C250082_PS_GMEDITS.doc
DOC document 44 KB Posted
- Solicitation number
- 250082
- Issued by
- Orange County, California
About this file
This is a procurement schedule document from the Orange County Transportation Authority (OCTA) outlining the timeline for IFB 250082, "Back-Up Generators and Uninterruptible Power Supply Equipment Service and Repairs." The IFB was issued on January 19, 2026, with advertisements running through January 26, 2026. Written questions from proposers were due by 5:00 p.m. on January 23, 2026, with OCTA's responses provided by January 28, 2026. Bids were due on February 16, 2026, at 11:00 a.m., and the blanket purchase order award was scheduled for February 26, 2026. The contract covers a three-year term for back-up generator and uninterruptible power supply equipment service and repair work.
The project budget is $290,000 for the entire three-year contract term. The document was prepared by Ellis Hoskin, Senior Contract Administrator at CAMM, and submitted to Christine Herrera, Contracts Analyst at Maintenance Resource Management, for review and concurrence on the procurement schedule. No specific set-asides, incumbent information, or additional funding sources are detailed in this schedule document.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
January 6, 2026 To:
Christine Herrera, Contracts Analyst, Maintenance Resource Management From:
Ellis Hoskin, Senior Contract Administrator, CAMM Subject:
Procurement Schedule for Release, Selection and Award
IFB - 250082 “Back-Up Generators and Uninterruptible Power Supply Equipment Service and Repairs”
Please review the time schedule for the subject IFB. If you have a problem with any of the dates or timelines let me know as soon as possible.
| January 19, 2026 |
| Issue IFB |
January 19, 2026 and January 26, 2026 Advertise
| January 23, 2026 |
| Written Questions Due from Proposers by 5:00 pm |
| January 28, 2026 |
| OCTA’s response to Proposers |
| February 16, 2026 |
| Bids Due – 11:00 a.m. |
| February 26, 2025 |
| Blanket Purchase Order Award |
Project Manager Concurrence:
Christine Herrera, Contracts Analyst, Maintenance Resource Management Date Revised: 3/20/2019