DBOC_Special_Conditions.pdf

PDF 34 KB Posted

Attached to
Daytona Beach Ocean Center Electrical Switchgear Replacement
Solicitation number
26-P-04LL
Issued by
Volusia County, Florida

About this file

This Special Conditions document outlines operational and site management requirements for contractors performing work at the Daytona Beach Ocean Center, a premier event venue in Volusia County, Florida. The project involves electrical switchgear replacement and must be coordinated around the Ocean Center's scheduled events calendar, which designates blackout dates when construction is prohibited. The contractor must achieve substantial completion within 30 days of Notice to Proceed and full completion within 35 days total. A mandatory pre-solicitation conference is scheduled for March 10, 2026, with written questions due by March 26, 2026, and electronic proposal submissions required through the County's eProcurement Portal by April 9, 2026 at 3:00 PM EST. The contractor must provide four weeks' advanced notice for any closures of building entrances or exits and one week's notice for project extensions beyond the approved schedule.

The contractor is responsible for securing portable restrooms, parking only in designated areas, and enclosing the work site and staging areas with six-foot chain link fencing with black liners and proper signage. All equipment, tools, and supplies must be secured at the designated staging areas at the end of each workday. The contractor may be required to supply a generator depending on the number of dark days and the Ocean Center's scheduled events, and work shifts may extend to 24 hours a day, seven days a week as needed to meet project timelines and minimize operational disruptions. Volusia County will not direct the means, methods, or work schedule of the contractor. Liquidated damages are assessed at $1,000 per day for failure to meet the 35-day completion deadline, and a payment and performance bond equal to 100 percent of the contract value is required prior to work commencement.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIAL CONDITIONS

Contractors will work around the Ocean Center scheduled events.

The events Calender will be provided for the project timeframe identifying blackout dates with no construction permitted. The Calander is subject to change.

The Ocean Center will set up the location of staging areas and will make the best efforts to be close to the project area. Staging area may be relocated for the ongoing events and client’s needs.

Contractors must park in designated areas only. Parking on sidewalks or outside dedicated workspace is prohibited.

Contractors will provide portable restrooms/ porta johns

Contractors are responsible for securing their work site and staging areas with 6-foot chain link fence with black liner and proper signage. All equipment, tools and supplies must be secured at the end of day is agreed staging areas.

The Ocean Center will need 4-week advanced notice for any closures of building entrances/ exits or work affecting direct building access. Extensions beyond approved time will need 1 week’s notice.

The Contractor may need to supply a generator depending on the number of dark days for the areas served by the switchgear replacement and the Ocean Centers scheduled events.

Volusia County will not direct means or methods of replacement or work schedule to the contractor. There may be a time when the scheduled work shift will be 24 hours a day 7 days a week to ensure project timeline is achieved and minimal dark days.