CN-370000-CN304-T22.pdf

PDF 334 KB Posted

Attached to
Master Agreement FL|CN304|000d9a7c09806a64121cbe0fc013a618
Contract number
CN304
Issued by
Florida

About this file

This document is a Task Assignment Notification Form issued by the Florida Department of Environmental Protection (FDEP) for Contract CN304, Task Assignment TA22. The project involves the Marjorie Harris Carr Cross Florida Greenway and is located at the Santos Equestrian Trail Head. The consultant performing the work is Greenman-Pedersen, Inc. (GPI), with Colby Brown, P.E. serving as the Consultant Representative and Ralph Perkins as the FDEP Contract Manager. The task was executed on September 25, 2023, and approved by FDEP Contract Authority Michael W. Foster Jr., P.E. on September 27, 2023.

The task assignment covers the preparation of plans and permitting to relocate a restroom facility to a new location due to newly identified Gopher Tortoise activity in the original site area. Task 1 encompasses construction plan updates including 90% engineering plans ($10,171.65), permitting and coordination with Marion County, SJRWMD, and FDEP including OSTDS permit resubmission ($2,480.52), and 100% engineering plans ($2,181.62). Task 2 provides construction administration services including bidding support and shop drawing reviews ($6,855.60), pre-construction meeting representation ($737.92), substantial completion meeting and punch list development ($1,291.36), final completion meeting attendance ($1,106.88), and as-built certifications for permit compliance ($2,062.06). The total task amount is $26,887.61, with funding allocated from two FLAIR codes: $10,262.67 from the 2020 allocation and $16,624.94 from the 2021 allocation. Task 1 has a 60-calendar-day completion schedule from Notice to Proceed, while Task 2 is scheduled for the construction phase with no fixed duration. The proposal specifically excludes FWC Gopher Tortoise permitting, archaeological services, DHR coordination, building permit fees, and electrical work.

View the file

Other files

File Type Posted
CN-370000-CN304-CMC3.pdf PDF
CN-370000-CN304-T20CO1.pdf PDF
CN-370000-CN304-T22CO1.pdf PDF
CN-370000-CN304-T20CO2.pdf PDF
CN-370000-CN304-T3CO3.pdf PDF
CN-370000-CN304-T18.pdf PDF
CN-370000-CN304-T6.pdf PDF
CN-370000-CN304-T1.pdf PDF
CN-370000-CN304-T13CO1.pdf PDF
CN-370000-CN304-T15.pdf.crdownload CRDOWNLOAD file
CN-370000-CN304-T4.pdf PDF
CN-370000-CN304-T9.pdf PDF
CN-370000-CN304-T8.pdf PDF
CN-370000-CN304-T15CO2.pdf PDF
CN-370000-CN304-TA7.pdf PDF
CN-370000-CN304-T10CO1.pdf PDF
CN-370000-CN304-CMC1.pdf PDF
CN-370000-CN304-T3CO2.pdf PDF
CN-370000-CN304-T15CO3.pdf PDF
CN-370000-CN304-T3CO5.pdf PDF
CN-370000-CN304-CMC5.pdf PDF
CN-370000-CN304-T15CO1.pdf PDF
CN-370000-CN304-T23.pdf PDF
CN-370000-CN304-T3.pdf PDF
CN-370000-CN304-T2CO1.pdf PDF
CN-370000-CN304-T5CO1.pdf PDF
CN-370000-CN304-CMC4.pdf PDF
CN-370000-CN304-T5.pdf PDF
CN-370000-CN304-T4CO2.pdf PDF
CN-370000-CN304-TA4CO1.pdf PDF
CN-370000-CN304-T16CO1.pdf PDF
CN-370000-CN304-T10.pdf PDF
CN-370000-CN304-T21.pdf PDF
CN-370000-CN304-T12.pdf PDF
CN-370000-CN304-T20.pdf PDF
CN-370000-CN304-T3CO4.pdf PDF
CN-370000-CN217-TA30.pdf PDF
CN-370000-CN304-T12CO1.pdf PDF
CN-370000-CN304-T11CO2.pdf PDF
CN-370000-CN304-CMC2.pdf PDF
CN-370000-CN304-T19.pdf PDF
CN-370000-CN304-TA13.pdf PDF
CN-370000-CN304-T3CO1.pdf PDF
CN-370000-CN304-T8CO1.pdf PDF
CN-370000-CN304-T14.pdf PDF
CN-370000-CN304-T4CO1.pdf PDF
CN-370000-CN304.pdf PDF
CN-370000-CN304-T16.pdf PDF
CN-370000-CN304-T15.pdf PDF
CN-370000-CN304-A1.pdf PDF
Show 40 more

Latest 50 of 52 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT NOTIFICATION FORM

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description of Task:

Project Manager:

Schedule Start Date: Fixed Price Cost:

Completion Date: Cost Reimbursement not to exceed:

Total Task Amount:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 digit FLAIR Code: Total:

CN304 TA22 FDEP 61218C

Santos Equestrian Restroom

Greenman-Pedersen, Inc.

Colby Brown, P.E. (850) 450-2921 colbybrown@gpinet.com

Ralph Perkins or successor (850) 245-2460 Ralph.Perkins@FloridaDEP.gov

To prepare plans, permitting and construction administration to relocate the restroom facility to a new location as a result of new Gopher Tortoise activity in the area per the proposal dated 9/12/2023.

Richard Marcil or successor

Upon Execution $ 26,887.61 Contract End Date

$ 26,887.61

Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.09.21 16:17:46 -04'00'

Vu Nguyen Vu Nguyen Digitally signed by Vu Nguyen Date: 2023.09.21 16:31:59 -04'00'

Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.09.22 11:21:59 -04'00'

Dustin Evans, PE Dustin T Evans

2023.09.25 08:29:05-04'00'

Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.

Digitally signed by Michael W.

Foster Jr., P.E.

Date: 2023.09.27 15:18:37 -04'00'

61218C 37503000275 088130/20 408001 U3200 131500 PF $ 10,262.67

61218C 37503000275 088130/21 675002 U3200 131500 XR $ 16,624.94

$ 26,887.61

Marjorie Harris Carr Cross Florida Greenway

Greenman-Pedersen, Inc. 4300 Bayou Blvd Ste 12 Pensacola, FL 32503 p 850-450-2921

An Equal Opportunity Employer

September 12, 2023

Mr. Rene Marcil Design Project Manager Division of Recreation and Parks

RE: Cross Florida Greenway – Santos Equestrian Trail Restroom – Task Assignment

Dear Mr. Marcil;

Per DEP’s request, and as the original TA12 has expired. The intent of this new Task Assignment is to prepare plans to relocate the restroom facility to a new location as a result of new Gopher Tortoise activity in the area the restroom was originally designed and to bring the unused Construction Administration funds on the project into a new Task Assignment.

We genuinely appreciate the opportunity to team with you on this project, and look forward to its successful completion.

Sincerely, Greenman-Pedersen, Inc.

Colby Brown, PE Senior Project Manager

Cross Florida Greenway – Santos Equestrian Trail Head Restroom Contract Number: CN304, Task Assignment

Introduction: As the previous contract has expired, this intent of this new Task Assignment is to prepare plans to relocate the restroom facility to a new location as a result of new Gopher Tortoise activity in the area that the restroom was originally designed and to bring the unused funds on the project into a new Task Assignment.

Task 1: Construction Plans Update

Subtask 1A: 90% Engineering Plans

Description:

Preparation of 90% construction plans for the relocation of the restroom facility and associated features. Site layout shall be coordinated with new gopher tortoise site survey 8-18-23 (sent to GPI on 9-5-23) to maintain a 25’ clear zone around any burrows identified. GPI will:

Coordinate and update the plans related to Electrical Requirements for a Solar system;

Research Florida Building Code Requirements Coordinate with local and regional building officials Update Plans to adhere to 2023 Florida Building Code (taking effect 12-31-2023) Add building foundation notes to the plan sheets.

Plan revisions required will be incorporated and provided in Subtask 1C and are not part of this Subtask.

Deliverables (Electronic Submittal):

· 90% Plan Set in 11 x 17 PDF Format

Fixed Price Cost:

Subtask 1A:

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost Greenman-Pedersen, Inc. Principal-In-Charge $ 197.34 0 $ - Greenman-Pedersen, Inc. Senior Project Manager $ 177.18 20 $ 3,543.60 Greenman-Pedersen, Inc. Senior Engineer/EOR $ 147.29 45 $ 6,628.05 Greenman-Pedersen, Inc. Project Engineer III $ 92.24 0 $ - Greenman-Pedersen, Inc. Civil Designer $ 76.28 0 $ - Greenman-Pedersen, Inc. Clerical $ 83.23 0 $ - Subtotal for Subtask 1A: $ 10,171.65

Subtask 1B: Permitting

Description:

Includes permitting and coordination with Marion County, SJRWMD, and FDEP. We will verify that no updates are required related to the existing general permit from SJRWMD and public water supply permit from FDEP.

The OSTDS permit from the Marion County Health Department has expired and will need to be resubmitted.

Coordination and preparation of permit application included. Proposal includes the application cost of the Marion County Department Health OSTDS Application ($350).

Deliverables (Electronic Submittal):

· Marion County OSTDS Permit Application and Coordination in PDF Format

Fixed Price Cost:

Subtask 1B:

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost Greenman-Pedersen, Inc. Principal-In-Charge $ 197.34 0 $ - Greenman-Pedersen, Inc. Senior Project Manager $ 177.18 14 $ 2,480.52 Greenman-Pedersen, Inc. Senior Engineer/EOR $ 147.29 0 $ - Greenman-Pedersen, Inc. Project Engineer III $ 92.24 0 $ - Greenman-Pedersen, Inc. Civil Designer $ 76.28 0 $ - Greenman-Pedersen, Inc. Clerical $ 83.23 0 $ - Subtotal for Subtask 1B: $ 2,480.52

Subtask 1C: 100% Engineering Plans

Description:

The 100% Engineering Plans will incorporate all changes/revisions required as a result of coordination with the Owner and/or Permitting Agency(s).

Deliverables (Electronic and Paper Submittal):

· 100% Plan Set in 11 x 17 PDF Format

· Signed and Sealed Hard Copy Plans – 2 - 11 x 17 sets

· AutoCad Compliant DWG Format via compact disk, email attachment or FTP

Fixed Price Cost:

Subtask 1C:

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost Greenman-Pedersen, Inc. Principal-In-Charge $ 197.34 0 $ - Greenman-Pedersen, Inc. Senior Project Manager $ 177.18 4 $ 708.72 Greenman-Pedersen, Inc. Senior Engineer/EOR $ 147.29 10 $ 1,472.90 Greenman-Pedersen, Inc. Project Engineer III $ 92.24 0 $ - Greenman-Pedersen, Inc. Civil Designer $ 76.28 0 $ - Greenman-Pedersen, Inc. Clerical $ 83.23 0 $ - Subtotal for Subtask 1C: $ 2,181.62

Task 2: Construction Administration Services

Description:

Subtask 2A: Includes any responses to questions received during bidding and any assistance prior to begin construction, any shop drawing or material reviews, and any general project questions / coordination. (Anticipate 4 RFI @ 4hrs and 2 shop drawing/material reviews @ 4hrs ea.). GPI representation at the pre-bid meeting.

Subtask 2B.1: GPI representation at the pre-construction meeting Subtask 2B.2: GPI representation at the substantial completion meeting. Includes development of a punch list.

Subtask 2B.3: GPI representation at the final completion meeting.

Subtask 2C: Includes the preparation of any required as-built certifications required to satisfy permit conditions in permits provided in TA 12 Subtask 4 and Subtask 1B.

Deliverables (Electronic and Paper Submittal):

Subtask 2A: Bid Support, o .PDF file of RFI Response Subtask 2B1: Attendance at pre-construction meeting with meeting minutes o .PDF file of meeting minutes Subtask 2B2: attendance at substantial completion meeting with punch list o .PDF file of punch list Subtask 2B3: Attendance at final completion meeting with meeting minutes o .PDF file of Punch List Subtask 2C: As-Built Certifications (water/sewer/OSTDS) o .PDF file of all required certifications

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 2A - Bidding and Shop Drawing RFI's Firm Name Position Classification Hourly

Rate Hours Total Fixed Price Cost

Greenman-Pedersen, Inc. Project Manager $147.29 24 $3,534.96 Greenman-Pedersen, Inc. Project Engineer III $92.24 36 $3,320.64 Total Fixed Price for Subtask 2A $6,855.60 Subtask 2B.1 - Pre-Construction Meeting Firm Name Position Classification Hourly

Rate Hours Total Fixed Price Cost

Greenman-Pedersen, Inc. Project Engineer III $92.24 8 $737.92 Total Fixed Price for Subtask 2B.1 $737.92 Subtask 2B.2 - Substantial Completion Meeting Firm Name Position Classification Hourly

Rate Hours Total Fixed Price Cost

Greenman-Pedersen, Inc. Project Engineer III $92.24 14 $1,291.36 Total Fixed Price for Subtask 2B.2 $1,291.36 Subtask 2B.3 - Final Completion Meeting Firm Name Position Classification Hourly

Rate Hours Total Fixed Price Cost

Greenman-Pedersen, Inc. Project Engineer III $92.24 12 $1,106.88 Total Fixed Price for Subtask 2B.3 $1,106.88 Subtask 2C - As-Built Certifications for Permits Firm Name Position Classification Hourly

Rate Hours Total Fixed Price Cost

Greenman-Pedersen, Inc. Project Manager $147.29 14 $2,062.06 Total Fixed Price for Subtask 2C $2,062.06 Total for Task 2: $12,053.82

Project Schedule dates are consecutive calendar days. Actual dates of submittals will be determined at Notice to Proceed.

Project Schedule:

Activity Duration (Calendar Days) Task 1: Construction Plans Update 60 Task 2: Construction Administration N/A

Summary of Fees:

Task Task Fixed Price Cost

Subtask 1A 90% Engineering Plans $10,171.65 Subtask 1B Permitting $2,480.52 Subtask 1C 100% Engineering Plans $2,181.62

Total Task 1 $14,833.79

Subtask 2A - Bidding and Shop Drawing RFI's $6,855.60 Subtask 2B.1 - Pre-Construction Meeting $737.92 Subtask 2B.2 - Substantial Completion Meeting $1,291.36

Subtask 2B.3 - Final Completion Meeting $1,106.88 Subtask 2C - As-Built Certifications for Permits $2,062.06

Total Task 2 $12,053.82 Grand Total $26,887.61

Assumptions/Exclusions

1. Any service not specifically described above is not included in this proposal.

2. There will be no; FWC Gopher Tortoise Permitting preparation, submittal or management of Burrow

Permit(s), FWC coordination, gopher tortoise excavation and relocation, or submittal of After-Action Report to FWC.

3. Assumes no architect is required

4. Assumes no electrical extension or easements of any form is required.

5. No ecological assessment or other environmental service is required.

6. Building permit fees are not included in proposal.

7. Archaeologist and DHR coordination has been excluded from this proposal.

END OF DOCUMENT