This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for Contract No. CN304. The document is a change order proposal submitted by Greenman-Pedersen, Inc. (GPI), an engineering and design consultant, with input from AREHNA, a geotechnical engineering firm. The contract pertains to design and permitting services for the reconstruction of an observation deck at Weeki Wachee Springs State Park located in Hernando County, Florida. The change order was executed on June 21-29, 2023, with all required signatures from FDEP budget, project management, and contract authority representatives, as well as the consultant.

Change Order #1 modifies the original task assignment to address structural concerns identified in a geotechnical investigation related to potential sinkhole activity near the proposed deck structure. The net increase in task amount is $9,444.47, bringing the total task cost to $35,165.35. Key modifications include: Task 1 (Permitting) increased from $3,086.44 to $4,117.47; Task 2 (100% Engineering Plans) increased from $3,824.36 to $9,326.10 to incorporate structural redesign; Task 4 (Glass Railing Design) eliminated with a reduction of $2,448.04; and new Task 4A (Geotechnical Report Addendum) added at $3,495.81. Task 6 (Electrical Design Plan) was adjusted to $6,650.12, including a reimbursable mileage adjustment. The new task end date is December 31, 2024, extending the original completion date by 365 days. Funding is provided through Grant CSFRF under FDEP's organizational code with a 29-digit FLAIR code allocation.

View the file

Other files

File Type Posted
CN-370000-CN304-CMC3.pdf PDF
CN-370000-CN304-T20CO1.pdf PDF
CN-370000-CN304-T22CO1.pdf PDF
CN-370000-CN304-T20CO2.pdf PDF
CN-370000-CN304-T3CO3.pdf PDF
CN-370000-CN304-T18.pdf PDF
CN-370000-CN304-T6.pdf PDF
CN-370000-CN304-T1.pdf PDF
CN-370000-CN304-T13CO1.pdf PDF
CN-370000-CN304-T15.pdf.crdownload CRDOWNLOAD file
CN-370000-CN304-T4.pdf PDF
CN-370000-CN304-T9.pdf PDF
CN-370000-CN304-T8.pdf PDF
CN-370000-CN304-T15CO2.pdf PDF
CN-370000-CN304-TA7.pdf PDF
CN-370000-CN304-T10CO1.pdf PDF
CN-370000-CN304-CMC1.pdf PDF
CN-370000-CN304-T3CO2.pdf PDF
CN-370000-CN304-T15CO3.pdf PDF
CN-370000-CN304-T3CO5.pdf PDF
CN-370000-CN304-CMC5.pdf PDF
CN-370000-CN304-T15CO1.pdf PDF
CN-370000-CN304-T23.pdf PDF
CN-370000-CN304-T3.pdf PDF
CN-370000-CN304-T2CO1.pdf PDF
CN-370000-CN304-T5CO1.pdf PDF
CN-370000-CN304-CMC4.pdf PDF
CN-370000-CN304-T22.pdf PDF
CN-370000-CN304-T5.pdf PDF
CN-370000-CN304-T4CO2.pdf PDF
CN-370000-CN304-TA4CO1.pdf PDF
CN-370000-CN304-T10.pdf PDF
CN-370000-CN304-T21.pdf PDF
CN-370000-CN304-T12.pdf PDF
CN-370000-CN304-T20.pdf PDF
CN-370000-CN304-T3CO4.pdf PDF
CN-370000-CN217-TA30.pdf PDF
CN-370000-CN304-T12CO1.pdf PDF
CN-370000-CN304-T11CO2.pdf PDF
CN-370000-CN304-CMC2.pdf PDF
CN-370000-CN304-T19.pdf PDF
CN-370000-CN304-TA13.pdf PDF
CN-370000-CN304-T3CO1.pdf PDF
CN-370000-CN304-T8CO1.pdf PDF
CN-370000-CN304-T14.pdf PDF
CN-370000-CN304-T4CO1.pdf PDF
CN-370000-CN304.pdf PDF
CN-370000-CN304-T16.pdf PDF
CN-370000-CN304-T15.pdf PDF
CN-370000-CN304-A1.pdf PDF
Show 40 more

Latest 50 of 52 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

(Revised 9-26-2018) Page 1 of 1

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description and Justification of Change:

Change in Task Amount:

Item Reimbursement Fixed Fee Total

Original Task Amount:

Task amount including all previous Change Orders:

Net increase/decrease in task amount for this Change Order:

Total Amounts with all Change Orders:

Change in Task Time:

Original Task Execution Date:

Original Task End Date:

Present Task End Date:

Net Change in Days:

New Task End Date:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 Digit FLAIR Code: Total:

CN304 16 1 6A003

Weeki Wachee State Park Theater Waiting Area Alterations

Greenman Pedersen, Inc.

Colby Brown 850-297-2929 colbybrown@gpinet.com

Ralph Perkins 850-245-2460 Ralph.Perkins@FloridaDEP.gov

Additional design and permitting services geotechnical,100% plan modifications, electrical to mermaid theater waiting area at Weeki Wachee Springs State Park per attached proposal dated 6.20.23.

$ 223.39 $ 25,497.49 $ 25,720.88 $ 223.39 $ 25,497.49 $ 25,720.88 -$ 223.39 $ 9,667.86 $ 9,444.47

$ 0.00 $ 35,165.35 $ 35,165.35

12/15/2022

12/31/2023

12/31/2023

12/31/2024

Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.06.21 09:22:54 -04'00'

Garland Sandel Garland Sandel Digitally signed by Garland Sandel Date: 2023.06.21 12:28:27 -04'00'

Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.06.21 14:04:16 -04'00'

Dustin Evans Dustin T Evans

2023.06.22 11:00:38-04'00'

Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.

Digitally signed by Michael W.

Foster Jr., P.E.

Date: 2023.06.29 09:18:24 -04'00'

6A003 CSFRF 37504000281 085154/22 000286 U3200 131500 AD $ 9,444.47

$ 9,444.47

Greenman-Pedersen, Inc. 1590 Village Square Boulevard Tallahassee, FL 32309 p 850.668.5211

An Equal Opportunity Employer

June 20, 2023

Mr. Garland Sandel Design Project Manager Bureau of Design and Construction Department of Environmental Protection O: 850-245-2798 C: 850-756-0063 Garland.Sandel@FloridaDEP.gov

RE: Weeki Wachee Observation Deck TA16 – Change Order #1

Dear Mr. Sandel;

Based on recent discussions related to the Geotech report and its findings regarding sinkhole activity, we submit this change order to address sinkhole activity concerns as well as contract management for the completion and construction of design and construction of the project.

To summarize:

Task #1 – Additional Permit verification - $3086.44 to $4117.47 Task #2 – 100% plans: Structural redesign for Sinkhole Activity - $3824.36 to $9326.10 Task #4 – Glass Railing: Will be removed from this project - $2448.04 to $0.00 Task #4A – (Added) Geotechnical Report Addendum - $0.00 to $3495.81 Task #6 – Electrical Design Plan for design and coordination - $4562.80 + $223.39 to $6650.12

We genuinely appreciate the opportunity and look forward to the project’s successful completion.

Sincerely, Greenman-Pedersen, Inc.

Colby Brown, PE Senior Project Manager colbybrown@gpinet.com mailto:Garland.Sandel@floridadep.gov mailto:colbybrown@gpinet.com

EXHIBIT “A”

Proposal for Redevelopment of a Covered Observation Deck

Task Assignment #16 – Change Order #1 Contract Number CN304

Introduction: This proposal is for finalizing the design and permitting services as well as the construction services associated with the reconstruction of an observation deck located at Weekie Wachee Springs State Park in Hernando County, FL. The state park is located at 6131 Commercial Way in Weekie Wachee, FL 34606 (Parcel ID R-Z SWM 17- 0000-0030-0000). A detailed breakdown and description of individual task efforts is listed below.

GPI provide design and permitting services for replacing the observation deck overhanging Weekie Wachee Spring, at Weekie Wachee Springs State Park. The platform currently serves as a queuing area for patrons waiting to enter the mermaid theatre for the upcoming show. The platform is currently cantilevered over the spring and has fallen into a state of disrepair over the years.

The park wishes to reconstruct the deck, ideally without the cantilever overhanging the spring that currently exists as a cost saving effort. The park also wishes to cover the deck with an overhead hip-roof style pavilion or other pre-engineered covering. It is understood that the proposed infrastructure will be limited to the size of the existing deck’s footprint, and therefore no additional stormwater permitting, civil site permitting, or design shall be required.

Change Order #1: As discussed in our meeting 05-31-23, GPI shall coordinate additional geotechnical investigation for guidance related to the structural foundation design to address the potential sink hole activity. This will require a redesign/update of the plans including project management for the various disciplines.

Task 1: Permitting

Description: This task assumes that the contractor will apply for the building permit. It is anticipated that the County will have comments during this permitting process, and this task includes 2 reasonable responses to RAI’s. This task assumes no additional disturbance to the flood zones or wetlands located onsite, and therefore no coordination with FEMA or the ACOE. This task also assumes that the proposed structure will occupy the same (or lesser) footprint, and will therefore not require Civil Site Plan permitting, environmental permitting, or permitting with the water management district. A diagrammatic site plan is expected to be required for building permitting.

It is anticipated that the Hernando County Building Permit fee shall be paid by the contractor when the permit is picked up.

As requested, this task will include additional permit requirement verification.

Deliverables:

Preparation and electronic submittal of Hernando County Building Permit Application forms and supporting documentation in PDF format.

Provide written responses and plan revisions necessary to accommodate Hernando County permitting

Comments

Performance Measure:

Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Cost Price:

Task 1:

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost GPI Principal-In-Charge $ 197.34 0 $ - GPI Senior Project Manager $ 177.18 0 $ - GPI Senior Engineer/EOR $ 147.29 7 $ 1,031.03 GPI Project Engineer III $ 92.24 0 $ - GPI Civil Designer $ 76.28 0 $ - GPI Clerical $ 83.23 0 $ -

Additional Subtotal for Task 1: $ 1,031.03

Task 2: 100% Engineering Plans

Description: The 100% Engineering Plans will incorporate any changes / revisions as required as a result of coordination with the Owner and/or Permitting Agencies. With 90% Plans, a re-design will be necessary for the modification to the structure as related to the new Geotechnical recommendations relating to the potential Sink Hole activity.

Deliverables:

100% Plan Set (electronic, pdf format) 2 Signed and Sealed Hard Copy Plans (hard copy) AutoCAD Compliant DWG Format via Email attachment or FTP

Performance Measure:

Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Cost Price:

Task 2:

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost GPI Principal-In-Charge $ 197.34 0 $ - GPI Senior Project Manager $ 177.18 8 $ 1,417.44 GPI Senior Engineer/EOR $ 147.29 14 $ 2,062.06 GPI Project Engineer III $ 92.24 12 $ 1,106.88 GPI Civil Designer $ 76.28 12 $ 915.36 GPI Clerical $ 83.23 0 $ -

Additional Subtotal for Task 2: $ 5,501.74

Task 3: Construction Admin / Project Closeout – No Cost Change

Task 4: Glass Railing Design & Details

Description: This task is being eliminated.

Fixed Cost Price:

Task 4:

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

GPI Principal-In-Charge $ 197.34 0 $ - GPI Senior Project Manager $ 177.18 -2 $ (354.36) GPI Senior Engineer/EOR $ 147.29 -8 $ (1,178.32) GPI Project Engineer III $ 92.24 0 $ - GPI Civil Designer $ 76.28 -12 $ (915.36) GPI Clerical $ 83.23 0 $ -

Additional Subtotal for Task 4: $ (2,448.04)

Task 4A: Geotechnical Addendum Letter (ADDED) Description: AREHNA previously completed a geotechnical investigation for the proposed deck improvements at the site (report dated October 8, 2021, AREHNA Project No. B-21-107). During that investigation, one boring adjacent to the proposed structure identified potential sinkhole activity. This task includes geotechnical engineering support to address concerns regarding the soil conditions near the structure. No additional soil borings or lab testing are proposed. This report includes providing recommendations for mitigating sinkhole risk to the proposed structure and providing a report addendum letter with proposed recommendations for design and construction beyond those already provided in our previous report.

Deliverables:

Certified Geotechnical Report Letter (Electronic, PDF Format)

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Cost Price:

Task 5: Stanchion Plan & Details – No Cost Change

Task 6: Electrical Layout Plan & Details Description: GPI shall provide an electrical plan and details to accompany the building permit submittal package.

This shall include product “cut sheets” that details selected products. GPI shall prepare this package based on selections provided by the Client (Fans, Lights, Speakers, Outlets). The plan shall show the locations of all products on the plan, along with their associated details, wiring notes, and modifications to the existing electrical riser diagram. This task requires client provided photos of the existing electrical Panel/Riser.

Deliverables:

Electric Plan included in plan sheets (Electronic, PDF Format) Building Permit “cut sheet” package (Electronic, PDF Format)

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Cost Price:

Task 6:

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost GPI Principal-In-Charge $ 197.34 1 $ 197.34 GPI Senior Project Manager $ 177.18 4 $ 708.72 GPI Senior Engineer/EOR $ 147.29 -2 $ (294.58) GPI Project Engineer III $ 92.24 16 $ 1,475.84 GPI Civil Designer $ 76.28 0 $ - GPI Clerical $ 83.23 0 $ - GPI Reimbursable Mileage - 502@$0.445 $ (223.39)

Additional Subtotal for Task 6: $ 1,863.93

Task 4A:

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost AREHNA Staff Engineer $ 86.41 12 $ 1,036.92 AREHNA Project Engineer $ 89.43 3 $ 268.29 AREHNA Senior Project Engineer $ 140.94 8 $ 1,127.52 AREHNA Principal Engineer $ 180.30 0 $ - AREHNA Senior Engineering Technician $ 51.99 0 $ - AREHNA CAD Operator $ 66.78 0 $ - AREHNA Secretary $ 55.55 0 $ - GPI Senior Project Manager $ 177.18 6 $ 1,063.08

Subtotal for Task 4A: $ 3,495.81

Task 7: Fence Installation Limits – No Cost Change

Summary of Fees:

Task Task Name: Change Order #1 Fixed Price Cost Orig Task Fixed Price Cost

Task 1: Permitting $ 1,031.03 $ 3,086.44 Task 2: 100% Engineering Plans $ 5,501.74 $ 3,824.36 Task 3: Construction Admin / Project Closeout $ - $ 6,614.46 Task 4: Glass Railing Design and Details $ (2,448.04) $ 2,448.04 Task 4A: Geotechnical Addendum Letter $ 3,495.81 Task 5: Stanchion Plan $ - $4,484.36 Task 6: Electrical Design Plan $ 1,863.93 $ 4,786.19 Task 7: Fence Installation and Detail Plan $ - $477.03

Total Fixed Cost Price $ 9,444.47 $25,720.88

Project Schedule:

Project Schedule dates are consecutive calendar days. Dates are based on time from Task Assignment Execution. As scheduling these meetings may require some lead time, this calendar should be considered an estimate, and will be dependent upon the schedules of the various agencies.

Task Activity Duration (Calendar Days) Dates Task 1: Permitting 30 (Estimate) From Tasks 4-7 Task 2: 100% Engineering Plans 30 (Estimate) From Task 1 Task 3: Construction Admin / Project Closeout 120 (Estimate) Post Construction Task 4: Geotechnical Addendum Letter 15 From Execution Task 5: Stanchion Plan 15 From Execution Task 6: Electrical Design Plan 30 From Execution Task 7: Fence Installation and Detail Plan 15 From Execution

Assumptions/Exclusions

1. Any service not specifically described above is not included in this proposal.

2. Assumes structure footprint is equal to, or smaller than existing.

3. Assumes no architect is required

4. No design of any fire sprinkler system is included in this proposal.

5. Assumes no registered landscape architect is required

6. Assumes no irrigation plan.

7. Assumes water services are immediately available to the site (via Well) and no utility extension of any form is required.

8. Assumes no civil site plans are required.

9. Project excludes design or redesign of the pergola.

10. No ecological assessment or other environmental service is required.

11. Building permit fees are not included in proposal.

12. Design of retaining wall, or alteration of the existing wall has been excluded from this proposal.

13. Archaeologist and DHR coordination has been excluded from this proposal.

14. No building design included.

CN304 TA14 CO1 Weeki Wachee Theater Waiting Area Modifications.pdf
BLANK TA CO FORM.pdf
FDEP - Weeki Wachee Observation Deck - CO#1 10-19-22.pdf
FINAL CN304 TA16 CO1 Weeki Wachee - Faculty Improvements.pdf
June 20, 2023