DBOC_Special_Conditions.pdf

PDF 34 KB Posted

Attached to
Daytona Beach Ocean Center Electrical Switchgear Replacement
Solicitation number
26-P-04LL
Issued by
Volusia County, Florida

About this file

This Special Conditions document outlines operational and logistical requirements for contractors performing electrical switchgear replacement work at the Daytona Beach Ocean Center, a venue managed by Volusia County, Florida. The project requires contractors to coordinate around the facility's scheduled events using a provided calendar that identifies blackout dates when construction is prohibited. Key operational requirements include mandatory attendance at a pre-solicitation conference on March 10, 2026, with written questions due by March 26, 2026, and proposal submissions required by April 9, 2026 at 3:00 PM EST through the County's eProcurement Portal. The project must be substantially completed within 30 days of Notice to Proceed with full completion required within 35 days total. Contractors must secure designated parking areas only, provide portable restrooms, establish six-foot chain link fencing with black liners around work sites and staging areas, and provide four weeks' advance notice for building entrance or exit closures and one week's notice for project extensions. The Ocean Center will designate staging area locations in proximity to the project area, though staging areas may be relocated to accommodate ongoing events.

The special conditions further stipulate that contractors must secure all equipment, tools, and supplies in designated staging areas at the end of each workday and may be required to supply a generator depending on the number of dark days necessitated by switchgear replacement work and the facility's event schedule. The work schedule may extend to 24 hours per day, seven days per week to ensure the project timeline is achieved with minimal facility downtime. Volusia County will not direct the contractor's means, methods, or work schedule. Liquidated damages are assessed at $1,000 per day for failure to meet the 35-day completion deadline. Contractors must maintain comprehensive insurance coverage including Workers' Compensation, Commercial General Liability ($1,000,000 per occurrence/$2,000,000 aggregate), Auto Liability ($1,000,000 combined single limit), and Excess Liability ($2,000,000), with the County named as additional insured. A payment and performance bond equal to 100 percent of the contract value is required prior to work commencement, with the total contract price listed as To Be Determined.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIAL CONDITIONS

Contractors will work around the Ocean Center scheduled events.

The events Calender will be provided for the project timeframe identifying blackout dates with no construction permitted. The Calander is subject to change.

The Ocean Center will set up the location of staging areas and will make the best efforts to be close to the project area. Staging area may be relocated for the ongoing events and client’s needs.

Contractors must park in designated areas only. Parking on sidewalks or outside dedicated workspace is prohibited.

Contractors will provide portable restrooms/ porta johns

Contractors are responsible for securing their work site and staging areas with 6-foot chain link fence with black liner and proper signage. All equipment, tools and supplies must be secured at the end of day is agreed staging areas.

The Ocean Center will need 4-week advanced notice for any closures of building entrances/ exits or work affecting direct building access. Extensions beyond approved time will need 1 week’s notice.

The Contractor may need to supply a generator depending on the number of dark days for the areas served by the switchgear replacement and the Ocean Centers scheduled events.

Volusia County will not direct means or methods of replacement or work schedule to the contractor. There may be a time when the scheduled work shift will be 24 hours a day 7 days a week to ensure project timeline is achieved and minimal dark days.

File details come from the government source that posted it. Updated .