About this file
This is a Special Conditions document prepared by Volusia County, Florida for the Daytona Beach Ocean Center Electrical Switchgear Replacement project (RFP 26-P-04LL, Contract No. C-2055). The project requires complete removal and replacement of the facility's main electrical switchboard and associated bus duct systems, with installation of a new 480Y/277V, 3-phase, 4-wire service-entrance-rated switchboard (Square D QED-2 model, 2000A capacity) and comprehensive electrical system upgrades. The contractor must substantially complete the work within 30 days of Notice to Proceed and achieve full completion within 35 days total. A mandatory pre-solicitation conference is scheduled for March 10, 2026, with written questions due by March 26, 2026, and electronic proposal submissions required by April 9, 2026 at 3:00 PM EST through the County's eProcurement Portal. Required qualifications include an active Florida-licensed building or general contractor license, an active Florida Certified Electrical Contractor as subcontractor, a superintendent with active Florida Journeyman's Electrical License and minimum four years' experience, and at least five years of established business history with three references demonstrating similar switchgear replacement projects completed within the past three years.
The special conditions establish strict operational requirements reflecting the facility's active event schedule, including adherence to a provided events calendar with blackout dates when no construction is permitted, provision of four weeks' advance notice for building entrance or exit closures and one week's notice for project extensions, and 24-hour, seven-days-per-week work shifts if necessary to meet the project timeline while minimizing dark days. Contractors must secure the work site with six-foot chain link fencing with black liners, provide portable restrooms, park only in designated areas, provide a generator depending on dark days and scheduled events, and store all equipment and supplies in designated staging areas at end of day. The Ocean Center will designate staging area locations and reserves the right to relocate them as needed. Volusia County will not direct means or methods of replacement or work schedule; however, the contractor must provide sufficient notice for any operational impacts. A payment and performance bond equal to 100 percent of contract value is required prior to work commencement, and liquidated damages are assessed at $1,000 per day for failure to meet the 35-day completion deadline. Comprehensive insurance requirements include Workers' Compensation, Commercial General Liability ($1,000,000 per occurrence/$2,000,000 aggregate), Auto Liability ($1,000,000 combined single limit), Excess Liability ($2,000,000), and Installation Floater coverage, with the County named as additional insured and all policies issued by Florida-licensed insurers with A.M. Best ratings of A- or better.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIAL CONDITIONS
Contractors will work around the Ocean Center scheduled events.
The events Calender will be provided for the project timeframe identifying blackout dates with no construction permitted. The Calander is subject to change.
The Ocean Center will set up the location of staging areas and will make the best efforts to be close to the project area. Staging area may be relocated for the ongoing events and client’s needs.
Contractors must park in designated areas only. Parking on sidewalks or outside dedicated workspace is prohibited.
Contractors will provide portable restrooms/ porta johns
Contractors are responsible for securing their work site and staging areas with 6-foot chain link fence with black liner and proper signage. All equipment, tools and supplies must be secured at the end of day is agreed staging areas.
The Ocean Center will need 4-week advanced notice for any closures of building entrances/ exits or work affecting direct building access. Extensions beyond approved time will need 1 week’s notice.
The Contractor may need to supply a generator depending on the number of dark days for the areas served by the switchgear replacement and the Ocean Centers scheduled events.
Volusia County will not direct means or methods of replacement or work schedule to the contractor. There may be a time when the scheduled work shift will be 24 hours a day 7 days a week to ensure project timeline is achieved and minimal dark days.