This is an interoffice memorandum from the Orange County Transportation Authority (OCTA) outlining the procurement timeline for RFP 250111, a feasibility study for the relocation of Newport Beach Fire Station No. 3 to the Newport Transportation Center and the relocation of the Newport Transportation Center to suitable alternative site(s). The RFP was issued on November 13, 2025, with public notices published on November 15 and 22, 2025. Written questions from proposers were due by November 25, 2025, with OCTA's responses provided by December 4, 2025. Proposals were submitted by December 17, 2025 at 2:00 p.m., followed by a pre-evaluation meeting on the same date. Proposal evaluation by the evaluation committee was scheduled for January 7, 2026, with interview notifications sent by January 14, 2026. Interviews were conducted on February 1, 2026, with contract execution following the selection process. The contract term is one year.
The project budget is $500,000 for the one-year feasibility study. This memorandum served as an internal coordination document from the Senior Contract Administrator to the Department Manager for Transit Planning to confirm the procurement schedule and timeline for contract release, selection, and award, allowing for any necessary adjustments to the stated dates prior to RFP issuance.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Newport_Transportation_Center_and_Fire_Station_No._3_Relocation_Feasibility_Study_(Addendum_#1_Revision).pdf | ||
| C250111_PP-APPROVED.pdf | ||
| C250111_Exhibit_C_Safety_Level_1.pdf | ||
| C250111_Exhibit_A_SOW.pdf | ||
| C250111_Exhibit_B_Proposed_Agreement.pdf | ||
| C250111_PP.pdf | ||
| [A]_C250111_Exhibit_A_SOW_idedits.docx | DOCX document | |
| [C]_C250111_Exhibit_C_Proposed_Agreement_idedits.docx | DOCX document | |
| [B]_C250111_Exhibit_B_Price_Summary_Sheet_idedits.docx | DOCX document | |
| C250111_PS_idedits.doc | DOC document | |
| C250111_PP_idedits.docx | DOCX document | |
| C250111_Public_Notice_Proof.pdf | ||
| C250111_Public_Notice.doc | DOC document | |
| C250111_SOW_Verification.pdf | ||
| C250111_R000882.pdf | ||
| C250111_PS.doc | DOC document | |
| C250111_ICE_R000882.pdf | ||
| C250111_Form_700_Legal_Counsel_Response_11-5-25.pdf |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Revised: 03/03/2010
INTEROFFICE MEMO
November 13, 2025
To: Katie Persons, Department Manager, Transit Planning
From: Gina Torres, Senior Contract Administrator, CAMM
Subject: Time Schedule for Release, Selection and Award
RFP 250111 "Newport Transportation Center and Fire Station No. 3 Relocation Feasibility Study"
Please review the time schedule for the subject RFP. If you have a problem with any of the dates or timelines let me know as soon as possible.
November 13, 2025 Issue RFP
November 15 and 22, 2025
Public Notice
November 25, 2025 Written questions due from proposers
December 4, 2025 OCTA’s response to proposers
December 17, 2025 Offers Submitted 2:00 p.m.
December 17, 2025 Pre-Evaluation Meeting
January 7, 2026 Evaluation Committee Reviews Proposals Send interview notification letters
January 14, 2026 Interviews
February 1, 2026 Contract Executed
Project Manager Concurrence:
Katie Persons, Department Manager, Transit Planning Date