C1007021A Cofferdam Formal Work Package Requirements.pdf

PDF 394 KB Posted

Attached to
Underwater Hull Maintenance and Repair Services - Military Sealift Command
Solicitation number
N3220526R0002
Issued by

About this file

This is a Safety Management System Procedures Checklist for Cofferdam Formal Work Package Requirements used by Military Sealift Command (MSC) for government operations on ashore and afloat vessel repairs.

The checklist establishes comprehensive requirements for developing and approving formal work packages (FWPs) related to cofferdam installation and removal during ship repairs. The assigned contractor must develop the FWP with liaison support from the Principal Port Engineer (PPE), who provides required drawings and information. MSC N7 maintains an IDIQ Underwater Hull Cleaning Contract for these services. The checklist covers five major sections: Administrative Controls (ship name, hull number, contractor details, FWP identification); Purpose/Scope (process description, cofferdam type, affected hull openings and equipment); Personnel Qualifications (diver training, competency, engineering credentials, fabrication personnel); Safety Guidelines (PPE, emergency flooding plans, safety briefs, warning signs); and Cofferdam/Internal Blank Design (design specifications, supporting documentation, identification, templating, dimensions, materials, stiffeners, eductor systems, gasket design, positive securing devices, rigging plans, and internal sealing blank requirements). The checklist also addresses Preparation, Installation, and Removal phases, including inspection protocols, freeboard maintenance, hull opening location, surface preparation, leak rates, communications, dewatering procedures, and monitoring requirements. Approval responsibility is divided between Ship's Force (administrative and operational items) and N72 Technical personnel (engineering and technical design items), with escalation to MSC N721 Naval Architecture Department available when needed. The procedure maintains 180-day incident-free status requirement for engineering repairs, with one-year status if an incident occurs.

View the file

Other files

File Type Posted
Solicitation Amendment N3220526R00020003 SF 30.pdf PDF
RFP N3220526R0002 - Q AND A 8.19.26.pdf PDF
Attachment 1 - UWH IDIQ PERFORMANCE WORK STATEMENT (PWS) Rev. 2.pdf PDF
Solicitation Amendment N3220526R00020002 SF 30.pdf PDF
Solicitation Amendment - N3220526R00020002.pdf PDF
RFP N3220526R0002 - Q AND A 7.14.26.pdf PDF
RFP N3220526R0002 - Q AND A 7.10.26.pdf PDF
Ordering Period Three (Year 3) - Rev. 1.xlsx XLSX spreadsheet
Solicitation Amendment - N3220526R00020001.pdf PDF
Ordering Period Four (Year 4) - Rev. 1.xlsx XLSX spreadsheet
Exhibit A - CDRLs A001 - A011 Rev. 1.pdf PDF
Attachment 1 - UWH IDIQ PERFORMANCE WORK STATEMENT (PWS) Rev. 1.pdf PDF
Solicitation Amendment N3220526R00020001 SF 30.pdf PDF
Option Period (6-Month Option) - Rev. 1.xlsx XLSX spreadsheet
Ordering Period Five (Year 5) - Rev. 1.xlsx XLSX spreadsheet
Ordering Period Two (Year 2) - Rev. 1.xlsx XLSX spreadsheet
Ordering Period One (Year 1) - Rev. 1.xlsx XLSX spreadsheet
Attachment 7 - Ship Characteristics Rev. 1.pdf PDF
RFP N3220526R0002 - Q AND A 7.6.26.pdf PDF
RFP N3220526R0002 - Q AND A.pdf PDF
Solicitation - N3220526R0002.pdf PDF
P100702A Cofferdam and Freeboard Requirements for Ship Repairs_Redacted.pdf PDF
Option Period (6-Month Option) -.xlsx XLSX spreadsheet
Ordering Period Three (Year 3) -.xlsx XLSX spreadsheet
Ordering Period Two (Year 2) -.xlsx XLSX spreadsheet
Attachment 8 - Wage Determinations WD.pdf PDF
Attachment 4 - CORPORATE EXPERIENCE DATASHEET.pdf PDF
Attachment 3 - NON DISCLOSURE AGREEMENT.docx DOCX document
Ordering Period Five (Year 5) -.xlsx XLSX spreadsheet
Attachment 9 - GFP Attachment.xlsx XLSX spreadsheet
Attachment 6 - PERFORMANCE QUESTIONNAIRE.docx DOCX document
Attachment 5 - PAST PERFORMANCE DATA SHEET.docx DOCX document
Attachment 2 - Representation and Certification.pdf PDF
Summary Pricing Sheet -.xlsx XLSX spreadsheet
Exhibit A - CDRLs A001 - A011.pdf PDF
Attachment 7 - Ship charasteristics.pdf PDF
Attachment 1 - UWH IDIQ PERFORMANCE WORK STATEMENT (PWS).pdf PDF
Ordering Period Four (Year 4) -.xlsx XLSX spreadsheet
Ordering Period One (Year 1) -.xlsx XLSX spreadsheet
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Cofferdam Formal Work Package Requirements ASHORE and AFLOAT Responsibilities and Approval Authorities

Military Sealift Command, Government Operations Safety Management System Procedures Manual

Original 28 May 2025

Engineering Repairs End of evolution plus 180 days without incident

(1 year if incident occurs) Engineer’s Files

SMS Checklist 10.7-002-01-ALL “Cofferdam Formal Work Package Requirements” Page 1 of 15

Instructions

1. The Formal Work Package (FWP) must be developed by the assigned contractor. MSC N7 maintains an IDIQ Underwater Hull Cleaning Contract.

2. The Principal Port Engineer (PPE) is to liaise with the underwater-husbandry contractor, to provide required drawings, information, and details as needed for FWP development.

3. The “Responsible” party as dictated in the third column of this checklist denotes the party responsible for validating the requirement exists in the FWP and is technically satisfactory.

4. Each item reviewed must receive an initial in the “Approved” / “Not Approved” column. Rows that may not be applicable to the repair must be annotated with “N/A” or “Not Applicable.”

5. Reference 5.3, as used in this checklist, refers to reference 5.3 in SMS procedure 10.7-002-

ALL “Cofferdam and Freeboard requirements for Ship Repairs.” Reference 5.3 in SMS procedure 10.7-002-ALL is the “Underwater Ship Husbandry Manual.”

6. If there is any Criteria that the ship is responsible for approving that the ship is not confident in approving, the ship should forward the request for approval to MSC N721 Naval Architecture

Department.

Criteria Specific

Requirement Responsible Approved

Not Approved

1. Administrative Controls

1.1 Ship's Name Ship's Force

1.2 Ship's Hull Number Ship's Force

1.3 Contractor's Name Ship's Force

1.4 Contractor's Address Ship's Force

1.5 Work Item and Paragraph Ship's Force

1.6 FWP Title Ship's Force

1.7 FWP Number with Revision Ship's Force

1.8 Date of FWP Development Ship's Force

1.9 FWP Submission Date Ship's Force

1.10 FWP Creator's Name Ship's Force

1.11 Approval Signatures

SMS Form 10.7-002-02-

ALL

Ship's Force

2. Purpose / Scope

2.1 Describe the Process and:

(a) Type of Cofferdam Used

(b) Affected Hull Opening

(c) Affected Equipment / System

3. Personnel Qualifications

Military Sealift Command, Government Operations Safety Management System Procedures Manual

Original 28 May 2025

Engineering Repairs End of evolution plus 180 days without incident

(1 year if incident occurs)

SMS Checklist 10.7-002-01-ALL “Cofferdam Formal Work Package Requirements” Page 2 of 15

3.1 Diver Training Plan. Note: the

Diving Contractor's Training Plan & documentation complies with reference 5.3, 16-10.2.1 & 16-10.2.2

Reference 5.3 16-10.2.1 16-10.2.2 16-10.2.4 16-10.2.4.1 16-10.2.4.2 16-10.2.4.3

3.2 Diver Competency. Note the

Divers:

(a) Are ADCI recognized with 7 years (min) commercial diving experience

(b) Have current medical physical screening

(c) Have current CPR and First Aid Certification

(d) Have Cofferdam Program Certification

(e) Have performed six (6) (min) cofferdam installations

(f) Have performed a cofferdam installation within the last six (6) months

Reference 5.3 16-1.6 16-10.2.3.3.1 16-10.2.3.3.2 16-10.2.4.2.5 16-10.2.4.2.8

3.2.1 Minimum diver cofferdam

training requirements. Require the completion of reference 5.3, Appendix E demonstrating diver fundamental cofferdam knowledge.

Reference 5.3 16-5.2.20 16-10.2.2 16-10.2.3.3.4 Appendix E

3.3 Engineering. Specific NON-

standard cofferdam(s) were designed by a degreed Engineer or Professional Engineer.

Reference 5.3 16-3.11 16-10.2.3.1

N72 Technical

3.4 Fabrication Personnel. Note

contractor welders are qualified to company's approved welding procedure(s).

Reference 5.3 16-10.2.3.2 16-10.2.4.3

4. Safety Guidelines

4.1 Personnel protective gear. Note

the minimum required PPE will be used.

Military Sealift Command, Government Operations Safety Management System Procedures Manual

Original 28 May 2025

Engineering Repairs End of evolution plus 180 days without incident

(1 year if incident occurs)

SMS Checklist 10.7-002-01-ALL “Cofferdam Formal Work Package Requirements” Page 3 of 15

4.2 Emergency Flooding Plan.

Whenever single-valve protection is in place, include in the written notification to the ship a specific plan for immediate installation of a replacement piping component or internal sealing blank. Provide a note indicating that ship's force is responsible for developing an on-site emergency flooding plan (dewatering response), which includes additional emergency dewatering equipment that must be operationally ready before commencing work and available for the entire time single-valve protection is in place.

Reference 5.3 16-4.7.1.5 16-5.2.10 16-7.6.5 16-10.2.6 16-10.2.6.9

4.3 Joint Safety Brief. Note

participation in a pre-job Joint Safety Brief, if contractor attendance is required.

4.4 Posted safety precautions.

Warning signs. Specify and describe each of the following (figure, sketch, etc)

4.4.1 Warning sign posted at quarter

deck to space that contains the systems impacted by the FWP.

4.4.2 Warning sign posted at the

entrance(s) to the space that contains the systems impacted by the FWP.

4.4.3 Warning sign posted at the

seawater supply manifold (eductor) if applicable.

4.4.4 Warning sign at the deck edge

in way of cofferdam support rigging if applicable.

5. Cofferdam and Internal Blank Design

5.3 Cofferdam Design. Specify a

suitable capacity cofferdam, including:

Reference 5.3 16-3.7 16-3.8 16-10.2.4.5 1-7 Appendix C

Military Sealift Command, Government Operations Safety Management System Procedures Manual

Original 28 May 2025

Engineering Repairs End of evolution plus 180 days without incident

(1 year if incident occurs)

SMS Checklist 10.7-002-01-ALL “Cofferdam Formal Work Package Requirements” Page 4 of 15

5.3.1 Supporting Documentation.

Require design and maintenance records that comply with Reference 5.3, Paragraph 16-5.2.7 (patches), or 16-6.6.4 (dry-chambers), or 16-7.6.3 (stern tube seals), including as necessary:

(a) Fabrication Drawings

(b) Inspections

(c) Engineering Calculations

(d) Cofferdam rated depth

(e) Maximum hull opening size

(f) Gasket requirements

(g) Eductor and vent line requirements

(h) Patch specific hull opening

(i) Attachment and alignment procedures

(j) Maintenance records

Note:

(1) NAVSEA approved designs require calculations if the material is aluminum due to the change in requirements from the 2015 aluminum design standard to the 2020 aluminum design standard.

(2) Commercially procured plugs from an approved manufacturer do not require a design sketch.

Reference 5.3 16-3.7 16-5.2.7 16-5.2.8 16-6.6.4 16-6.7.4 16-7.6.3 16-10.2.4.5

5.3.2 Identification. Require an

installation data plate or engraved (or welded) serial number on cofferdams, corresponding to supporting documentation.

Reference 5.3 16-5.2.7 16-6.6.4 16-10.2.4.5

5.3.3 Templating. Note the cofferdam

is contoured to fit the hull curvature as necessary.

Reference 5.3 16-2.1.2.2 16-2.1.2.3 16-3.10 16-5.3.3 16-6.7.3 16-7.7.3 16-8.1 16-8.2 Appendix C

Military Sealift Command, Government Operations Safety Management System Procedures Manual

Original 28 May 2025

Engineering Repairs End of evolution plus 180 days without incident

(1 year if incident occurs)

SMS Checklist 10.7-002-01-ALL “Cofferdam Formal Work Package Requirements” Page 5 of 15

5.3.4 Overall Dimensions. Specify

the gross dimensions of the cofferdam.

Reference 5.3 16-10.2.4.5 16-3.8

5.3.5 Material Types and

Thicknesses. Specify the appropriate material types and thicknesses conforming to Reference 5.3, Section 9.

Reference 5.3 16-3.8 16-10.2.4.5

5.3.6 Stiffeners. Specify the size and

spacing of stiffeners, if applicable.

Reference 5.3 16-2.1.2.2 16-3.8 16-5.3.1 16-6.2 16-9.1.1.2 16-9.2.3.7 16-9.5.4

5.3.7 Eductor, Air Supply and Vent.

Specify:

(a) As necessary, attachment locations of the eductor, air supply and vent, including suction side closure valves. Note: All patch pipe nipples used to attach external vent lines must have valves installed to secure the space when dewatering is complete.

(b) As necessary, size and type of eductor, air supply and vent. Note:

External vent lines must be non-collapsible hoses.

(c) As necessary, that the cofferdam must be vented to atmosphere by an internal vent or an external non-collapsible vent line.

Note: When using an internal vent, communications must be established between topside and internal space workers to ensure that the internal vent valve is open prior to eductor operation.

(d) As necessary, that a vent line (internal or external) must be installed and opened before dewatering to prevent a vacuum and overloading the patch.

(e) As necessary, a caution tag on all internal vents stating: “EXTERNAL

Reference 5.3 16-3.8 16-3.9 16-5.2.2 16-

5.2.14 16-

5.3.4 16- 6.7.5 Appendix A

Military Sealift Command, Government Operations Safety Management System Procedures Manual

Original 28 May 2025

Engineering Repairs End of evolution plus 180 days without incident

(1 year if incident occurs)

SMS Checklist 10.7-002-01-ALL “Cofferdam Formal Work Package Requirements” Page 6 of 15

COFFERDAM VENT VALVE. IF

WATER PRESENT OR

PRESSURIZED AIR RELEASED

WHEN OPENED, TAKE ACTION TO

CONFIRM COFFERDAM

ADEQUACY."

5.3.8 Gasket Design. Require

gasket to be fabricated from ASTM D 1056-00 Type 2, Class B or C, Grade 1 or 2 closed cell foam and a minimum of 3 inches in width (complying with Reference 5.3, 16-9.3.1 or 16-9.3.2, as applicable).

Reference 5.3 16-3.8 16-5.2.3 16-9.3.1 16-10.2.4.5 Appendix A

5.3.9 Gasket Adhesive. Specify that

a marine grade adhesive was used to mount the gasket to the cofferdam flange.

Reference 5.3 16-5.3.1 Appendix A

5.3.10 Positive Securing Device

Design. Specify the method used to secure the cofferdam to the hull (e.g., J-bolt, hogging lines, etc.)

Reference 5.3 16-3.8 16-3.12 Appendix F

Military Sealift Command, Government Operations Safety Management System Procedures Manual

Original 28 May 2025

Engineering Repairs End of evolution plus 180 days without incident

(1 year if incident occurs)

SMS Checklist 10.7-002-01-ALL “Cofferdam Formal Work Package Requirements” Page 7 of 15

5.3.10.1. J-Bolt Minimum

Requirements. Refer to, and include, Reference 5.3, Appendix F if a j-bolt is used.

Reference 5.3 16-9.2.3.4 Appendix F

5.3.11. Mechanical Fasteners.

Specify the fastener type, as necessary.

Reference 5.3

16-3.8 16-9.4

5.2. Internal Sealing Blank Design

and Documentation. If an internal sealing blank is necessary, require the installation of a less than ½-inch vent valve in the blank and specify:

Note: Vent lines must be less than ½” IPS or else a temporary reducer must be installed to make the opening less than ½” IPS.

Reference 5.3 16-3.4.2.1.

(2) 16-4.7.1.1 16-4.7.1.2 16-4.7.1.5 16-5.2.1 16-5.2.2 App D: 2, 19

5.2.1. Blank conforms to Standard

DWG# 845 4612172(latest applicable revision).

Reference 5.3 3.9

5.2.2. Gasket conforms to MIL-PRF-

1149 (latest revision) or equivalent.

5.2.3. Fasteners conform to with

MIL-DTL-1222J or equivalent

5.2.4. Positive attachment of a

Danger Tag.

Reference 5.3 Appendix D

5.2.5. Require the blank to be

documented on a certified check-off sheet (Reference 5.3, Appendix D) verifying its installation and removal.

Reference 5.3 App D: 2, 19, 22, 23

Military Sealift Command, Government Operations Safety Management System Procedures Manual

Original 28 May 2025

Engineering Repairs End of evolution plus 180 days without incident

(1 year if incident occurs)

SMS Checklist 10.7-002-01-ALL “Cofferdam Formal Work Package Requirements” Page 8 of 15

5.3.Rigging Plan. Specify a rigging plan to positively secure the cofferdam to the hull, including, as necessary:

(a) Lifting requirements

(b) Suitable rigging equipment (e.g., chainfalls, turnbuckles, shackles, bellybands, hogging lines, chafing gear, counterweights)

(c) Securing and attachment requirements (e.g., padeye dimensions and locations) and consideration of rigging load requirements, per Reference 5.3, Section 9

(d) Manufacturer and weight testing requirements (Lifting Straps, Padeyes, Wire)

(e) Direction and magnitude of expected loads from installation, use, and removal of the cofferdam

(f) Rigging points and supporting structure designed with the factors of safety from Reference 5.3, Table 16- 6.

Note: If rigging to existing ship structure include the following statement: "All existing ship structure selected for rigging purposes, in accordance with this procedure, must be visually inspected, before its use, for any questionable indications that would appear to compromise its strength (e.g., cracks, unintentional holes, severe corrosion) or items or structure that appear insufficient to carry the intended load(s). This authorization is ONLY applicable to the installation and removal of the cofferdam of this procedure." If Contractor personnel are unclear or unsure as to whether an item is acceptable to rig from, contact the SUPERVISOR immediately for clarification / approval.

Reference 5.3

16-3.12 16-5.2.6 16-5.3.4 16-5.3.5 16-6.7.6 16-7.7.5

16-9.2.3.4 16-9.5.2 16-9.5.3

16-10.2.5.2 Appendix B Appendix F

5.4 Preparation

Military Sealift Command, Government Operations Safety Management System Procedures Manual

Original 28 May 2025

Engineering Repairs End of evolution plus 180 days without incident

(1 year if incident occurs)

SMS Checklist 10.7-002-01-ALL “Cofferdam Formal Work Package Requirements” Page 9 of 15

5.4.1. Patch and Plug Inspection.

Include Reference 5.3, Appendix C Patch and Plug Inspection Checksheet and require its completion confirming cofferdam inspection.

Reference 5.3 16-3.7.3. (b) 16-3.8. (7) 16-4.7.1.3 16-4.7.1.6 16-5.2.8 16-5.2.11 16-6.6.5 16-6.7.4 16-10.2.4.4 Appendix C

5.4.2. Freeboard. Note that

watertight integrity of 4-feet (MIN) above the maximum anticipated draft must be maintained.

F 5.4.3. Hull Opening or Access Cut Location. To locate cofferdam, specify, as necessary:

5.4.3.1. Hull Opening Item #.

Referenced on docking drawing.

5.4.3.2. Hull Opening Size.

Referenced on docking drawing.

5.4.3.3. Hull Fairing. Referenced on

docking drawing.

5.4.3.4. Hull Opening Strainer Bars.

Detailed on the seachest drawing and referenced on the piping drawing.

5.4.3.5. Access Cut. In lieu of hull

opening, detail the location and access cut size.

5.4.3.6. Surface Preparation. Inspect

and clean hull surfaces to obtain a 100% seal.

Reference 5.3 16-4.8.6 16-4.9.2 16-5.4.2 16-5.2.6 16-6.8.1 16-7.8.1 Appendix C

5.4.3.7. Sealing Surface, Hull. A 3-

inch minimum sealing surface on the hull around the opening to accommodate the minimum cofferdam gasket width.

Reference 5.3 16-9.3.1. (b) App D: 5

Military Sealift Command, Government Operations Safety Management System Procedures Manual

Original 28 May 2025

Engineering Repairs End of evolution plus 180 days without incident

(1 year if incident occurs)

SMS Checklist 10.7-002-01-ALL “Cofferdam Formal Work Package Requirements” Page 10 of 15

5.4.4. Briefing. Specify a method

ensuring cognizant personnel must have direct knowledge of the requirements before starting the process.

5.4.5. On-site Documentation.

Specify that the following on-site documentation must be available for the duration of the process, separately or as part of the PCP.

(a) Applicable System Drawings.

(b) Approved FWP

(c) Reference 5.3

(d) Applicable Standard Forms.

Including but not limited to, Reference 5.3, Appendices C, D and G, as necessary

(e) Rigging Plan

(f) Cofferdam Design Package

(g) Emergency Flooding Plan

(h) Diving Contractor’s Safe Practices Manual

(i) Docking Plan Drawing.

Reference 5.3 16-10.2.6

5.4.6. FWP Control. Specify a

method establishing administrative control of the authorized FWP for the duration of the process, including a record of the data demonstrating satisfactory completion of the procedure.

Note: This is normally accomplished by a First-Line Supervisor ensuring all personnel must maintain compliance with FWP requirements.

5.4.7. Notifications.

5.4.7.1. Government. Notify the Ship

of the start of the process.

Ship's force

Military Sealift Command, Government Operations Safety Management System Procedures Manual

Original 28 May 2025

Engineering Repairs End of evolution plus 180 days without incident

(1 year if incident occurs)

SMS Checklist 10.7-002-01-ALL “Cofferdam Formal Work Package Requirements” Page 11 of 15

5.4.7.2. Ship’s Force Notification of

Cofferdam Installation (Location) and Single Valve Protection. Include, and complete, as required, Reference 5.3, Appendix G Report of Ship’s Responsibility for Patch Installation and/or Single Valve Protection confirming the Ship’s Master or Designated Representative have been notified and acknowledge the cofferdam’s location (if installed) and level of valve protection. Note: Unlike single/double valve protection, weld repairs to the hull do not require App.

G as implied by Ref. 5.3, 16- 10.2.6.6.

Reference 5.3 16-4.7.1.3 16-4.7.1.4 16-5.2.1 16-5.2.2 16-5.2.9 16-5.2.10 16-6.6.10 16-7.6.5 16-7.6.6 16-10.2.6.6

5.4.8. Leak Rate. Specify an

appropriate leak rate.

Reference 5.3 16-4.7.1.8 16-5.2.17 16-6.6.8 16-7.6.8

5.4.9. Inspection Dive. Note a pre-

installation inspection dive must be accomplished verifying existing conditions.

Reference 5.3 16-3.6 16-7.7.4

5.4.10. Communications. Specify

mandatory two way communication (e.g., hand-held radio, sound powered telephone) between the Contractor (Surveillance Personnel) and Ship’s Force (Quarterdeck or Watch Station) for the duration of the process.

Reference 5.3 16-3.4.2.6 16-4.8.4 16-5.2.14 16-5.5.3 16-10.2.5.3 App D: 14,

5.4.11. Dewatering.

Military Sealift Command, Government Operations Safety Management System Procedures Manual

Original 28 May 2025

Engineering Repairs End of evolution plus 180 days without incident

(1 year if incident occurs)

SMS Checklist 10.7-002-01-ALL “Cofferdam Formal Work Package Requirements” Page 12 of 15

5.4.11.1. Dewatering. If necessary, require installation, tagging (as required) and inspection of all vent lines, eductors and air supply lines (dry chambers), in accordance with Reference 5.3, Appendix D, as necessary.

Reference 5.3 16-5.2.2 16-5.2.14 16-5.2.15 16-5.2.18.1 16-5.2.18.2 16-5.3.4 16-6.6.7 16-6.7.5 16-7.6.6

5.4.11.2. Pumping, Seawater Supply.

If necessary, require maintenance of a seawater supply (supply valve wired open and either a backup fire pump or secondary fire main).

5.4.12. Operational Compliance

Check-List. Include, and complete, the Operational Check-List, Reference 5.3, Table 16-9.

Reference 5.3 16-10.3.1

5.5. INSTALLATION.

5.5.3. Installation Checksheet.

Include Reference 5.3, Appendix D Patch and Plug Installation Check sheet and complete only those steps pertaining to cofferdam installation.

Reference 5.3 16-3.13 16-4.7.1.3 16-4.7.1.9 16-5.2.11 16-5.2.19

5.5.2. Verify System and Hull

Opening. Verify the removed valve or system corresponds to the system blanked and the hull opening.

Reference 5.3 16-5.4.1

5.5.3. Locate and Position

Cofferdam. Require:

(a) Cofferdam to be located in conjunction with the Rigging Plan and Inspection Dive.

(b) A 4-foot minimum freeboard

(c) A 6-inch minimum clearance between the cofferdam side and hot work area, if applicable. If the 6-inch minimum clearance cannot be maintained provide written justification.

Reference 5.3 3.6 3.12 5.3.5 6.7.6 7.7.5 App C: 1b, 1c App D: 1

Military Sealift Command, Government Operations Safety Management System Procedures Manual

Original 28 May 2025

Engineering Repairs End of evolution plus 180 days without incident

(1 year if incident occurs)

SMS Checklist 10.7-002-01-ALL “Cofferdam Formal Work Package Requirements” Page 13 of 15

5.5.4. Verify Cofferdam Seal

(Watertight Integrity). Require Divers to verify cofferdam’s watertight integrity, and, if necessary, retightening of the primary means of cofferdam attachment to establish a watertight seal.

Reference 5.3

5.5.4.1. Notification of Cofferdam

Seal. Require Lead Shop notification that a seal has been established.

Reference 5.3

5.5.5. Internal Seal Blank. If

necessary, require:

(a) The installation of an internal seal blank, conforming to the specified design requirements, immediately after removal of the damaged (or repair) component (internal piping or watertight boundary is opened) to maintain double-valve protection.

(b) The Contractors to confirm that an internal seal blank with a less than ½” diameter vent valve has been installed immediately after removal of the damaged (or repair) component.

Reference 5.3 16-3.4.2.1.

(2) 16-4.7.1.1 16-4.7.1.2 16-4.7.1.5 16-5.2.1 16-5.2.2 App D: 2, 19

5.5.6. Test & Inspection Plan;

Acceptance & Rejection Criteria.

Include a Test & Inspection Plan denoting the relevant acceptance and rejection criteria.

5.5.7. Monitoring. Require cognizant

personnel (e.g., Divers or Ship’s Force) to monitor watertight integrity of all applicable cofferdams (with dewatering equipment secured) while actually providing single or double-valve protection at intervals no greater than every 7 days for patches and continuously for dry chambers (when occupied).

Note 1: The vent valve on internal seal blanks facilitates internal vent cofferdam monitoring.

Note 2: The blank vent valve may be left shut when not temporarily opened by the ship's sounding and security detail for patch or plug seal monitoring or, upon approval by the Ship, the blank vent valve may be

Reference 5.3 16-3.4.2.5(4) 16-5.2.2 16-5.2.18 16-6.6.9 16-6.7.2 16-7.7.2 Appendix D:

Appendix G

Military Sealift Command, Government Operations Safety Management System Procedures Manual

Original 28 May 2025

Engineering Repairs End of evolution plus 180 days without incident

(1 year if incident occurs)

SMS Checklist 10.7-002-01-ALL “Cofferdam Formal Work Package Requirements” Page 14 of 15 left continuously open to maintain cofferdam differential pressure.

5.6.REMOVAL.

5.6.1. Removal Checklist. Remove

cofferdam and complete those remaining steps in Reference 5.3, Appendix D Patch and Plug Installation Checksheet applicable to the removal phase of the cofferdam procedure.

Reference 5.3 16-3.13 16-4.7.1.3 16-4.7.1.9 4.8.1 4.9.7 16-5.2.11 16-5.2.19 5.5 7.9

5.6.2. Removal/Installation

Equipment, On-site. Equipment to move/manipulate the component must be available on-site.

5.6.3. Cofferdam Seal Verification.

Either open the ½-inch vent valve or loosen blank fasteners to slightly spread (open) the seal and verify the cofferdam is holding back sea pressure. If leakage exists correct cofferdam seal.

Reference 5.3 16-4.8.9 16-4.8.10 16-5.5.3

5.6.4. Internal Sealing Blank.

Remove internal sealing blank and retain on-site for immediate installation, if necessary.

Reference 5.3

Military Sealift Command, Government Operations Safety Management System Procedures Manual

Original 28 May 2025

Engineering Repairs End of evolution plus 180 days without incident

(1 year if incident occurs)

SMS Checklist 10.7-002-01-ALL “Cofferdam Formal Work Package Requirements” Page 15 of 15

5.6.5. Double Valve Protection.

Verify reestablishment of double-valve protection after component has been installed and 24-hour surveillance or diver stand by for single-valve protection is no longer required.

Reference 5.3

5.6.6. Divers Stand-By, Removal.

Require Divers to be on stand-by during removal of internal blank and re/installation of component.

Reference 5.3

5.6.7. Verify System Integrity.

Require loosening of cofferdam after the component is installed to verify the flange seal is tight (zero leaks) and, if not, the Divers must retighten the cofferdam to reestablish watertight integrity of the component.

When seal is verified, remove the cofferdam.

Reference 5.3

Note:

Non-standard cofferdams are cofferdams other than those provided by Reference 5.3, Section 9.

File details come from the government source that posted it. Updated .