Correct Plumbing Piping and Replace
Fixtures
VA Medical Center, Memphis, TN
March 31, 2020
Bid Documents
Specifications
Project Number: 614-18-106
Correct Plumbing Piping & Replace Fixtures 02-01-19
VAMC Memphis, TN
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
DIVISION 00 - SPECIAL SECTIONS DATE
00 01 15 List of Drawing Sheets 07-15
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 12-18
01 01 110 IC Infection Control 03-20
01 01 10 1-Hour Construction Smoke Barrier 03-20
01 01 10 FSS Fire and Safety Control 03-20
01 27 50 Unit Prices
01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 04-13
01 33 23 Shop Drawings, Product Data, and Samples 05-17
01 35 26 Safety Requirements 02-17
01 42 19 Reference Standards 05-16
01 74 19 Construction Waste Management 09-13
01 81 13 Sustainable Construction Requirements 10-17
01 91 00 General Commissioning Requirements 10-15
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17
02 82 13.13 Glovebag Asbestos Abatement 09-15
02 82 13.2 Targeted Survey for Asbestos 03-20
02 82 13.3 Biannual Periodic Report 01-20
02 82 13.4 Asbestos OM Closure Form 06-11
DIVISION 03 – CONCRETE (NOT USED)
03 30 53 (Short Form) Cast-In-Place Concrete 08-17
DIVISION 05 – METALS (NOT USED)
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES (NOT USED)
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 84 00 Firestopping 02-16
07 92 00 Joint Sealants 10-17
DIVISION 08 – OPENINGS
08 31 13 Access Doors and Frames 02-16
DIVISION 09 – FINISHES
09 22 16 Non-Structural Metal Framing 06-18
09 29 00 Gypsum Board 06-18
09 30 13 Ceramic/Porcelain Tiling 09-15
09 51 00 Acoustical Ceilings 12-18
09 65 13 Resilient Base and Accessories 02-16
09 65 19 Resilient Tile Flooring 05-18
00 01 10-2
09 67 23.20 Resinous Flooring (Epoxy Base) 09-18
09 91 00 Painting 01-16
DIVISION 11 – EQUIPMENT (NOT USED)
DIVISION 12 – FURNISHINGS (NOT USED)
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-Structural
Components
01-14
DIVISION 14– CONVEYING EQUIPMENT (NOT USED)
DIVISION 21- FIRE SUPPRESSION (NOT USED)
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 07-16
22 05 12 General Motor Requirements for Plumbing Equipment 09-15
22 05 19 Meters and Gages for Plumbing Piping 09-15
22 05 23 General-Duty Valves for Plumbing Piping 09-15
22 07 11 Plumbing Insulation 09-15
22 08 00 Commissioning of Plumbing Systems 11-16
22 11 00 Facility Water Distribution 09-15
22 11 23 Domestic Water Pumps 09-15
22 35 00 Domestic Water Heat Exchangers 12-16
22 40 00 Plumbing Fixtures 09-15
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 08-17
23 07 11 HVAC and Boiler Plant Insulation 02-15
23 08 00 Commissioning of HVAC Systems 11-16
23 09 24 Water Quality Monitoring and Instrumentation N/A
23 22 13 Steam and Condensate Heating Piping 08-17
23 22 23 Steam Condensate Pumps 08-17
DIVISION 25 – INTEGRATED AUTOMATION (NOT USED)
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-16
26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17
26 05 26 Grounding and Bonding for Electrical Systems 01-17
26 05 33 Raceway and Boxes for Electrical Systems 01-18
26 29 21 Enclosed Switches and Circuit Breakers 01-17
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirements for Communications Installations 06-15
27 05 26 Grounding and Bonding for Communications Systems 06-15
27 05 33 Raceways and Boxes for Communications Systems 10-18
27 15 00 Communications Structured Cabling 01-16
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY (NOT
USED)
00 01 10-3
DIVISION 31 – EARTHWORK (NOT USED)
DIVISION 32 – EXTERIOR IMPROVEMENTS (NOT USED)
DIVISION 33 – UTILITIES (NOT USED)
DIVISION 34 – TRANSPORTATION (NOT USED)
DIVISION 48 – Electrical Power Generation (NOT USED)
00 01 10-4
THIS PAGE LEFT BLANK
Correct Plumbing Piping & Replace Fixtures 07-01-15
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWINGS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
GENERAL
G001 Cover Sheet
G002 Legends, Abbreviations and Notes
G003 General Key Notes
G004 Phasing Plan and Notes – First Floor
G005 Phasing Plan and Notes – Third Floor
HAZARDOUS ABATEMENT
H001 Hazardous Material Abatement General Notes
ARCHITECTURAL
Building 1
1-A101 Building 1 – Pipe Basement Plan – Overall Plan
1-A102 Building 1 – Pipe Basement Plan – Zone A
1-A104 Building 1 – Pipe Basement Plan – Zone C
1-A108 Building 1 – Ground Floor – Overall Plan
1-A109 Building 1 – Ground Floor – Zone A Plan
1-A110 Building 1 – Ground Floor – Zone B Plan
1-A111 Building 1 – Ground Floor – Zone C Plan
1-A112 Building 1 – Ground Floor– Zone D Plan
1-A113 Building 1 – Ground Floor– Zone E Plan
1-A114 Building 1 – Ground Floor – Zone F Plan
1-A115 Building 1 – First Floor – Overall Plan
1-A116 Building 1 – First Floor – Zone A Plan
1-A117 Building 1 – First Floor – Zone B Plan
1-A118 Building 1 – First Floor – Zone C Plan
1-A119 Building 1 – First Floor – Zone D Plan
1-A120 Building 1 – First Floor – Zone E Plan
1-A121 Building 1 – First Floor – Zone F Plan
1-A122 Building 1 – Second Floor – Overall Plan
1-A123 Building 1 – Second Floor – Zone A Plan
1-A124 Building 1 – Second Floor – Zone B Plan
00 01 15 - 2
Architecture Building 1 (cont.)
1-A125 Building 1 – Second Floor – Zone C Plan
1-A126 Building 1 – Second Floor – Zone D Plan
1-A127 Building 1 – Second Floor – Zone E Plan
1-A128 Building 1 – Second Floor – Zone F Plan
1-A129 Building 1 – Third Floor – Overall Plan
1-A130 Building 1 – Third Floor – Zone A Plan
1-A131 Building 1 – Third Floor – Zone B Plan
1-A132 Building 1 – Third Floor – Zone C Plan
1-A133 Building 1 – Fourth Floor – Overall Plan
Building 1A
1A-A101 Building 1A - Ground Floor – Overall Plan
1A-A102 Building 1A - Ground Floor – Zone A
1A-A103 Building 1A - Ground Floor – Zone B
1A-A104 Building 1A - Ground Floor – Zone C
1A-A105 Building 1A - Ground Floor – Zone D
1A-A106 Building 1A – First Floor – Overall Plan
1A-A107 Building 1A – First Floor – Zone A
1A-A108 Building 1A – First Floor – Zone B
1A-A109 Building 1A – First Floor – Zone C
1A-A110 Building 1A – First Floor – Zone D
A1-A111 Building 1A – Second Floor – Overall Plan
A1-A112 Building 1A – Second Floor – Zone A
A1-A113 Building 1A – Second Floor – Zone B
A1-A114 Building 1A – Second Floor – Zone C
A1-A115 Building 1A – Second Floor – Zone D
A1-A116 Building 1A – Third Floor – Overall Plan
A1-A117 Building 1A – Third Floor – Zone A
A1-A118 Building 1A – Third Floor – Zone B
A1-A119 Building 1A – Third Floor – Zone C
A1-A120 Building 1A – Third Floor – Zone D
A1-A121 Building 1A – Fourth Floor – Overall Plan
A1-A122 Building 1A – Fourth Floor – Zone A
A1-A123 Building 1A – Fourth Floor – Zone B
A1-A124 Building 1A – Fourth Floor – Zone C
A1-A125 Building 1A – Fourth Floor – Zone D
A1-A126 Building 1A – Fifth Floor – Overall Plan
00 01 15 - 3
Architecture Building 1A (cont.)
A1-A127 Building 1A – Fifth Floor – Zone A
A1-A128 Building 1A – Fifth Floor – Zone B
A1-A129 Building 1A – Fifth Floor – Zone C
A1-A130 Building 1A – Fifth Floor – Zone D
Building 1AC
1AC-A101 Building 1AC – Ground Floor – Overall Plan
1AC-A102 Building 1AC – First Floor – Overall Plan
1AC-A103 Building 1AC – Second Floor – Overall Plan
Building 5
5-A101 Building 5 – Ground Floor – Overall Plan
5-A102 Building 5 – Ground Floor – Zone A
5-A103 Building 5 – Ground Floor – Zone B
5-A104 Building 5 – Ground Floor – Zone C
5-A105 Building 5 – First Floor – Overall Plan
5-A106 Building 5 – First Floor – Zone A
5-A107 Building 5 – First Floor – Zone B
5-A108 Building 5 – First Floor – Zone C
5-A109 Building 5 – Second Floor – Overall Plan
Building 7
7-A101 Building 7 – Ground Floor – Overall Plan
7-A102 Building 7 – Ground Floor – Zone A
7-A103 Building 7 – Ground Floor – Zone B
7-A104 Building 7 – Ground Floor – Zone C
7-A105 Building 7 – Ground Floor – Zone D
7-A106 Building 7 – First Floor – Overall Plan
7-A107 Building 7 – First Floor – Zone A
7-A108 Building 7 – First Floor – Zone B
7-A109 Building 7 – First Floor – Zone C
7-A110 Building 7 – First Floor – Zone D
7-A111 Building 7 – Second Floor – Overall Plan
7-A112 Building 7 – Second Floor – Zone A
7-A113 Building 7 – Second Floor – Zone B
7-A114 Building 7 – Second Floor – Zone C
7-A115 Building 7 – Second Floor – Zone D
00 01 15 - 4
Building 9
9-A101 Building 9 – First Floor – Overall Plan
9-A501 Wall Details
9-A601 Partition Types and Finish Schedule
PLUMBING
P001 Legends and Notes
P002 Controls and Instrumentation
Building 1
1-PD101 Basement Floor Zone A Demolition Piping Plan
1-PD102 Basement Floor Zone B Demolition Piping Plan
1-PD103 Basement Floor Zone C Demolition Piping Plan
1-PD104 Basement Floor Zone D Demolition Piping Plan
1-PD105 Basement Floor Zone E Demolition Piping Plan
1-PD106 Basement Floor Zone F Demolition Piping Plan
1-PD107 Ground Floor Zone A Demolition Piping Plan
1-PD108 Ground Floor Zone B Demolition Piping Plan
1-PD109 Ground Floor Zone C Demolition Piping Plan
1-PD110 Ground Floor Zone D Demolition Piping Plan
1-PD111 Ground Floor Zone E Demolition Piping Plan
1-PD112 Ground Floor Zone F Demolition Piping Plan
1-PD113 First Floor Zone A Demolition Piping Plan
1-PD114 First Floor Zone B Demolition Piping Plan
1-PD115 First Floor Zone C Demolition Piping Plan
1-PD116 First Floor Zone D Demolition Piping Plan
1-PD117 First Floor Zone E Demolition Piping Plan
1-PD118 First Floor Zone F Demolition Piping Plan
1-PD119 Second Floor Zone A Demolition Piping Plan
1-PD120 Second Floor Zone B Demolition Piping Plan
1-PD121 Second Floor Zone C Demolition Piping Plan
1-PD122 Second Floor Zone D Demolition Piping Plan
1-PD123 Second Floor Zone E Demolition Piping Plan
1-PD124 Second Floor Zone F Demolition Piping Plan
1-PD125 Third Floor Zone A Demolition Piping Plan
1-PD126 Third Floor Zone B Demolition Piping Plan
1-PD127 Third Floor Zone C Demolition Piping Plan
1-PD128 Fourth Floor Zone A Demolition Piping Plan
1-PD129 Fourth Floor Zone B Demolition Piping Plan
1-PD201 Mechanical Room Demolition Plumbing Phase 1
1-PD202 Mechanical Room Demolition Plumbing Phase 2
1-MED201 Mechanical Room Demolition Steam Phase 1
1-MED202 Mech Room Demolition Steam & Electrical Phase 2
00 01 15 - 5
1-PP101
Plumbing – Bldg. 1 (cont.)
Basement Level Zone A New Work Piping Plan
1-PP102 Basement Level Zone B New Work Piping Plan
1-PP103 Basement Level Zone C New Work Piping Plan
1-PP104 Basement Level Zone D New Work Piping Plan
1-PP105 Basement Level Zone E New Work Piping Plan
1-PP106 Basement Level Zone F New Work Piping Plan
1-PP107 Ground Floor Zone A New Work Piping Plan
1-PP108 Ground Floor Zone B New Work Piping Plan
1-PP109 Ground Floor Zone C New Work Piping Plan
1-PP110 Ground Floor Zone D New Work Piping Plan
1-PP111 Ground Floor Zone E New Work Piping Plan
1-PP112 Ground Floor Zone F New Work Piping Plan
1-PP113 First Floor Zone A New Work Piping Plan
1-PP114 First Floor Zone B New Work Piping Plan
1-PP115 First Floor Zone C New Work Piping Plan
1-PP116 First Floor Zone D New Work Piping Plan
1-PP117 First Floor Zone E New Work Piping Plan
1-PP118 First Floor Zone F New Work Piping Plan
1-PP119 Second Floor Zone A New Work Piping Plan
1-PP120 Second Floor Zone B New Work Piping Plan
1-PP121 Second Floor Zone C New Work Piping Plan
1-PP122 Second Floor Zone D New Work Piping Plan
1-PP123 Second Floor Zone E New Work Piping Plan
1-PP124 Second Floor Zone F New Work Piping Plan
1-PP125 Third Floor Zone A New Work Piping Plan
1-PP126 Third Floor Zone B New Work Piping Plan
1-PP127 Third Floor Zone C New Work Piping Plan
1-PP128 Fourth Floor Zone A New Work Piping Plan
1-PP129 Fourth Floor Zone B New Work Piping Plan
1-PP201 Mechanical Room New Work Plumbing Phase 1
1-PP301 Wtr Htr Plumb Piping New Work Riser Diag - Phase 1
1MEP201 Mechanical Room New Work Steam & Electrical Phase 1
1A-PD101 Ground Floor Zone A – Demolition Piping Plan
1A-PD102 Ground Floor Zone B – Demolition Piping Plan
1A-PD103 Ground Floor Zone C – Demolition Piping Plan
1A-PD104 Ground Floor Zone D – Demolition Piping Plan
1A-PD105 First Floor Zone A – Demolition Piping Plan
1A-PD106 First Floor Zone B – Demolition Piping Plan
1A-PD107 First Floor Zone C – Demolition Piping Plan
00 01 15 - 6
Plumbing – Bldg. 1A (cont.)
1A-PD108 First Floor Zone D – Demolition Piping Plan
1A-PD109 Second Floor Zone A – Demolition Piping Plan
1A-PD110 Second Floor Zone B – Demolition Piping Plan
1A-PD111 Second Floor Zone C – Demolition Piping Plan
1A-PD112 Second Floor Zone D – Demolition Piping Plan
1A-PD113 Third Floor Zone A – Demolition Piping Plan
1A-PD114 Third Floor Zone B – Demolition Piping Plan
1A-PD115 Third Floor Zone C – Demolition Piping Plan
1A-PD116 Third Floor Zone D – Demolition Piping Plan
1A-PD117 Fourth Floor Zone A – Demolition Piping Plan
1A-PD118 Fourth Floor Zone B – Demolition Piping Plan
1A-PD119 Fourth Floor Zone C – Demolition Piping Plan
1A-PD120 Fourth Floor Zone D – Demolition Piping Plan
1A-PD121 Fifth Floor Zone A – Demolition Piping Plan
1A-PD122 Fifth Floor Zone B – Demolition Piping Plan
1A-PD123 Fifth Floor Zone C – Demolition Piping Plan
1A-PD124 Fifth Floor Zone D – Demolition Piping Plan
1A-PD201 Mech Room Demolition Plumbing - Phases 1 & 2
1A-PD301 Wtr Htr Plumb Piping Demo Riser Diag-Phase 1
1A-PD302 Wtr Htr Plumb Piping Demo Riser Diag-Phase 2
1A-MED201 Mech Room Demo Steam and Electrical Phases 1&2
1A-PP101 Ground Floor Zone A – New Work Piping Plan
1A-PP102 Ground Floor Zone B – New Work Piping Plan
1A-PP103 Ground Floor Zone C – New Work Piping Plan
1A-PP104 Ground Floor Zone D – New Work Piping Plan
1A-PP105 First Floor Zone A – New Work Piping Plan
1A-PP106 First Floor Zone B – New Work Piping Plan
1A-PP107 First Floor Zone C – New Work Piping Plan
1A-PP108 First Floor Zone D – New Work Piping Plan
1A-PP109 Second Floor Zone A – New Work Piping Plan
1A-PP110 Second Floor Zone B – New Work Piping Plan
1A-PP111 Second Floor Zone C – New Work Piping Plan
1A-PP112 Second Floor Zone D – New Work Piping Plan
1A-PP113 Third Floor Zone A – New Work Piping Plan
1A-PP114 Third Floor Zone B – New Work Piping Plan
1A-PP115 Third Floor Zone C – New Work Piping Plan
00 01 15 - 7
Plumbing – Bldg. 1A (cont.)
1A-PP116 Third Floor Zone D – New Work Piping Plan
1A-PP117 Fourth Floor Zone A – New Work Piping Plan
1A-PP118 Fourth Floor Zone B – New Work Piping Plan
1A-PP119 Fourth Floor Zone C – New Work Piping Plan
1A-PP120 Fourth Floor Zone D – New Work Piping Plan
1A-PP121 Fifth Floor Zone A – New Work Piping Plan
1A-PP122 Fifth Floor Zone B – New Work Piping Plan
1A-PP123 Fifth Floor Zone C – New Work Piping Plan
1A-PP124 Fifth Floor Zone D – New Work Piping Plan
1A-PP201 Mech Room – New Work Plumbing - Phases 1 & 2
1A-PP301 Wtr Htr Plumb Ppg New Work Riser Diag – Phase 1
1A-PP302 Wtr Htr Plumb Ppg New Work Riser Diag – Phase 2
1A-MEP201 Mech Room – New Work Steam & Elect Phases 1&2
1AC-PD101 Ground Floor – Demolition Piping Plan
1AC-PD102 First Floor – Demolition Piping Plan
1AC-PD103 Second Floor – Demolition Piping Plan
1AC-PD201 Mech Room Demolition Plumbing - Phases 1 & 2
1AC-PD301 Wtr Htr Plumb Piping Demo Riser Diag – Phase 1
1AC-PD302 Wtr Htr Plumb Piping Demo Riser Diag – Phase 2
1AC-MED201 Mech Room – Demo Steam & Electrical Phases 1&2
1AC-PP101 Ground Floor – New Work Piping Plan
1AC-PP102 First Floor – New Work Piping Plan
1AC-PP103 Second Floor – New Work Piping Plan
1AC-PP201 Mech Room – New Work Plumbing - Phases 1 & 2
1AC-PP301 Wtr Htr Plumb Ppg New Work Riser Diag – Phase 1
1AC-PP302 Wtr Htr Plumb Ppg New Work Riser Diag – Phase 2
1AC-MEP201 Mech Room – New Work Steam & Elect Phases 1&2
5-PD101 Ground Floor Zone A – Demolition Piping Plan
5-PD102 Ground Floor Zone B – Demolition Piping Plan
5-PD103 Ground Floor Zone C – Demolition Piping Plan
5-PD104 First Floor Zone A – Demolition Piping Plan
5-PD105 First Floor Zone B – Demolition Piping Plan
5-PD106 First Floor Zone C – Demolition Piping Plan
00 01 15 - 8
Plumbing – Bldg. 5 (cont.)
5-PD107 Second Floor – Demolition Piping Plan
5-PD201 Mech Room Demolition Plumbing - Phases 1 & 2
5-PD301 Water Heater Plumbing Piping Demo Riser Diagram
– Phase 1
5-PD302 Water Heater Plumbing Piping Demo Riser Diagram
– Phase 2
5-MED201 Mech Room – Demolition Steam & Elect Phases 1&2
5-PP101 Ground Floor Zone A – New Work Piping Plan
5-PP102 Ground Floor Zone B – New Work Piping Plan
5-PP103 Ground Floor Zone C – New Work Piping Plan
5-PP104 First Floor Zone A – New Work Piping Plan
5-PP105 First Floor Zone B – New Work Piping Plan
5-PP106 First Floor Zone C – New Work Piping Plan
5-PP107 Second Floor – New Work Piping Plan
5-PP201 Mechanical Room New Work Plumbing Phase 1&2
5-PP301 Water Heater Plumbing Piping New Work Riser
Diagram – Phase 1
5-PP302 Water Heater Plumbing Piping Demo Riser Diagram
– Phase 2
5-MEP201 Mech Room New Work Steam and Elect Phase 1&2
7-PD101 Ground Floor Zone A – Demolition Piping Plan
7-PD102 Ground Floor Zone B – Demolition Piping Plan
7-PD103 Ground Floor Zone C – Demolition Piping Plan
7-PD104 Ground Floor Zone D – Demolition Piping Plan
7-PD105 First Floor Zone A – Demolition Piping Plan
7-PD106 First Floor Zone B – Demolition Piping Plan
7-PD107 First Floor Zone C – Demolition Piping Plan
7-PD108 First Floor Zone D – Demolition Piping Plan
7-PD109 Second Floor Zone A – Demolition Piping Plan
7-PD110 Second Floor Zone B – Demolition Piping Plan
7-PD111 Second Floor Zone C – Demolition Piping Plan
7-PD112 Second Floor Zone D – Demolition Piping Plan
7-PD201 Mechanical Room Demolition Plumbing –Phases 1&2
7-MED201 Mech Room – Demo Steam & Electrical Phases 1&2
7-PP101 Ground Floor Zone A – New Work Piping Plan
00 01 15 - 9
Plumbing – Bldg. 7 (cont.)
7-PP102 Ground Floor Zone B – New Work Piping Plan
7-PP103 Ground Floor Zone C – New Work Piping Plan
7-PP104 Ground Floor Zone D – New Work Piping Plan
7-PP105 First Floor Zone A – New Work Piping Plan
7-PP106 First Floor Zone B – New Work Piping Plan
7-PP107 First Floor Zone C – New Work Piping Plan
7-PP108 First Floor Zone D – New Work Piping Plan
7-PP109 Second Floor Zone A – New Work Piping Plan
7-PP110 Second Floor Zone B – New Work Piping Plan
7-PP111 Second Floor Zone C – New Work Piping Plan
7-PP112 Second Floor Zone D – New Work Piping Plan
7-PP201 Mechanical Room New Work Plumbing – Phase 1&2
7-MEP201 Mech Room – New Work Steam & Elect Phases 1
9-PD101 First Floor – Demolition Piping Plan
9-PP101 First Floor – New Work Piping Plan
9-PP401 Details
9-PP402 Details
9-PP501 Schedules
END OF BID DOCUMENTS
The drawings listed below accompanying this specification form a part of the contract. It is provided as a separate set of drawings for the existing conditions and identified as “Mapping Set”.
Drawing No. Title
GENERAL
G001 Cover Sheet
Existing Conditions Map
P001 Domestic Water Existing Conditions Map
Building 1
1-PP101E Basement Level Zone A - Dom Water Exist Cond Map
1-PP102E Basement Level Zone B - Dom Water Exist Cond Map
1-PP103E Basement Level Zone C - Dom Water Exist Cond Map
1-PP104E Basement Level Zone D - Dom Water Exist Cond Map
00 01 15 - 10
Existing Con Map Bldg 1 cont.
1-PP105E Basement Level Zone E - Dom Water Exist Cond Map
1-PP106E Basement Level Zone F - Dom Water Exist Cond Map
1-PP107E Ground Floor Zone A - Dom Water Exist Cond Map
1-PP108E Ground Floor Zone B - Dom Water Exist Cond Map
1-PP109E Ground Floor Zone C - Dom Water Exist Cond Map
1-PP110E Ground Floor Zone D - Dom Water Exist Cond Map
1-PP111E Ground Floor Zone E - Dom Water Exist Cond Map
1-PP112E Ground Floor Zone F - Dom Water Exist Cond Map
1-PP113E First Floor Zone A - Dom Water Exist Cond Map
1-PP114E First Floor Zone B - Dom Water Exist Cond Map
1-PP115E First Floor Zone C - Dom Water Exist Cond Map
1-PP116E First Floor Zone D - Dom Water Exist Cond Map
1-PP117E First Floor Zone E - Dom Water Exist Cond Map
1-PP118E First Floor Zone F - Dom Water Exist Cond Map
1-PP119E Second Floor Zone A - Dom Water Exist Cond Map
1-PP120E Second Floor Zone B - Dom Water Exist Cond Map
1-PP121E Second Floor Zone C - Dom Water Exist Cond Map
1-PP122E Second Floor Zone D - Dom Water Exist Cond Map
1-PP123E Second Floor Zone E - Dom Water Exist Cond Map
1-PP124E Second Floor Zone F - Dom Water Exist Cond Map
1-PP125E Third Floor Zone A - Dom Water Exist Cond Map
1-PP126E Third Floor Zone B - Dom Water Exist Cond Map
1-PP127E Third Floor Zone C - Dom Water Exist Cond Map
1-PP128E Fourth Floor Zone A - Dom Water Exist Cond Map
1-PP129E Fourth Floor Zone B - Dom Water Exist Cond Map
1A-PP101E Ground Floor Zone A-Dom Water Exist Cond Map
1A-PP102E Ground Floor Zone B-Dom Water Exist Cond Map
1A-PP103E Ground Floor Zone C-Dom Water Exist Cond Map
1A-PP104E Ground Floor Zone D-Dom Water Exist Cond Map
1A-PP105E First Floor Zone A-Dom Water Exist Cond Map
1A-PP106E First Floor Zone B-Dom Water Exist Cond Map
1A-PP107E First Floor Zone C-Dom Water Exist Cond Map
1A-PP108E First Floor Zone D-Dom Water Exist Cond Map
1A-PP109E Second Floor Zone A-Dom Water Exist Cond Map
1A-PP110E Second Floor Zone B-Dom Water Exist Cond Map
1A-PP111E Second Floor Zone C-Dom Water Exist Cond Map
1A-PP112E Second Floor Zone D-Dom Water Exist Cond Map
1A-PP113E Third Floor Zone A-Dom Water Exist Cond Map
1A-PP114E Third Floor Zone B-Dom Water Exist Cond Map
00 01 15 - 11
Bldg 1A cont.
1A-PP115E Third Floor Zone C-Dom Water Exist Cond Map
1A-PP116E Third Floor Zone D-Dom Water Exist Cond Map
1A-PP117E Fourth Floor Zone A-Dom Water Exist Cond Map
1A-PP118E Fourth Floor Zone B-Dom Water Exist Cond Map
1A-PP119E Fourth Floor Zone C-Dom Water Exist Cond Map
Existing Con Map Bldg 1A cont.
1A-PP120E Fourth Floor Zone D-Dom Water Exist Cond Map
1A-PP121E Fifth Floor Zone A-Dom Water Exist Cond Map
1A-PP122E Fifth Floor Zone B-Dom Water Exist Cond Map
1A-PP123E Fifth Floor Zone C-Dom Water Exist Cond Map
1A-PP124E Fifth Floor Zone D-Dom Water Exist Cond Map
1AC-PP101E Ground Floor-Dom Water Exist Cond Map
1AC-PP102E First Floor-Dom Water Exist Cond Map
1AC-PP103E Second Floor-Dom Water Exist Cond Map
5-PP101E Ground Floor Zone A-Dom Water Exist Cond Map
5-PP102E Ground Floor Zone B-Dom Water Exist Cond Map
5-PP103E Ground Floor Zone C-Dom Water Exist Cond Map
5-PP104E First Floor Zone A-Dom Water Exist Cond Map
5-PP105E First Floor Zone B-Dom Water Exist Cond Map
5-PP106E First Floor Zone C-Dom Water Exist Cond Map
5-PP107E Second Floor – Dom Water Exist Cond Map
7-PP101E Ground Floor Zone A-Dom Water Exist Cond Map
7-PP102E Ground Floor Zone B-Dom Water Exist Cond Map
7-PP103E Ground Floor Zone C-Dom Water Exist Cond Map
7-PP104E Ground Floor Zone D-Dom Water Exist Cond Map
7-PP105E First Floor Zone A-Dom Water Exist Cond Map
7-PP106E First Floor Zone B-Dom Water Exist Cond Map
7-PP107E First Floor Zone C-Dom Water Exist Cond Map
7-PP108E First Floor Zone D-Dom Water Exist Cond Map
7-PP109E Second Floor Zone A-Dom Water Exist Cond Map
00 01 15 - 12
Bldg 7 cont.
7-PP110E Second Floor Zone B-Dom Water Exist Cond Map
7-PP111E Second Floor Zone C-Dom Water Exist Cond Map
7-PP112E Second Floor Zone D-Dom Water Exist Cond Map
9-PP101E First Floor – Dom Water Exist Cond Map
- - - E N D - - -
Correct Plumbing Piping & Replace Fixtures 12-01-18
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing, and furnish labor and materials and perform work for Plumbing Corrections and Fixture
Replacement as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the
Medical Center Engineering Officer.
C. Offices of Toland-Mizell-Molnar, LLC. as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
A. BID ITEM I, Base Bid: Work includes all work as described in contract documents for general construction, plumbing, electrical, monitoring equipment, controls, architectural, and related trades as necessary for a complete project as related to dead end removal, water heater replacement, hot water circulation pump replacement, balancing valve replacement, new medium pressure steam supply pipe, new condensate return pipe, new high pressure steam to medium pressure steam pressure reducing station, new steam pressure relief valve vent piping, new cold water pipe for heater replacement, new hot water pipe for heater replacement, new hot water return pipe for heater replacement, and new insulation for all associated pipe. Water heaters shall be installed, 01 00 00 -2 tested, and operational at one location/building before start of construction at any subsequent location/building. Building/location sequence will be coordinated and scheduled with VA COR. BID ITEM 1 Base
Bid also includes additional installed ball valves, blocking valves, insulation footage of existing domestic water pipe, and asbestos containing materials removal and disposal identified as quantity allowances.
Excluded from BID ITEM 1 Base Bid:
1. All work described for chlorine monitoring stations, monitoring station controls, and associated monitoring station items.
2. All work described for Building 5.
3. Period of performance: 520 calendar days from issuance of the
Notice to Proceed.
B. OPTION NO. 1: Provide all work described for chlorine monitoring stations, monitoring station controls, and associated monitoring station items at 6 locations; …
1. The Government may exercise OPTION NO. 1 by written notice to the Contractor prior to December 31, 2020; provided that the
Government gives the Contractor a preliminary written notice of its intent to exercise OPTION NO. 1 prior to December 1, 2020. The preliminary notice does not commit the Government to exercise OPTION No. 1.
2. Period of performance: 520 calendar days from issuance of the
Notice to Proceed.
C. OPTION NO. 2: Provide all work described for Building 5
1. The Government may exercise OPTION NO. 2 by written notice to the Contractor prior to December 31, 2020; provided that the
Government gives the Contractor a preliminary written notice of its intent to exercise OPTION NO. 2 prior to December 1, 2020. The preliminary notice does not commit the Government to exercise OPTION No. 2.
2. Period of performance: 520 calendar days from the exercise of
Option 2, or 580 calendar days from the issuance of Notice to
Proceed, whichever date is later.
01 00 00 -3
D. OPTION NO. 3: Provide all work described for chlorine monitoring stations, monitoring station controls, and associated monitoring station items at remaining locations shown on contract drawings.
1. The Government may exercise OPTION NO. 3 by written notice to the Contractor prior to December 31, 2020; provided that the
Government gives the Contractor a preliminary written notice of its intent to exercise OPTION NO. 3 prior to December 1, 2020. The preliminary notice does not commit the Government to exercise OPTION No. 3.
2. Period of performance: 520 calendar days from the exercise of
Option 2, or 580 calendar days from the issuance of Notice to
Proceed, whichever date is later.
E. UNIT PRICED ITEMS:
1. Related Work: Section 01 27 50, UNIT PRICES AND QUANTITY
ALLOWANCES.
2. New three-piece ball valves (separate line item for each size
– P-1 thru P-9);
a. 50 units each of ½”, ¾”, 1”, 1 ¼”, 1½”, 2” & 2½”
b. 25 units each of 3” & 4”
3. New Pipe-block valves (separate line item for each size – P-10 thru P-15);
a. 25 units each of ½”, ¾”, 1”, 1 ¼”, 1½”, & 2”
4. ACM abatement values (using the specified “Glove-Bag methodology – H-1):
a. 100 pipe fittings
5. Insulation of uninsulated piping not affected by new work (I-1 thru I-3):
a. 1/2" – 1” domestic water pipe size insulation and complete installation. Provide 500 linear feet. Provide price per linear foot.
b. 1-1/4” – 2” domestic water pipe size insulation and complete installation. Provide 500 linear feet. Provide price per linear foot.
c. 2-1/2” – 4” domestic water pipe size insulation and complete installation. Provide 500 linear feet. Provide price per linear foot.
01 00 00 -4
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR for the purpose of security inspections of every area of project including toolboxes and parked machines and take any emergency action.
01 00 00 -5
2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71
00, DOOR HARDWARE and coordinate.
D. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of
“sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
01 00 00 -6
E. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. A limited number of (2 to 5) permits shall be issued for General
Contractor and its employees for parking in designated areas only.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
C. Working space and space available for storing materials shall be as determined by the COR.
D. Workmen are subject to rules of Medical Center applicable to their conduct.
E. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR.
01 00 00 -7
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities sufficient for not more than two workdays. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
F. Phasing:
The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.
It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to: Night work hours.
To insure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to insure accomplishment of this work in successive phases mutually agreeable to
Medical Center Director, COR and Contractor, as follows:
G. Buildings will be occupied during performance of work.
Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of
Veterans Affairs personnel and patients through other construction
01 00 00 -8 areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting, etc. to facilitate patient and staff access.
Coordinate alteration work in areas occupied by Department of
Veterans Affairs so that Medical Center operations will continue during the construction period.
H. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment.
J. Utilities Services: Maintain existing utility services for Medical
Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.
When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR
COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR
ELECTRONIC SAFETY AND SECURITY for additional requirements.
01 00 00 -9
2. Contractor shall submit a request to interrupt any such services to
COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
K. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
L. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
01 00 00 -10
M. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Supply
Service, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by all three, to the Contracting Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout // affected areas of building.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur, and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR and/or Supply Representative, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by
Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE
CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4 and VAAR
852.236-88).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on
01 00 00 -11 conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of
Contractor to restore damage caused by Contractor's workmen in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled, and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
01 00 00 -12
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
4. PCB Transformers and Capacitors: The Contractor shall be responsible for disposal of the Polychlorinated Biphenyl (PCB) transformers and capacitors. The transformers and capacitors shall be taken out of service and handled in accordance with the procedures of the
Environmental Protection Agency (EPA) and the Department of
Transportation (DOT) as outlined in Code of Federal Regulation
(CFR), Titled 40 and 49 respectively. The EPA's Toxic Substance
Control Act (TSCA) Compliance Program Policy Nos. 6-PCB-6 and 6-PCB-
7 also apply. Upon removal of PCB transformers and capacitors for disposal, the "originator" copy of the Uniform Hazardous Waste
Manifest (EPA Form 8700-22), along with the Uniform Hazardous Waste
Manifest Continuation Sheet (EPA Form 8700-22A) shall be returned to the Contracting Officer who will annotate the contract file and transmit the Manifest to the Medical Center's Chief.
a. Copies of the following listed CFR titles may be obtained from the Government Printing Office:
40 CFR 261........Identification and Listing of Hazardous Waste
40 CFR 262........Standards Applicable to Generators of Hazardous
Waste
40 CFR 263........Standards Applicable to Transporters of
Hazardous Waste
40 CFR 761........PCB Manufacturing, Processing, Distribution in
Commerce, and use Prohibitions
49 CFR 172........Hazardous Material tables and Hazardous
Material Communications Regulations
01 00 00 -13
49 CFR 173........Shippers - General Requirements for Shipments and Packaging
49 CRR 173........Subpart A General
49 CFR 173........Subpart B Preparation of Hazardous Material for
Transportation
49 CFR 173........Subpart J Other Regulated Material; Definitions and Preparation
TSCA..............Compliance Program Policy Nos. 6-PCB-6 and 6-
PCB-7
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the
COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
01 00 00 -14
(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR
52.236-2).
1.14 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the COR’s review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.15 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on Medical
Center property When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
1.18 TEMPORARY USE OF EXISTING ELEVATORS
A. Use of existing elevators for handling building materials and
Contractor's personnel will be permitted subject to following provisions:
1. Contractor makes all arrangements with the COR for use of elevators.
The COR will ascertain that elevators are in proper condition.
Personnel for operating elevators will not be provided by the
Department of Veterans Affairs.
2. Contractor covers and provides maximum protection of following elevator components:
a. Entrance jambs, heads soffits and threshold plates.
b. Entrance columns, canopy, return panels and inside surfaces of car enclosure walls.
01 00 00 -15
c. Finish flooring.
1.20 TEMPORARY TOILETS
A. A Contractor may have for use of Contractor's workmen, such toilet accommodations as may be assigned to Contractor by Medical Center.
Contractor shall keep such places clean and be responsible for any damage done thereto by Contractor's workmen. Failure to maintain satisfactory condition in toilets will deprive Contractor of the privilege to use such toilets.
1.21 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The Contractor shall carefully conserve any utilities furnished without charge.
B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as…