C250214_PP.pdf
PDF 166 KB Posted
- Attached to
- Bus Scaffolding Systems
- Solicitation number
- 250214
- Issued by
- Orange County, California
About this file
This is a procurement plan interoffice memorandum from the Orange County Transportation Authority (OCTA) in California, dated March 31, 2026, outlining the evaluation and contract strategy for Invitation for Bid (IFB) No. 250214 for Bus Scaffolding Systems. The procurement seeks qualified contractors to provide two bus scaffolding systems for a two-year contract term. The IFB approach was selected because the requirement allows for selection of the lowest, responsive, and responsible bidder without requiring specialized skills, qualifications, or detailed work plans. The evaluation will be based solely on cost, which will serve as the determining factor in the bid assessment. No optional renewal terms are noted in the procurement plan.
The contract will be awarded as a firm fixed price blanket purchase order with one-time fees covering scaffolding equipment, installation and setup, freight, training, and warranty for each base. The total budget allocated for this procurement is $500,000 from local Measure M funding. The contract includes provisions for retention, prevailing wages, and liquidated damages. An independent cost estimate has been received, and requisition number R001097 was submitted. The procurement plan indicates that a Database of Eligible vendors (DBE) goal applies to this solicitation. The procurement schedule and staffing requirements are attached to the plan, which required concurrence from both the Transit Technical Services Supervisor and the Department Manager of Contracts and Procurement.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bus_Scaffolding_Systems.pdf | ||
| C250214_PP-APPROVED.pdf | ||
| 250214_IFB_Exhibit_A_SOW.pdf | ||
| 250214_IFB_Exhibit_A_SOW_GMEDITS.docx | DOCX document | |
| C250214_SOWV_gmedits.pdf | ||
| C250214_PP_GMEDITS.pdf | ||
| C250214_Notice_of_Proof.pdf | ||
| 250214_PS_v3.pdf | ||
| 250214_IFB_Exhibit_B_Price_Summary_Sheet.pdf | ||
| 250214_IFB_Exhibit_C_Insurance.pdf | ||
| 250214_IFB_Exhibit_D_Safety_Specifications.pdf | ||
| C250214_250214-001.pdf | ||
| C250214_ICE.pdf | ||
| DBE_Program_Requirements.docx | DOCX document | |
| Davis-Bacon_Labor_Provisions.pdf | ||
| C250214_PM_Correspondence.pdf | ||
| C250214_Insurance_Review.pdf | ||
| C250214_SOWV.pdf |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INTEROFFICE MEMO
March 31, 2026
To: Eric Peterson, Supervisor, Transit Technical Services
From: Trevor Worthy, Senior Contract Administrator, CAMM
Subject: Procurement Plan for Release, Selection and Award
IFB No. 250214 for “Bus Scaffolding Systems”
Please review the procurement plan for the subject IFB and advise your concurrence with the evaluation criteria and contract elements. Include suggested evaluation team members and/or comments.
Procurement Type: RFP IFB
Justification (explain the rationale for using the particular procurement type):
An IFB approach is selected for this procurement as the nature of the requirements allows the lowest, responsive, and responsible bidder to be selected for award.
Evaluation Criteria:
PROPOSAL WEIGHT
Qualifications of the Firm N/A Staffing/Project Organization N/A Work Plan N/A Cost 100% Justification:
There are no required skills, qualifications, or detailed work plan necessary to complete this Scope of Work. The only criterion is cost as that will be the determining factor for the evaluation of this effort.
Contract Type: Time & Expense CTO-Based Firm Fixed Price
Justification (Explain the rationale for using the particular contract type):
A firm fixed price, blanket purchase order will be awarded. One-time fees (for each base) will be incurred for the scaffolding, installation/set-up, freight, training, and warranty.
Procurement Plan, IFB No. 250214
Retention: Yes % No N/A
Prevailing Wages: Yes $ No N/A
Liquidated Damages: Yes $ No N/A
Procurement Schedule: Attached
Contract Term: Two (2)-year term
Funding Source: Local Measure M Federal (FHWA)
Dollar Amount: $500,000 Option Term
Independent Cost Estimate Received: Yes No
Requisition Received: Yes, Req No. R001097 No
DBE Goal: Yes No
Project Manager Concurrence:
Eric Peterson, Supervisor, Transit Technical Services Date
CAMM Section Manager Concurrence:
Georgia Martinez, Department Manager, Contracts and Procurement Date