C250082_ICE.pdf

PDF 335 KB Posted

Attached to
Back-Up Generators and Uninterruptible Power Supply Equipment Service and Repairs
Solicitation number
250082
Issued by
Orange County, California

About this file

This is an Independent Cost Estimate (ICE) document prepared by the Orange County Transportation Authority (OCTA) for a procurement of back-up generators and uninterruptible power supply (UPS) equipment service and repairs. The project covers preventive maintenance and inspection (PMI) services and parts across six OCTA locations, including the addition of the OC Streetcar Maintenance and Storage Facility (MSF). The procurement constitutes a three-year contract replacement for the existing agreement C-23039, which expires February 28, 2026. The estimated contract term is through October 1, 2025, with services to be provided on an as-needed basis for repair labor in addition to scheduled preventive maintenance.

The total estimated cost for this procurement is $291,000 over the three-year period, consisting of $270,000 for PMI services and parts ($1,250 monthly per location multiplied by six locations over 36 months) and $21,000 for as-needed repair labor ($175 per hour at 40 hours annually). The estimate is based on historical usage data, anticipated labor and material rate increases, and increased repair requirements due to aging equipment. This ICE was prepared by Christine Herrera, Contracts Analyst, on October 1, 2025, and accompanies Purchase Requisition No. R000693 to be submitted to Contracts Administration & Materials Management (CAMM) along with the scope of work for procurement processing.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INDEPENDENT COST ESTIMATE (ICE)

FA-CAMM-006.docm (09/25/15) Page 1 of 3

INSTRUCTIONS

Complete and submit all three pages to Contracts Administration & Materials Management (CAMM), along with your requisition and scope of work. CAMM will not start the procurement until all three documents have been received.

PART I – GENERAL INFORMATION

Project Description: Back-up Generators and Uninterruptible Power Supply (UPS) Equipment Service and Repairs

SHADED AREA FOR PROCUREMENT USE ONLY

Assigned Buyer No.:

D/M/WBE%:

Purchase Requisition No.: R000693

New Contract / Procurement

Contract Amendment Current IFAS Printout Contract / PO No.: C-23039 (Required for Amendments)

Contract Task Order

Option Term

Date: 10/1/2025

Requestor: Christine Herrera Contracts Analyst Phone Ext.: 5485 Name Title

Signature:

Cost Estimate: $ 291,000.00 (include shipping, handling and taxes, if applicable)

PART II – ESTIMATE GUIDE

Please substantiate the estimate using the following information.

Estimate Type Items to Include Where to Find Supporting Information

Services (Other than A&E)

1. Tasks you want done

2. Types of people needed (i.e., supervisor, administrative assistant, other)

3. Positions required (i.e., Project Manager, Deputy PM, Senior Engineer / Planner, other)

4. Estimated hours by position

5. Salary / billing rates applied

6. Prevailing wage rate category applied

7. Profit / applied fee

8. Direct expenses

9. Completion schedule

1. Current or past contracts for similar services

2. Other properties / departments doing similar work

3. Historical price and cost data

Estimate Guide Continued

FA-CAMM-006.docm (09/25/15) Page 2 of 3

Estimate Type Items to Include Where to Find Supporting Information

Architects, Engineers, Designers

1. Tasks you want done

2. Types of people needed (i.e., engineers, administrative assistant, other)

3. Positions (Project Manager, Deputy PM, Senior Engineer / Planner, other)

4. Estimated hours by position

5. Salary / billing rates applied

6. Profit / applied fee

7. Overhead rate (%)

8. Direct expenses

9. Completion schedule

1. Current or past contracts for similar services

2. Other properties / departments doing similar work

3. Historical price and cost data

Goods/Equipment 1. Product needed

2. Quantity

3. Unit price

4. Markups, overhead, profit

5. Delivery schedule desired

6. Warranty

1. Vendor survey / market survey

2. Current or past contracts for the same or similar product

3. Historical price and cost data

4. Various published indices

Construction 1. Product needed

2. Labor (at a minimum use Davis Bacon)

3. Materials

4. Bonds

5. Insurance

6. Mobilization

7. Equipment

8. Markups, fringes, overheads, profit

9. Completion schedule

1. “Means Book”

2. “Blue Book”

3. Davis Bacon wage rates / prevailing wages

4. Current or past contracts for the same project

5. Historical price and cost data

Additional Information: This independent cost estimate is for a 3-year procurement replacing agreement C-23039 for Back-Up Generators and UPS Equipment Service and Repairs which expires 2/28/2026. Estimated costs are based on historical use, labor & material rate increases, and increased repairs due to aging equipment. This procurement will also cover the addition of the OC Streetcar MSF facility.

Average Monthly PMI = $1,250 x 6 locations = $7,500 x 36 months = $270,000 As-Need Labor = $175/hour x 40 hours/ year = $7,000 x 3 years = $21,000 Total Estimate: $291,000

FA-CAMM-006.docm (09/25/15) Page 3 of 3

PART III – INDEPENDENT COST ESTIMATE

Using the information provided in Part II, prepare the ICE for your procurement.

Use any or all of the categories listed below.

Prepared By: Christine Herrera Date: 10/1/2025

Signature:

DESCRIPTION OF COST ELEMENTS

1. DIRECT LABOR

(List of Labor Categories)

Estimated Hours

Rate Per Hour ($)

Estimated Cost ($)

Total Est.

Cost ($)

General As-Needed Repair Labor 120 $ 175.00 $ 21,000.00 $ $ 0.00 $ $ 0.00 $ $ 0.00 $ $ 0.00 $ $ 0.00

Total Direct Labor: $ 21,000.00

2. OVERHEAD

Rate (%)

(use decimal input)

Total Labor ($)

Estimated Cost ($)

Total Est.

Cost ($)

% $ 21,000.00 $ 0.00 $ 0.00

3. MATERIALS/SERVICES (Excluding Information Technology [IT]) Estimated Cost ($)

Total Est.

Cost ($)

Back-Up Generators and UPS Equipment PMI Service & Parts $ 270,000.00 $ 270,000.00

4. INFORMATION TECHNOLOGY SUPPORT Estimated Cost ($)

Total Est.

Cost ($)

Total IT Support: $ 0.00

5. TRAVEL Estimated Cost ($)

Total Est.

Cost ($)

$ $ 0.00

6. SUBCONTRACTOR(S) / CONSULTANT(S) Estimated Cost ($)

Total Est.

Cost ($)

Total Subcontractor(s) / Consultant(s): $ 0.00

7. OTHER DIRECT COSTS Estimated Cost ($)

Total Est.

Cost ($)

$ $ 0.00

8. TOTAL ESTIMATED COST: $ 291,000.00

File details come from the government source that posted it. Updated .