About this file
This is an Independent Cost Estimate (ICE) document prepared by the Orange County Transportation Authority (OCTA) for tree maintenance and pruning services. The procurement covers tree trimming, removal, stump grinding, and palm tree skinning services across OCTA properties, including new locations at the OC Streetcar and MSF facilities. The scope includes approximately 960 trees for trimming, 15 trees for removal and stump grinding, and 30 palm trees for skinning (600 linear feet). The contract term is two years with an option term date of October 1, 2025. The requisition number is R000690, and the contract replaces the expiring Agreement C-53855 (expiring March 31, 2026).
The total estimated cost for the two-year contract period is $210,600.00, calculated at an annual cost of $105,300.00 based on historical billing data under the existing agreement. Unit prices reflect $90 per tree for trimming, $300 per tree for removal and stump grinding, and $24 per linear foot for palm tree skinning. This is a prevailing wage contract, and the cost estimate is based on historical average billing rates from Agreement C-53855 covering approximately 760 trees, with additional estimated costs for approximately 200 new trees at the specified locations. The estimate was prepared by Christine Herrera, Contracts Analyst, and submitted to Contracts Administration & Materials Management (CAMM) for procurement processing.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INDEPENDENT COST ESTIMATE (ICE)
FA-CAMM-006.docm (09/25/15) Page 1 of 3
INSTRUCTIONS
Complete and submit all three pages to Contracts Administration & Materials Management (CAMM), along with your requisition and scope of work. CAMM will not start the procurement until all three documents have been received.
PART I – GENERAL INFORMATION
Project Description: Tree Maintenance & Pruning Services
SHADED AREA FOR PROCUREMENT USE ONLY
Assigned Buyer No.:
D/M/WBE%:
Purchase Requisition No.: R000690
New Contract / Procurement
Contract Amendment Current IFAS Printout Contract / PO No.:
(Required for Amendments)
Contract Task Order
Option Term
Date: 10/1/2025
Requestor: Christine Herrera Contracts Analyst Phone Ext.: 5485 Name Title
Signature:
Cost Estimate: $ 210,600.00 (include shipping, handling and taxes, if applicable)
PART II – ESTIMATE GUIDE
Please substantiate the estimate using the following information.
Estimate Type Items to Include Where to Find Supporting Information
Services (Other than A&E)
1. Tasks you want done
2. Types of people needed (i.e., supervisor, administrative assistant, other)
3. Positions required (i.e., Project Manager, Deputy PM, Senior Engineer / Planner, other)
4. Estimated hours by position
5. Salary / billing rates applied
6. Prevailing wage rate category applied
7. Profit / applied fee
8. Direct expenses
9. Completion schedule
1. Current or past contracts for similar services
2. Other properties / departments doing similar work
3. Historical price and cost data
Estimate Guide Continued
FA-CAMM-006.docm (09/25/15) Page 2 of 3
Estimate Type Items to Include Where to Find Supporting Information
Architects, Engineers, Designers
1. Tasks you want done
2. Types of people needed (i.e., engineers, administrative assistant, other)
3. Positions (Project Manager, Deputy PM, Senior Engineer / Planner, other)
4. Estimated hours by position
5. Salary / billing rates applied
6. Profit / applied fee
7. Overhead rate (%)
8. Direct expenses
9. Completion schedule
1. Current or past contracts for similar services
2. Other properties / departments doing similar work
3. Historical price and cost data
Goods/Equipment 1. Product needed
2. Quantity
3. Unit price
4. Markups, overhead, profit
5. Delivery schedule desired
6. Warranty
1. Vendor survey / market survey
2. Current or past contracts for the same or similar product
3. Historical price and cost data
4. Various published indices
Construction 1. Product needed
2. Labor (at a minimum use Davis Bacon)
3. Materials
4. Bonds
5. Insurance
6. Mobilization
7. Equipment
8. Markups, fringes, overheads, profit
9. Completion schedule
1. “Means Book”
2. “Blue Book”
3. Davis Bacon wage rates / prevailing wages
4. Current or past contracts for the same project
5. Historical price and cost data
Additional Information: This contract replaces Agreement C-53855 expiring 3/31/2026. The Independent Cost Estimate is based on historical billing under the existing agreement for approximately 760 trees and includes estimated costs for approximately 200 additional trees at the OC Streetcar and MSF locations. Unit prices reflect historical average billing rates under Agreement C-53855. Estimated Annual Costs:
Tree Trimming: 960 trees × $90 per tree = $86,400 Tree Removal & Stump Grinding: 15 trees × $300 per tree = $4,500 Palm Tree Skinning: 30 trees × 20 feet (600 LF) × $24 per foot = $14,400 Total Estimated Annual Cost: $105,300 Total for Two-Year Term: $105,300 × 2 years = $210,600
FA-CAMM-006.docm (09/25/15) Page 3 of 3
PART III – INDEPENDENT COST ESTIMATE
Using the information provided in Part II, prepare the ICE for your procurement.
Use any or all of the categories listed below.
Prepared By: Christine Herrera Date: 10/1/2025
Signature:
DESCRIPTION OF COST ELEMENTS
1. DIRECT LABOR
(List of Labor Categories)
Estimated Hours
Rate Per Hour ($)
Estimated Cost ($)
Total Est.
Cost ($)
$ $ 0.00 $ $ 0.00 $ $ 0.00 $ $ 0.00 $ $ 0.00 $ $ 0.00
Total Direct Labor: $ 0.00
2. OVERHEAD
Rate (%)
(use decimal input)
Total Labor ($)
Estimated Cost ($)
Total Est.
Cost ($)
% $ 0.00 $ 0.00 $ 0.00
3. MATERIALS/SERVICES (Excluding Information Technology [IT]) Estimated Cost ($)
Total Est.
Cost ($)
Tree Maintenance & Pruning Services $ 210,600.00 $ 210,600.00
4. INFORMATION TECHNOLOGY SUPPORT Estimated Cost ($)
Total Est.
Cost ($)
Total IT Support: $ 0.00
5. TRAVEL Estimated Cost ($)
Total Est.
Cost ($)
$ $ 0.00
6. SUBCONTRACTOR(S) / CONSULTANT(S) Estimated Cost ($)
Total Est.
Cost ($)
Total Subcontractor(s) / Consultant(s): $ 0.00
7. OTHER DIRECT COSTS Estimated Cost ($)
Total Est.
Cost ($)
$ $ 0.00
8. TOTAL ESTIMATED COST: $ 210,600.00