52.211-18, Variations in Estimated Quantities".
i. Perched water conditions will require groundwater control at depths greater than 2 feet.
1.6 REQUIREMENTS FOR OFF SITE SOIL
Soils brought in from off site for use as fill/backfill material shall be tested for petroleum hydrocarbons, BTEX, PCBs and HW characteristics (including toxicity, ignitability, corrosivity, and reactivity). Material shall not contain concentrations of these analytes above the appropriate State and/or EPA criteria, and shall pass the tests for HW characteristics. Determine petroleum hydrocarbon concentrations by using appropriate State protocols. Determine BTEX concentrations by using EPA SW-846.3-3 Method 5035/8260B. Perform complete TCLP in accordance with EPA SW-846.3-3 Method 1311. Perform HW characteristic tests for ignitability, corrosivity, and reactivity in accordance with accepted standard methods. Perform PCB testing in accordance with accepted standard methods for sampling and analysis of bulk solid samples. Provide borrow site testing for petroleum hydrocarbons and BTEX from a grab sample of material from the area most likely to be contaminated at the borrow site (as indicated by visual or olfactory evidence), with at least one test from each borrow site. For each borrow site, provide borrow site testing for HW characteristics from a composite sample of material, collected in accordance with standard soil sampling techniques. Do not bring material onsite until tests results have been received and approved by the Contracting Officer.
1.7 QUALITY ASSURANCE
1.7.1 Shoring and Sheeting Plan
Submit drawings and calculations, certified by a registered professional engineer, describing the methods for shoring and sheeting of excavations.
Drawings shall include material sizes and types, arrangement of members, and the sequence and method of installation and removal. Calculations shall include data and references used.
The Contractor is required to hire a Professional Geotechnical Engineer to provide inspection of excavations and soil/groundwater conditions throughout construction. The Geotechnical Engineer shall be responsible for performing pre-construction and periodic site visits throughout construction to assess site conditions. The Geotechnical Engineer shall update the excavation, sheeting and dewatering plans as construction progresses to reflect changing conditions and shall submit an updated plan if necessary. A written report shall be submitted, at least monthly, informing the Contractor and Contracting Officer of the status of the plan and an accounting of the Contractor's adherence to the plan addressing any
SECTION 31 23 00.00 20 Page 4 present or potential problems. The Geotechnical Engineer shall be available to meet with the Contracting Officer at any time throughout the contract duration.
1.7.2 Dewatering Work Plan
Submit procedures for accomplishing dewatering work.
1.7.3 Utilities
Movement of construction machinery and equipment over pipes and utilities during construction shall be at the Contractor's risk. Perform work adjacent to non-Government utilities as indicated in accordance with procedures outlined by utility company. Excavation made with power-driven equipment is not permitted within two feet of known Government-owned utility or subsurface construction. For work immediately adjacent to or for excavations exposing a utility or other buried obstruction, excavate by hand. Start hand excavation on each side of the indicated obstruction and continue until the obstruction is uncovered or until clearance for the new grade is assured. Support uncovered lines or other existing work affected by the contract excavation until approval for backfill is granted by the Contracting Officer. Report damage to utility lines or subsurface construction immediately to the Contracting Officer.
1.7.4 Regulatory Requirements
Provide work and materials in accordance with applicable requirements of NCDOT SS except as noted otherwise herein. Divisions and Sections mentioned herein refer to those specifications. NCDOT SS parargraphs "Measurement and Payment" shall not apply.
1.7.4.1 Modifications of References
Where term "Engineer" and "State" is used in NCDOT SS it shall be construed to mean Contracting Officer and Federal Government, respectively.
PART 2 PRODUCTS
2.1 SOIL MATERIALS
2.1.1 Satisfactory Materials
Any materials classified by ASTM D2487 as GW, GP, GM, GP-GM, GW-GM, GC, GP-GC, GM-GC, SW, SP, SM, SW-SM, SC, SW-SC, SP-SM, SP-SC, free of debris, roots, wood, scrap material, vegetation, refuse, soft unsound particles, and frozen, deleterious, or objectionable materials. Unless specified otherwise, the maximum particle diameter shall be one-half the lift thickness at the intended location.
2.1.2 Unsatisfactory Materials
Materials which do not comply with the requirements for satisfactory materials. Unsatisfactory materials also include man-made fills, trash, refuse, or backfills from previous construction. Unsatisfactory material also includes material classified as satisfactory which contains root and other organic matter, frozen material, and stones larger than 3 inches.
The Contracting Officer shall be notified of any contaminated materials.
SECTION 31 23 00.00 20 Page 5
2.1.3 Cohesionless and Cohesive Materials
Cohesionless materials include materials classified in ASTM D2487 as GW, GP, SW, and SP. Cohesive materials include materials classified as GC, SC, ML, CL, MH, and CH. Materials classified as GM, GP-GM, GW-GM, SW-SM, SP-SM, and SM shall be identified as cohesionless only when the fines are nonplastic (plasticity index equals zero). Materials classified as GM and SM will be identified as cohesive only when the fines have a plasticity index greater than zero.
2.1.4 Common Fill
Approved, unclassified soil material with the characteristics required to compact to the soil density specified for the intended location.
2.1.5 Backfill and Fill Material/Structural Fill
ASTM D2487, classification SW, SP, SM, SP-SM with a maximum ASTM D4318 plasticity index of zero, and a maximum of 25 percent by weight passing ASTM D1140, No. 200 sieve.
2.1.6 Select Material
Provide materials meeting requirements of ASTM C33/C33M, size No.57 crushed stone.
2.1.7 Topsoil
Provide as specified in Section 32 93 00 EXTERIOR PLANTS.
2.2 POROUS FILL
ASTM C33/C33M fine aggregate grading with a maximum of 3 percent by weight passing ASTM D1140, No. 200 sieve, or coarse aggregate Size 57, 67, or 77 and conforming to the general soil material requirements specified in paragraph entitled "Satisfactory Materials."
2.3 UTILITY BEDDING MATERIAL
Except as specified otherwise in the individual piping section, provide bedding for buried piping in accordance with AWWA C600, Type 4, except as specified herein. Backfill to top of pipe shall be compacted to 95 percent of ASTM D698 maximum density. Plastic piping shall have bedding to spring line of pipe. Provide ASTM D2321 materials meeting requirements for select material.
2.4 BORROW
Obtain borrow materials required in excess of those furnished from excavations from sources outside of Government property.
2.5 MATERIAL FOR RIP-RAP
Rock material for erosion control rip-rap shall conform to NCDOT SS, Section 1042, Class B, unless indicated otherwise. Provide a certificate for each Class or Type rip-rap material used that material meets specified requirements.
SECTION 31 23 00.00 20 Page 6
2.6 BURIED WARNING AND IDENTIFICATION TAPE
Polyethylene plastic warning tape manufactured specifically for warning and identification of buried utility lines. Provide tape on rolls, 3 inch minimum width, color coded as specified below for the intended utility with warning and identification imprinted in bold black letters continuously over the entire tape length. Warning and identification to read, "CAUTION, BURIED (intended service) LINE BELOW" or similar wording.
Color and printing shall be permanent, unaffected by moisture or soil.
Warning Tape Color Codes
Red: Electric
Yellow: Gas, Oil; Dangerous Materials
Orange: Telephone and Other Communications
Blue: Potable Water Systems
Green: Sewer Systems
2.6.1 Warning Tape for Metallic Piping
Acid and alkali-resistant polyethylene plastic tape conforming to the width, color, and printing requirements specified above. Minimum thickness of tape shall be 0.003 inch. Tape shall have a minimum strength of 1500 psi lengthwise, and 1250 psi crosswise, with a maximum 350 percent elongation.
2.6.2 Detectable Warning Tape for Non-Metallic Piping
Polyethylene plastic tape conforming to the width, color, and printing requirements specified above. Minimum thickness of the tape shall be
0.004 inch. Tape shall have a minimum strength of 1500 psi lengthwise and 1250 psi crosswise. Tape shall be manufactured with integral wires, foil backing, or other means of enabling detection by a metal detector when tape is buried up to 3 feet deep. Encase metallic element of the tape in a protective jacket or provide with other means of corrosion protection.
2.7 DETECTION WIRE FOR NON-METALLIC PIPING
Detection wire shall be insulated single strand, solid copper with a minimum of 12 AWG.
PART 3 EXECUTION
3.1 PROTECTION
3.1.1 Shoring and Sheeting
Provide shoring and sheeting where necessary. In addition to Section 25 A and B of EM 385-1-1 , include provisions in the shoring and sheeting plan that will accomplish the following:
a. Prevent undermining of pavements, foundations and slabs.
SECTION 31 23 00.00 20 Page 7
b. Prevent slippage or movement in banks or slopes adjacent to the excavation.
c. Abandonment of shoring and sheeting materials in place is not allowed.
3.1.2 Drainage and Dewatering
Provide for the collection and disposal of surface and subsurface water encountered during construction.
3.1.2.1 Drainage
So that construction operations progress successfully, completely drain construction site during periods of construction to keep soil materials sufficiently dry. The Contractor shall establish/construct storm drainage features (ponds/basins) at the earliest stages of site development, and throughout construction grade the construction area to provide positive surface water runoff away from the construction activity and/or provide temporary ditches, dikes, swales, and other drainage features and equipment as required to maintain dry soils, prevent erosion and undermining of foundations. When unsuitable working platforms for equipment operation and unsuitable soil support for subsequent construction features develop, remove unsuitable material and provide new soil material as specified herein. It is the responsibility of the Contractor to assess the soil and ground water conditions presented by the plans and specifications and to employ necessary measures to permit construction to proceed. Excavated slopes and backfill surfaces shall be protected to prevent erosion and sloughing. Excavation shall be performed so that the site, the area immediately surrounding the site, and the area affecting operations at the site shall be continually and effectively drained.
3.1.2.2 Dewatering
Groundwater flowing toward or into excavations shall be controlled to prevent sloughing of excavation slopes and walls, boils, uplift and heave in the excavation and to eliminate interference with orderly progress of construction. French drains, sumps, ditches or trenches will not be permitted within 3 feet of the foundation of any structure, except with specific written approval, and after specific contractual provisions for restoration of the foundation area have been made. Control measures shall be taken by the time the excavation reaches the water level in order to maintain the integrity of the in situ material. While the excavation is open, the water level shall be maintained continuously, at least 2 feet below the working level.
Operate dewatering system continuously until construction work below existing water levels is complete. Submit performance records weekly.
3.1.3 Underground Utilities
Location of the existing utilities indicated is approximate. The Contractor shall physically verify the location and elevation of the existing utilities indicated prior to starting construction. The Contractor shall scan the construction site with electromagnetic and sonic equipment and mark the surface of the ground where existing underground utilities are discovered.
SECTION 31 23 00.00 20 Page 8
3.1.4 Machinery and Equipment
Movement of construction machinery and equipment over pipes during construction shall be at the Contractor's risk. Repair, or remove and provide new pipe for existing or newly installed pipe that has been displaced or damaged.
3.2 SURFACE PREPARATION
3.2.1 Clearing and Grubbing
Unless indicated otherwise, remove trees, stumps, logs, shrubs, brush and vegetation and other items that would interfere with construction operations within the limits of disturbance indicated. Remove stumps entirely. Grub out matted roots and roots over 2 inches in diameter to at least 18 inches below existing surface.
3.2.2 Stripping
Strip suitable soil from the site where excavation or grading is indicated and stockpile separately from other excavated material. Material unsuitable for use as topsoil shall be stockpiled and used for common fill.
Locate topsoil so that the material can be used readily for the finished grading. Where sufficient existing topsoil conforming to the material requirements is not available on site, provide borrow materials suitable for use as topsoil. Protect topsoil and keep in segregated piles until needed.
3.2.3 Unsuitable Material
Remove vegetation, debris, decayed vegetable matter, sod, mulch, and rubbish underneath paved areas or concrete slabs.
3.3 EXCAVATION
Excavate to contours, elevation, and dimensions indicated. Reuse excavated materials that meet the specified requirements for the material type required at the intended location. Keep excavations free from water.
Excavate soil disturbed or weakened by Contractor's operations, soils softened or made unsuitable for subsequent construction due to exposure to weather. Excavations below indicated depths will not be permitted except to remove unsatisfactory material. Unsatisfactory material encountered below the grades shown shall be removed as directed by the Contracting Officer. Refill with structural fill and compact to 95 percent of ASTM D698 maximum density. Unless specified otherwise, refill excavations cut below indicated depth with structUral fill lmaterial and compact to 95 percent of ASTM D698 maximum density. Satisfactory material removed below the depths indicated, without specific direction of the Contracting Officer, shall be replaced with structural fill materials to the indicated excavation grade; except as specified for spread footings. Determination of elevations and measurements of approved overdepth excavation of unsatisfactory material below grades indicated shall be done under the direction of the Contracting Officer.
3.3.1 Structures With Spread Footings
Ensure that footing subgrades have been inspected and approved by the Contracting Officer prior to concrete placement. Fill over excavations with concrete during foundation placement.
SECTION 31 23 00.00 20 Page 9
3.3.2 Pipe Trenches
Excavate to the dimension indicated. Grade bottom of trenches to provide uniform support for each section of pipe after pipe bedding placement.
Tamp if necessary to provide a firm pipe bed. Recesses shall be excavated to accommodate bells and joints so that pipe will be uniformly supported for the entire length.
3.3.3 Excavated Materials
Satisfactory excavated material required for fill or backfill shall be placed in the proper section of the permanent work required or shall be separately stockpiled if it cannot be readily placed. Satisfactory material in excess of that required for the permanent work and all unsatisfactory material shall be disposed of as specified in Paragraph
"DISPOSITION OF SURPLUS MATERIAL."
3.3.4 Final Grade of Surfaces to Support Concrete
Excavation to final grade shall not be made until just before concrete is to be placed.
3.4 SUBGRADE PREPARATION
Unsatisfactory material in surfaces to receive fill or in excavated areas shall be removed and replaced with structural fill materials as directed by the Contracting Officer. The surface shall be scarified to a depth of 6 inches before the fill is started. When subgrades are less than the specified density, the ground surface shall be broken up to a minimum depth of 6 inches, pulverized, and compacted to the specified density.
When the subgrade is part fill and part excavation or natural ground, the excavated or natural ground portion shall be scarified to a depth of 6 inches and compacted as specified for the adjacent fill. Material shall not be placed on surfaces that are muddy, frozen, or contain frost.
Compaction shall be accomplished by sheepsfoot rollers, pneumatic-tired rollers, steel-wheeled rollers, or other approved equipment well suited to the soil being compacted. Material shall be moistened or aerated as necessary to plus or minus 2 percent of optimum moisture. Minimum subgrade density shall be as specified herein.
3.4.1 Proof Rolling
Proof rolling shall be done on an exposed subgrade free of surface water (wet conditions resulting from rainfall) which would promote degradation of an otherwise acceptable subgrade. After stripping, proof roll the existing subgrade within and to 5 feet beyond the building area (including entrance landings) and to 5 feet beyond the back of curb at the proposed pavement footprint with six passes of a dump truck loaded with 212 cubic feet of soil or a 15 ton, pneumatic-tired roller. Operate the roller/ truck in a systematic manner to ensure the number of passes over all areas, and at speeds between 2 1/2 to 3 1/2 miles per hour. When proof rolling under buildings, the building subgrade shall be considered to extend 5 feet beyond the building lines, and one-half of the passes made with the roller shall be in a direction perpendicular to the other passes.
Notify the Contracting Officer a minimum of 3 days prior to proof rolling. Proof rolling shall be performed in the presence of the Contracting Officer. Rutting or pumping of material shall be undercut as directed by the Contracting Officer and replaced with structural fill
SECTION 31 23 00.00 20 Page 10 material. Bids shall be based on replacing approximately 200 cubic yards, at various locations.
3.5 FILLING AND BACKFILLING
Fill and backfill to contours, elevations, and dimensions indicated.
Compact each lift before placing overlaying lift.
3.5.1 Common Fill Placement
Provide for general site. Use satisfactory materials. Place in 6 inch lifts. Compact areas not accessible to rollers or compactors with mechanical hand tampers. Aerate material excessively moistened by rain to a satisfactory moisture content. Finish to a smooth surface by blading, rolling with a smooth roller, or both.
3.5.2 Backfill and Fill/Structural Fill Material Placement
Provide for paved areas and under concrete slabs, except where select material is provided. Place in 8 inch lifts. Do not place over wet or frozen areas. Place backfill material adjacent to structures as the structural elements are completed and accepted. Backfill against concrete only when approved. Place and compact material to avoid loading upon or against the structure.
3.5.3 Select Material Placement
Provide as indicated or specified. Place in 6 inch lifts. Do not place over wet or frozen areas. Backfill adjacent to structures shall be placed as structural elements are completed and accepted. Backfill against concrete only when approved. Place and compact material to avoid loading upon or against structure.
3.5.4 Backfill and Fill Material Placement Over Pipes and at Walls
Backfilling shall not begin until construction below finish grade has been approved, underground utilities systems have been inspected, tested and approved, forms removed, and the excavation cleaned of trash and debris.
Backfill shall be brought to indicated finish grade and shall include backfill for outside grease interceptors and underground fuel tanks.
Where pipe is coated or wrapped for protection against corrosion, the backfill material up to an elevation 2 feet above sewer lines and 1 foot above other utility lines shall be free from stones larger than 1 inch in any dimension. Heavy equipment for spreading and compacting backfill shall not be operated closer to foundation or retaining walls than a distance equal to the height of backfill above the top of footing; the area remaining shall be compacted in layers not more than 4 inches in compacted thickness with power-driven hand tampers suitable for the material being compacted. Backfill shall be placed carefully around pipes or tanks to avoid damage to coatings, wrappings, or tanks. Backfill shall not be placed against foundation walls prior to 7 days after completion of the walls. As far as practicable, backfill shall be brought up evenly on each side of the wall and sloped to drain away from the wall.
3.5.5 Porous Fill Placement
Provide under floor and area-way slabs on a compacted subgrade. Place in 4 inch lifts with a minimum of two passes of a hand-operated plate-type vibratory compactor.
SECTION 31 23 00.00 20 Page 11
3.5.6 Trench Backfilling
Backfill as rapidly as construction, testing, and acceptance of work permits. Place and compact backfill under structures and paved areas in 8 inch lifts to top of trench and in 6 inch lifts to one foot over pipe outside structures and paved areas.
3.6 BORROW
Where satisfactory materials are not available in sufficient quantity from required excavations, approved borrow materials shall be obtained as specified herein.
3.7 BURIED WARNING AND IDENTIFICATION TAPE
Provide buried utility lines with utility identification tape. Bury tape 12 inches below finished grade; under pavements and slabs, bury tape 6 inches below top of subgrade.
3.8 BURIED DETECTION WIRE
Bury detection wire directly above non-metallic piping at a distance not to exceed 12 inches above the top of pipe. The wire shall extend continuously and unbroken, from manhole to manhole. The ends of the wire shall terminate inside the manholes at each end of the pipe, with a minimum of 3 feet of wire, coiled, remaining accessible in each manhole.
The wire shall remain insulated over it's entire length. The wire shall enter manholes between the top of the corbel and the frame, and extend up through the chimney seal between the frame and the chimney seal. For force mains, the wire shall terminate in the valve pit at the pump station end of the pipe.
3.9 COMPACTION
Determine in-place density of existing subgrade; if required density exists, no compaction of existing subgrade will be required. Density requirements specified herein are for cohesionless materials. When cohesive materials are encountered or used, density requirements may be reduced by 5 percent.
3.9.1 General Site
Compact underneath areas designated for vegetation and areas outside the 5 foot line of the paved area or structure to 85 percent of ASTM D698.
3.9.2 Structures, Spread Footings, and Concrete Slabs
Compact top 8 inches of subgrades to 95 percent of ASTM D698. Compact fill and backfill/structural fill material and select material to 95 percent of ASTM D698.
3.9.3 Adjacent Area
Compact areas within 5 feet of structures to 95 percent of ASTM D698.
3.9.4 Paved Areas
Compact top 6 inches of subgrades to 90 percent of ASTM D698. Compact
SECTION 31 23 00.00 20 Page 12 fill and backfill materials to 95 percent of ASTM D698.
3.10 RIP-RAP CONSTRUCTION
Construct rip-rap as indicated.
3.10.1 Stone Placement
Place rock for rip-rap to produce a well graded mass with the minimum practicable percentage of voids in conformance with lines and grades indicated. Distribute larger rock fragments, with dimensions extending the full depth of the rip-rap throughout the entire mass and eliminate "pockets" of small rock fragments. Rearrange individual pieces by mechanical equipment or by hand as necessary to obtain the distribution of fragment sizes specified above.
3.11 FINISH OPERATIONS
3.11.1 Grading
Finish grades as indicated within one-tenth of one foot. Grade areas to drain water away from structures. Maintain areas free of trash and debris. For existing grades that will remain but which were disturbed by Contractor's operations, grade as directed.
3.11.2 Topsoil and Sod
Provide topsoil as specified in Section 32 93 00 EXTERIOR PLANTS. Provide sodding as specified in Section 32 92 23 SODDING.
3.11.3 Protection of Surfaces
Protect newly backfilled, graded, and topsoiled areas from traffic, erosion, and settlements that may occur. Repair or reestablish damaged grades, elevations, or slopes.
3.12 DISPOSITION OF SURPLUS MATERIAL
Dispose of surplus soil and material per Section 01 57 19 TEMPORARY
ENVIRONMENTAL CONTROLS.
3.13 FIELD QUALITY CONTROL
3.13.1 Sampling
Take the number and size of samples required to perform the following tests.
3.13.2 Testing
Perform one of each of the following tests for each material used. Provide additional tests for each source change.
3.13.2.1 Fill and Backfill/Structural Fill Material Testing
Test fill material in accordance with ASTM C136/C136M for conformance to ASTM D2487 gradation limits; ASTM D1140 for material finer than the No. 200 sieve; ASTM D4318 for liquid limit and for plastic limit; ASTM D698 or ASTM D1557 for moisture density relations, as applicable.
SECTION 31 23 00.00 20 Page 13
3.13.2.2 Select Material Testing
Test select material in accordance with ASTM C136/C136M for conformance to ASTM D2487 gradation limits; ASTM D1140 for material finer than the No. 200 sieve; ASTM D698 or ASTM D1557 for moisture density relations, as applicable.
3.13.2.3 Porous Fill Testing
Test porous fill in accordance with ASTM C136/C136M for conformance to gradation specified in ASTM C33/C33M.
3.13.2.4 Density Tests
Test density in accordance with ASTM D1556/D1556M , or ASTM D6938. When ASTM D6938 density tests are used, verify density test results by performing an ASTM D1556/D1556M density test at a location already ASTM D6938 tested as specified herein. Perform an ASTM D1556/D1556M density test at the start of the job, and for every 10 ASTM D6938 density tests thereafter. Test subgrade and each lift at randomly selected locations every 2000 square feet of existing grade in fills for structures and concrete slabs, and every 2500 square feet for other fill areas and every 2000 square feet of subgrade in cut. Include density test results in daily report.
Bedding and backfill in trenches: One test per 100 linear feet in each lift.
SECTION 31 23 00.00 20 Page 14
SECTION 31 31 16.13
CHEMICAL TERMITE CONTROL
08/16
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. DEPARTMENT OF DEFENSE (DOD)
DODI 4150.07 (2019) DOD Pest Management Program
1.2 ADMINISTRATIVE REQUIREMENTS
Coordinate work related to final grades, landscape plantings, foundations, or any other alterations to finished construction which might alter the condition of treated soils with this specification.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Termiticide Application Plan; G
SD-03 Product Data
Termiticides
SD-05 Design Data
Mixing Formulation
SD-06 Test Reports
Soil Moisture
Calibration Test
SD-07 Certificates
Qualifications
Foundation Exterior
Utilities and Vents
List of Equipment
SECTION 31 31 16.13 Page 1
SD-08 Manufacturer's Instructions
Termiticides
SD-11 Closeout Submittals
Verification of Measurement
Warranty
Pest Management Report
1.4 QUALITY CONTROL
1.4.1 Regulatory Requirements
Comply with DODI 4150.07 for requirements on Contractor's licensing, certification, and record keeping. Maintain daily records using the Pest Management Maintenance Record, DD Form 1532-1, or a computer generated equivalent, and submit copies of records when requested by the Contracting Officer. These forms may be obtained from the main web site:
http://www.dtic.mil/whs/directives/forms/eforms/dd1532-1.pdf
1.4.2 Qualifications
For the application of pesticides, use the services of an applicator whose principal business is pest control. The applicator must be commercially certified in the state where the work is to be performed as required by DODI 4150.07. Termiticide applicators must also be certified in the U.S. Environmental Protection Agency (EPA) pesticide applicator category which includes structural pest control. Submit a copy of the pest control business license and pesticide applicator certificates.
1.4.3 Safety Requirements
Formulate, treat, and dispose of termiticides and their containers in accordance with label directions. Draw water for formulating only from sites designated by the Contracting Officer, and fit the filling hose with a backflow preventer meeting local plumbing codes or standards. Perform filling operations under the direct and continuous observation of a contractor's representative to prevent overflow. Secure pesticides and related materials under lock and key when unattended. Ensure that proper protective clothing and equipment are worn and used during all phases of termiticide application. Dispose of used pesticide containers off Government property.
1.5 DELIVERY, STORAGE, AND HANDLING
1.5.1 Delivery
Deliver termiticide material to the site in the original unopened containers bearing legible labels indicating the EPA registration number, manufacturer's registered uses and in new or otherwise good condition as supplied by the manufacturer or formulator.
1.5.2 Inspection
Inspect termiticides upon arrival at the job site for conformity to type and quality in accordance with paragraph TERMITICIDES. Each label must
SECTION 31 31 16.13 Page 2 bear evidence of registration under the Federal Insecticide, Fungicide, and Rodenticide Act (FIFRA), as amended or under appropriate regulations of the host county. Inspect other materials for conformance with specified requirements. Remove unacceptable materials from the job site.
1.5.3 Storage
Storage of pesticides on the installation will not be permitted unless it is written into the contract.
1.5.4 Handling
Handle and mix termiticides in accordance with the manufacturer's label and SDS, preventing contamination by dirt, water, and organic material.
Protect termiticides from weather elements as recommended by the manufacturer's label and SDS. Spill kits must be maintained on pest control vehicles and must be available at the mixing site. Conduct termiticide mixing in an area with adequate spill containment.
1.6 SITE CONDITIONS
The following site conditions determine the acceptable time of application.
1.6.1 Soil Moisture
Test soils to be treated immediately before application. Test soil moisture content to a minimum depth of 3 inches. The soil moisture must be as recommended by the termiticide manufacturer. Application of thetermiticide is not permitted when soil moisture content exceeds manufacturer's recommendations.
1.6.2 Runoff and Wind Drift
Application of termiticide will not be permitted during or immediately following heavy rains, when conditions may allow runoff, or create an environmental hazard or when average wind speed exceeds 10 miles per hour. Termiticide is not permitted to enter water systems, aquifers, or endanger humans or animals.
1.7 WARRANTY
Provide a 5 year written warranty against infestations or reinfestations by subterranean termites of the buildings or building additions constructed under this contract. Include in the warranty annual inspections of the buildings or building additions during the warranty period. If live subterranean termite infestation or subterranean termite damage is discovered during the warranty period, and the soil and building conditions have not been altered in the interim:
a. Retreat the site and perform other treatment as may be necessary for elimination of subterranean termite infestation;
b. Repair damage caused by termite infestation; and
c. Reinspect the building approximately 180 days after the re-treatment.
SECTION 31 31 16.13 Page 3
PART 2 PRODUCTS
2.1 SYSTEM DESCRIPTION
Chemical termite control uses liquid termiticide treatments applied to the soil to form a continuous chemical barrier in the soil around both sides of the foundation. The application can be surface applied or rodded and trenched. This barrier prevents foraging termites from reaching the foundation and piers. Only the soil adjacent to these foundation elements is treated. For slab construction (including foundations, patios and garages), the entire soil (or gravel) surface is treated before the vapor barrier is installed and the slab poured over it. Soil treatment is coordinated with all building activities from foundation construction through final grading of the soil around the building's exterior. In order for the treatment to be effective, the final phase of the application must be done after final grading and sometimes after landscaping is completed so that the treated soil is not disturbed.
2.2 MATERIALS
2.2.1 Termiticides
Provide termiticides currently registered by the EPA or approved for such use by the appropriate agency of the host county and as approved by the Contracting Officer. Select non-repellant termiticides for maximum effectiveness and duration after application. Select a termiticide that is suitable for the soil and climatic conditions at the project site and apply at the highest labeled rate. Submit manufacturer's label and Safety Data Sheet (SDS) for termiticides proposed for use.
PART 3 EXECUTION
3.1 PREPARATION
Eliminate food sources by removing debris from clearing and grubbing and post construction wood scraps such as ground stakes, form boards, and scrap lumber from the site, before termiticide application begins.
3.1.1 Verification
Before work starts, verify that final grades are as indicated and smooth grading has been completed. Finely grade soil and remove particles larger than 1 inch. Compact soil particles to eliminate soil movement.
3.1.2 Foundation Exterior
If the exterior perimeter treatment is applied when the horizontal barrier is applied it will be damaged or removed before construction is completed. The exterior foundation perimeter treatment will have to occur in phases when any pads, porches, aprons, sidewalks, final grading or landscape planting are simultaneously involved adjacent to the building foundation. This treatment area should be coordinated after all major construction but before any pads, porches, or other items requiring special consideration are poured adjacent to the foundation walls. Submit written verification that final grading, landscape planting and other items adjacent to the foundation will not disturb treatment of the soil on the exterior sides of foundation walls, grade beams, and similar structures.
SECTION 31 31 16.13 Page 4
3.1.3 Utilities and Vents
Turn off and block HVAC ducts and vents located in treatment area prior to application, to protect people and animals from termiticide. Submit written verification that the HVAC ducts and vents, water and sewer lines, and plumbing have been turned off or blocked prior to applying termiticide.
3.1.4 Application Plan
Prior to commencing application of termiticide, submit a Termiticide Application Plan addressing the following items:
a. proposed sequence of treatment work including dates and times of application
b. termiticide trade name
c. EPA registration number
d. chemical composition
e. concentration of original and diluted material
f. formulation
g. manufacturer's recommended application rates
h. regional requirements
i. application rate of active ingredients
j. method of application
k. area or volume to be treated
l. amount to be applied
m. copy of the pest control business license
n. copy of the pesticide applicator certificates
3.2 APPLICATION
For areas to be treated, establish complete and unbroken vertical and horizontal soil poison barriers between the soil and all portions of the intended structure which may allow termite access to wood and wood related products. Make applications to crawl spaces in accordance with label directions.