Bridge Inspection Rpt_5460-001P-2022.pdf
PDF 2 MB Posted
- Attached to
- Great Smoky Mountains National Park
- Solicitation number
- 693C73-23-R-000019
About this file
This bridge inspection report summarizes the condition of the West Prong Little Pigeon River bridge located in the Great Smoky Mountains National Park. The 164-foot long, three-span concrete arch bridge was built in 1937 and last inspected on May 9, 2022. The bridge carries Newfound Gap Road over the West Prong Little Pigeon River.
The report identifies various maintenance and rehabilitation needs including cleaning and resealing expansion joints, sealing cracks in the arch underside, resetting loose coping stones, and removing vegetation from parapets and wingwalls. Estimated preliminary costs are $2,000 for maintenance and $40,000 for rehabilitation. The bridge's structural evaluation summary rates its superstructure as fair to good condition overall, with priority of improvement classified as minor. Several photographs document deficiencies such as cracking of the asphalt wearing surface and deterioration of parapet joints requiring repair.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BRIDGE INSPECTION REPORT
WEST PRONG LPR BRIDGE AT HEADQUARTERS
NEWFOUND GAP ROAD OVER WEST PRONG LITTLE PIGEON RIVER
GREAT SMOKY MOUNTAINS NATIONAL PARK
LN
STRUCTURE NO. 5460-001P
INSPECTION TYPE: ROUTINE
INSPECTION DATE: 5/9/2022
EU
Report prepared by:
Federal Highway Administration Federal Lands Bridge Office Bridge Inspection and Management Program 21400 Ridgetop Circle Sterling, Virginia 20166 https://bridge.flhd.fhwa.dot.gov
STRUCTURE SUMMARY STRUCTURE NO. 5460-001P
WEST PRONG LPR BRIDGE AT INSPECTION DATE: 05/09/2022
HEADQUARTERS
BRIDGE IDENTIFICATION AND DESCRIPTION
MAIN SPAN MATERIAL:
MAIN SPAN TYPE:
# OF BEAMS, MAIN SPAN: .
DECK TYPE:
WEARING SURFACE:
ABUT. FOUNDATIONS:
PIER FOUDNATION(S):
ABUTMENT / PIER MAT'L: ..
PROJ./PLAN REF. NO:
NPS ROAD CLASS:
STRUCTURE HISTORY:
2 - CONCRETE CONTINUOUS
11 - ARCH - DECK
N - NOT APPLICABLE
N - NA
2 - SPREAD FTG ON BEARING MAT'L
2 - SPREAD FTG ON BEARING MAT'L
1 - CONCRETE
1A4
1 - PRINCIPAL PARK ROAD
2012 (EST.) - ROADWAY REPAVED.
LOCATION
NO. OF MAIN SPANS:
NO. OF APPR. SPANS:
STRUCT. TOTAL LENGTH: .
MAX. SPAN LENGTH:
DECK WIDTH:
CURB TO CURB WIDTH:
YEAR BUILT:
YEAR RECONSTRUCTED: .
SKEW ANGLE:
FRACTURE CRITICAL:
164.0 FT (50 M)
48 FT (14.6 M)
41.3 FT (12.6 M)
37.3 FT (11.4 M)
0 °
N
GREAT SMOKY MOUNTAINS NATIONAL PARK MILE POINT: .. 1.50 (KM PT 2.41)
STATE: .............................. 474 - TENNESSEE LOCATION: .... 13.0 MILES NORTHWEST FROM
NEWFOUND GAP.FACILITY CARRIED: ......... NEWFOUND GAP ROAD
FEATURE INTERSECTED: WEST PRONG LITTLE PIGEON
INSPECTION TEAM: O. Tariq, J. Valcheff
CONDITION ASSESSMENT:
Osama Tariq
REPORT REVIEW:
Zane Bailey 703-404-6242
REPORT APPROVAL: Date: 10/26/2022
Jorgomai Ceesay
STRUCTURE EVALUATION SUMMARY
This concrete arch bridge is in fair to good structural condition overall. Problems include deterioration of the vertical joint filler material with vegetation growth, a loose coping stone at the end of the northeast wingwall, undermining of the downstream apron at the south pier, and missing object markers at the ends of the parapets.
Other problems include cracking throughout the asphalt pavement over the structure and approaches, cracking of the arch underside with efflorescence, vegetation growth along the wingwalls, erosion at the west end of the north pier and south abutment, and accumulation of drift in center span.
The Structure Evaluation Summary continues on the following page.
STRUCTURE SUMMARY STRUCTURE NO. 5460-001P
WEST PRONG LPR BRIDGE AT INSPECTION DATE: 05/09/2022
HEADQUARTERS
It should be noted that the loose coping stone at the northwest wingwall has been reset since the last inspection.
Corrective measures should be taken as outlined in this report to help prevent the possible development of more serious or costly problems in the future.
RECOMMENDATIONS AND ESTIMATED COSTS STRUCTURE NO. 5460-001P
WEST PRONG LPR BRIDGE AT HEADQUARTERS INSPECTION DATE : 05/09/2022
226 PRIORITY OF IMPROVEMENT D
A (Critical) - Structure is closed, in immediate damage of collapse, or presents a critical safety danger.
B (Major) - Structure is seriously deficient or presents a safety hazard, but can remain open at reduced loads or with frequent inspections.
C (Moderate) - Structure is deficient, functionally obsolete, or requires substantial repairs to prevent a serious deficiency or unsafe condition.
D (Minor) - Structure is generally in good condition. Preventive maintenance may be required.
E (Special) - Structure is under construction or reconstruction.
Item No.
Maintenance Recommendations
(GENERALLY NOT FLHP ELIGIBLE)
QTY. UNIT UNIT
COST
PRELIM.
COST
ESTIMATE
58.6,60.6 REMOVE VEGETATION FROM PARAPETS AND ALONG
WINGWALLS. 1 LS 1000 1000
222.7 INSTALL TYPE 3 REFLECTIVE OBJECT MARKERS AT ENDS
OF PARAPETS. 1 LS 1000 1000
PRELIM. MAINTENANCE TOTAL : 2000
Item REHABILITATION/RECONSTRUCTION
UNIT
UNIT PRELIM. COST ESTIMATES
No. (TYPICALLY NEEDED WITHIN 5 YEARS)
QTY. COST
REHAB RECONSTR
58.6,60.8 CLEAN AND RESEAL VERTICAL EXPANSION
JOINTS. 1 LS 15000 15000
59.3 CLEAN AND SEAL CRACKS ON ARCH
UNDERSIDE AS NECESSARY. 1 LS 5000 5000
60.6 RESET LOOSE COPING STONE AT END OF
NORTHEAST WINGWALL. 1 LS 4000 4000
CONTRACT COSTS FOR MOBILIZATION,
TRAFFIC CONTROL, AND CONTINGENCIES. 1 LS 16000 16000
PRELIM. REHABILITATION/RECONSTRUCTION TOTAL : 40000
1 LS 1000 1000
1 LS 1000 1000
1 LS 15000 15000
1 LS 5000 5000
1 LS 4000 4000
1 LS 16000 16000
40000
RECOMMENDATIONS AND ESTIMATED COSTS STRUCTURE NO. 5460-001P
WEST PRONG LPR BRIDGE AT HEADQUARTERS INSPECTION DATE : 05/09/2022
226 PRIORITY OF IMPROVEMENT D
A (Critical) - Structure is closed, in immediate damage of collapse, or presents a critical safety danger.
B (Major) - Structure is seriously deficient or presents a safety hazard, but can remain open at reduced loads or with frequent inspections.
C (Moderate) - Structure is deficient, functionally obsolete, or requires substantial repairs to prevent a serious deficiency or unsafe condition.
D (Minor) - Structure is generally in good condition. Preventive maintenance may be required.
E (Special) - Structure is under construction or reconstruction.
COST ESTIMATE SUMMARY
PRELIM. MAINTENANCE TOTAL :
PRELIM. REHABILITATION TOTAL :
PRELIM. RECONSTRUCTION TOTAL : .. 0
42000TOTAL ITEMIZED COSTS:
PRELIMINARY ESTIMATE TOTAL * :
(*Includes typical contract costs for mobilization, traffic control and design/construction engineering: but does not include detour bridges, work beyond the bridge limits, or work not listed above. Estimates are approximate and are for planning purposes only; they should not be used as a complete or final engineers estimate.)
Remarks : Cost estimates assume that recommended actions will be combined with similar work being performed on other structures.
420002000
40000
42000
STRUCTURE NO. 5460-001P
WEST PRONG LPR BRIDGE AT HEADQUARTERS INSPECTION DATE: 05/08/2022
1. DECK SLAB
4. RIDEABILITY
5. CURBS, SIDEWALKS, AND MEDIAN
6. PARAPETS AND/OR RAILINGS
7. DRAINS AND DRAINAGE
8. UTILITIES
9. DEFLECTION AND/OR VIBRATION
N
10.OTHER:
1. BEARING DEVICES
2. GIRDERS OR BEAMS
3. ARCH(ES) OR SLAB(S)
4. FLOOR BEAMS AND STRINGERS
5. TRUSSES
6. DIAPHRAGMS AND BRACING
7. PAINT
8. FASCIA(E)
9. DEFLECTION AND/OR VIBRATION
10.ALIGNMENT
11.OTHER
1. ALIGNMENT
2. EROSION AND/OR SCOUR
3. CHANNEL PROTECTION
4. WATERWAY OBSTRUCTIONS
5. OTHER
6. ADEQUACY OF OPENING
7. NORMAL VELOCITY
8. AVERAGE CLEAR OPENING
9. STREAMBED COMPOSITION:
1. APPROACH SLABS
2. RELIEF JOINTS
3. APPROACH GUARDRAIL
4. SURFACING
5. EROSION
6. SETTLEMENT
7. SIGNS
8. ALIGNMENT
9. OTHER
1. WALL
2. WEEP HOLES
3. FOUNDATION
4. EROSION AND/OR SCOUR
5. SETTLEMENT OR DEFLECTION
6. OTHER
N
G
N
G
G
N
N
N
N
F
N
N
N
N
G
G
G
N
F
F
G
F
F
1- SUFF
2 - MED
N
N
N
G
G
G
G
N
N
2. EXPANSION JOINTS N
3. WEARING SURFACE F
N
FLOOD GAUGE
8 FT
G
NOT APPLICABLEN
EXCELLENT CONDITION9
VERY GOOD CONDITION - no problems noted.8
GOOD CONDITION - some minor problems.7
SATISFACTORY CONDITION - structural elements show some minor deterioration.6
FA R CONDITION - all primary structural elements are sound but may have minor section loss, cracking, spalling, or scour.
POOR CONDITION - advanced section loss, deterioration, spalling, or scour.4
SERIOUS CONDITION - loss of section, deterioration, spalling, or scour have seriously affected primary structural components. Local failures are possible. Fatigue cracks in steel or shear cracks in concrete may be present.
CRITICAL CONDITION - advanced deterioration of primary structural elements. Fatigue cracks in steel or shear cracks in concrete may be present or scour may have removed substructure support. Unless closely monitored it may be necessary to close the structure until corrective action can be taken.
MM NENT FA LURE CONDITION - major deterioration or section loss present in critical structural components or obvious vertical or horizontal movement affecting structure stability.
Structure is closed to
FA LED CONDITION - out of service; beyond corrective action. 0
STONES
1. BREASTWALLS OR COLUMNS G
2. PILE BENTS N
3. CAPS AND/OR BEARING SEATS N
4. BACKWALLS AND/OR BULKHEADS N
5. FOUNDATIONS N
6. WINGWALLS G
7. WEEP HOLES G
8. EXPANSION JOINTS P
9. EROSION AND/OR SCOUR F
10.SETTLEMENT OR DEFLECTION G
11.SLOPE PROTECTION N
12.OTHER N
A. BRIDGE RAILINGS:
B. TRANSITIONS:
C. APPROACH GUARDRAILS:
D. APPROACH GUARDRAIL ENDS:
N
N
N
13. WALLS AND/OR COLUMNS
14.PILE BENTS
15.CAPS AND/OR BEARING SEATS
16.FOUNDATIONS
17.EROSION AND/OR SCOUR
18.SETTLEMENT OR DEFLECTION
19.OTHER STONE APRON
G
N
N
N
F
G
G
0 - Does not meet standards or a safety features is required and none is provided.
1 - Meets currently acceptable standards.
N - Not applicable or a safety features is not required.
58.3
222.4
MINOR LONGITUDINAL AND TRANSVERSE CRACKING OF ASPHALT OVER STRUCTURE AND APPROACHES.
58.6 MINOR CRACKING OF PARAPET MASONRY MORTAR JOINTS; MINOR EFFLORESCENCE ON STONES. MODERATE VEGETATION GROWTH ON PARAPETS. SEVERE DETERIORATION OF FILLER MATERIAL IN VERTICAL EXPANSION JOINTS ON PARAPETS.
59.3
59.8
MINOR LONGITUDINAL AND TRANSVERSE CRACKING OF ARCH UNDERSIDE WITH MINOR TO MODERATE EFFLORESCENCE.
MINOR HONEYCOMBING ON ARCH UNDERSIDE. MINOR LEAKAGE THROUGH CENTER SPAN ARCH, EAST SIDE, NEAR SOUTH PIER.
EXPOSED REBAR (2"L) ON ARCH UNDERSIDE ON EAST SIDE OF CENTER SPAN.
MODERATE EFFLORESCENCE ON RING STONES AND ON SPANDRESL WALLS.
60.1
60.6
MODERATE EFFLORESCENCE FROM RING STONES ON ENDS OF ABUTMENT BREASTWALL MASONRY.
MODERATE TO HEAVY VEGETATION GROWTH ALONG WINGWALLS. ONE LOOSE COPING STONE AT END OF NORTHWEST WINGWALL HAS BEEN RESET SINCE LAST INSPECTION. ONE LOOSE STONE AT END OF NORTHEAST WINGWALL. MODERATE
DETERIORATION OF WINGWALL MASONRY MORTAR JOINTS WITH EFFLORESCENCE.
60.8 SEVERE DETERIORATION OF FILLER MATERIAL AND MODERATE VINE GROWTH IN VERTICAL EXPANSION JOINTS WITH MODERATE VINE GROWTH; TREE GROWING FROM VERTICAL JOINT ON BOTH SIDES OF NORTH PIER.
60.9 MODERATE EROSION (10'L X 6'W X 3'D) AT WEST END OF SOUTH ABUTMENT BREASTWALL.
60.17
60.19
61.1
61.2
61.4
HEAVY BUILD-UP OF STONES AND SOIL IN NORTH AND CENTER SPANS; FLOW IS THROUGH SOUTH SPAN AGAINST SOUTH PIER.
MODERATE SCOUR ALONG SOUTH PIER EXPOSING APRON; UNABLE TO VERIFY PREVIOUSLY NOTED UNDERMINING DUE TO
HIGH FLOW.
MODERATE EROSION (20'L X 10'W X 3'D) AT WEST END OF NORTH PIER.
SEVERAL FALLEN TREES ON WEST SIDE OF NORTH SPAN. MODERATE ACCUMULATION OF DRIFT IN CENTER SPAN.
61.2 SEE BRIDGE FILE FOR SCOUR EVALUATION.
61.5 FLOOD GAUGE ATTACHED TO SOUTH ABUTMENT, EAST SIDE. CONDUIT IS LOOSE; INSULATION WRAPPING AROUND CONDUIT
HAS COME OFF.
222.5 MINOR EROSION ALONG NORTHWEST PARAPET.
222.7 TYPE 3 REFLECTIVE OBJECT MARKERS MISSING AT NORTHEAST, NORTHWEST, AND SOUTHWEST PARAPET ENDS.
H 15 14 25 23
HS 19 17 32 29
TYPE 3 17 15 29 26
TYPE 3S2 28 25 47 43
TYPE 3-3 33 30 56 51
2 - H 15
X CAPACITY MEETS OR EXCEEDS DESIGN LOAD
CAPACITY IS LESS THAN DESIGN LOAD
ORIGINAL LOAD RATING CALCULATION APPLICABLE
ORIGINAL LOAD RATING CALCULATION REVISED
06/20/2019
SEE BRIDGE FILE FOR LOAD RATING CALCULATIONS.
WEST PRONG LPR BR DGE AT HEADQUARTERS INSPECTION DATE: 05/08/2022
(201) PARK: GREAT SMOKY MOUNTAINS NATIONAL PARK
(202) STRUCTURE NAME:..............WEST PRONG LPR BRIDGE AT
HEADQUARTERS
(203) STRUCTURE KIND:............... 1 - BRIDGE
(204) STRUCTURE NUMBER:.........5460-001 P
4 - SOUTHEAST(205) NPS REGION:
(206) ROUTE CODE NUMBER:
(207) ROAD SECTION NO:............. 001P
(208) NPS ROAD CLASS:............... 1 - PRINCIPAL PARK ROAD
(209) WITHIN NPS BNDRY?:.......... Yes
(210) OPERATING UNIT:.................N. DIST.
(211) PROJECT NO(S):................... 1A4
(212) DRAWING NUMBERS:...........1120C
(21) MAINTAINED BY:......................66 - NATIONAL PARK SERVICE
(22) OWNER:................................... 66 - NATIONAL PARK SERVICE
(1) STATE:
(2) STATE HWY. AGENCY DIST:
(3) COUNTY CODE:
(4) CITY / PLACE CODE:
(5) INVENTORY ROUTE:
(6) FEATURES INTERSECTED:
(7) FACILITY CARRIED:
(8) STATE STRUCTURE NO:
(9) LOCATION:
(10) INV. RTE. - MIN. VERT. CLR:
(11) MILE POINT:
(27) YEAR BUILT:
(106) YEAR RECONSTRUCTED:
(20) TOLL:
(37) HISTORIC DESIGNATION:
474 - TENNESSEE
47155 SEVIER
00000
1 6 7 00010 0
WEST PRONG LITTLE PIGEON RIVER
NEWFOUND GAP ROAD
5460001P0000000
13.0 MILES NORTHWEST FROM
NEWFOUND GAP.
99.99 FT ( 99.99 M)
1 50 (KM PT: 2.41 )
3 - ON FREE ROAD
3 - MAY BE ELIGIBLE FOR NATIONAL
REGISTER
(43A) MAIN STR. MATERIAL:..........2 - CONCRETE CONTINUOUS (44A) APPR. STR. MATERIAL:............ 0 - Other
(43B) MAIN STR. TYPE:.................. 11 - ARCH - DECK (44B) APPR. STR. TYPE:.................... 00 - OTHER
(45) NO. OF MAIN SPANS:..............003 (46) NO OF APPROACH SPANS:
(48) MAX. SPAN LENGTH:..............48 FT ( 14.6 M)
(49) STRUCTURE LENGTH:........... 164. FT ( 50 M) (108) WEAR SURFACE/PROTECT SYSTEM:
(216A) ABUTMENT #1 FDN:........... 2 - SPREAD FTG ON BEARING MAT'L A) TYPE WEARING SURFACE:.. N - NA
(216B) ABUTMENT #2 FDN:........... 2 - SPREAD FTG ON BEARING MAT'L B) TYPE MEMBRANE:................. N - NA
(217A) PREDOM. PIER FDN:.......... 2 - SPREAD FTG ON BEARING MAT'L C) TYPE PROTECTION:.............. N - NA
(217B) SECOND. PIER FDN:.......... 2 - SPREAD FTG ON BEARING MAT'L (218) IS SALT USED?.......................... YES
(107) DECK TYPE:.......................... N - NOT APPLICABLE
(31) DESIGN LOAD:.........................2 - H 15 (41) LOAD RESTRICTION:.................. A - OPEN
(66) INVENTORY RATING:..............19.0 METRIC TONS) (70) BRIDGE POSTING:...................... 5 - EQUAL TO OR ABOVE LEGALTONS ( 17.2
LOADS
(64) OPERATING RATING:..............32.0 TONS ( 29 METRIC TONS)
(90) INSPECTION DATE: 05/09/2022 (91) FREQ. OF INSP: 24 MONTHS (92 / 93) CRITICAL FEATURE INSPECTION (CFI):
(219) ADD. STUDIES NEEDED: N - 0 - NONE (A) FRACTURE CRITICAL:.......... N
(220) SPECIAL STUDY TYPE: 0 - NONE INSP. EVERY MONTHS - LAST INSP:
(221) SPECIAL STUDY DATE: (B) UNDERWATER:..................... N
INSP. EVERY MONTHS - LAST INSP:
(C) SPECIAL INSPECTION:........ N
INSP. EVERY MONTHS - LAST INSP:
WEST PRONG LPR BR DGE AT HEADQUARTERS INSPECTION DATE: 05/08/2022
(16) LATITUDE:................................ 35 41' 15.1" N (51) CURB TO CURB WIDTH:............ 37.3 FT ( 11.4 M)
(17) LONGITUDE:............................ 83 32 ' 07.6" W (52) DECK WIDTH:.......................... 41.3 FT ( 12.6 M)
(19) DETOUR LENGTH:.................. 90 MI ( 145 KM) (32) APPR. ROADWAY WIDTH:...... 44.5 FT ( 13.6 M)
(28A) LANES ON STRUCT:.............02 (213) APPR. PAVEMENT WIDTH:... 29.5 FT ( 9 M)
(28B) LANES UNDER STRUCT:......00 LEFT SHOULDER:............... 7 0 FT ( 2.1 M)
(42A) SERVICE ON:.........................5 - HIGHWAY-PEDESTRIAN RIGHT SHOULDER:.......... 8 0 FT ( 2.4 M)
(42B) SERVICE UNDER:................. 5 - WATERWAY (33) BRIDGE MEDIAN:.................... 0 - NO MEDIAN
(29) AVG DAILY TRAFFIC:..............7265 (34) SKEW ANGLE:
(30) YEAR OF ADT:......................... 2019 (35) STRUCTURE FLARED:............ 0 - NO FLARE
(114) FUTURE ADT:.........................7990 (47) TOTAL HORIZ. CLEARANCE:.. 37.3 FT ( 11.4 M)
(115) YEAR OF FUTURE ADT:........2039 (50) SIDEWALKS
(101) PARALLEL STRUCTURE:......N - NO PARALLEL STRUCTURE LEFT:.................................... 0 0 FT ( 0 M)
(38) NAVIGATION CONTROL:.........0 - NO NAVIGATION CONTROL ON RIGHT:.................................. 0 0 FT ( 0 M)
WATERWAY (BRIDGE PERMIT NOT
REQUIRED)
(39) VERTICAL CLEARANCE:.........0.0 FT ( 0 M) (214) BRIDGE RAIL TYPE
3 - PARAPET ONLY(40) HORIZ. CLEARANCE:..............0.0 FT ( 0 M) RAIL CONFIGURATION:
(111) ABUT OR PIER PROT:........... MATERIAL:........................... 9 - OTHER
LATERAL UNDERCLEARANCE: DESIGN TYPE:..................... 1 - CONTINUOUS RAIL
(55) RIGHT:..............................0.0 FT ( 0 M) (215) BRIDGE RAIL HEIGHT:.......... 2.67 FT ( 0 81 M)
(56) LEFT:................................ 0.0 FT ( 0 M) (53) MIN. VRT. CLR. OVER DECK: 99.99 FT ( 99.99 M)
(54) MIN. VRT. UNDRCLRANCE:... .00 FT ( 0 M)
(58) DECK:.......................................N (67) STRUCTURAL EVALUATION:
(59) SUPERSTRUCTURE:...............6 (68) DECK GEOMETRY:
(60) SUBSTRUCTURE:.......... 7 (69) UNDERCLEARANCES:................ N
(61) CHANNEL:................................6 (71) WATERWAY ADEQUACY:
(62) CULVERT:.................................N (72) APPROACH ALIGNMENT:
(222) APPROACHES:...................... 7 (113) SCOUR CRITICAL:.................... 5 - SCOUR WITHIN LIMITS OF
FOOTING OR PILES
(223) RETAINING WALL:.................N (225) PURPOSE OF IMPROVEMENT: 2 - REHAB/RECONSTRUCTION
(36) TRAFFIC SAFETY FEAT: 1 N N N (226) PRIORITY OF IMPROVEMENT: D - MINOR
(75A) TYPE OF WORK:................... (227) MAINTENANCE COST:.............$ 2000
(75B) WORK DONE BY:.................. (228) REHAB / RECNSTR COST:..... $ 40000
(76) IMPROVEMENT LENGTH:....... FT ( 0 M) (229) CONSTRUCTION COST:.......... $ 0
(230) STRUCTURE HISTORY:
2012 (EST ) - ROADWAY REPAVED.
(231) ADDITIONAL CONSIDERATIONS:
(330) ADDITIONAL CONFIGURATION INFORMATION:
$ 2000
$ 40000
(229) CONSTRUCTION COST:.......... $ 0
Inspector: Osama Tariq Structure Number: 5460001P0000000
Inspection Date: 05/09/2022 Facility Carried: NEWFOUND GAP ROA
Bridge Inspection Report
Pictures
PHOTO 3
Description LOOKING SOUTH TOWARD NEWFOUND GAP
PHOTO 4
Description WEST (DOWNSTREAM) SIDE
Bridge Inspection Report
Pictures
PHOTO 5
Description GENERAL TOPSIDE VIEW LOOKING SOUTH
PHOTO 6
Description TYPICAL LONGITUDINAL AND TRANSVERSE CRACKING OF ASPHALT PAVEMENT, NORTHBOUND LANE OVER SOUTH PIER SHOWN
Bridge Inspection Report
Pictures
PHOTO 7
Description TYPICAL DETERIORATION OF PARAPET MASONRY MORTAR JOINTS, WEST PARAPET IN
CENTER SPAN NEAR NORTH PIER SHOWN
PHOTO 8
Description TYPICAL DETERIORATION OF VERTICAL JOINT FILLER MATERIAL ON PARAPETS, WEST
PARAPET AT SOUTH PIER SHOWN
Bridge Inspection Report
Pictures
PHOTO 9
Description LOOSE COPING STONE AT END OF NORTHWEST WIGNWALL
PHOTO 10
Description TYPICAL LONGITUDINAL AND TRANSVERSE CRACKING OF ASPHALT PAVEMENT;
SOUTHBOUND LANE AT NORTH APPROACH SHOWN
Bridge Inspection Report
Pictures
PHOTO 11
Description TYPICAL HONEYCOMBING ON ARCH UNDERSIDE, SOUTH SPAN AT SOUTH ABUTMENT
SHOWN; NOTE TYPICAL DETERIORATION OF INSULATION WRAPPING ON CONDUIT FRO
FLOOD GAUGE
PHOTO 12
Description GENERAL UNDERSIDE VIEW LOOKING SOUTH, SOUTH SPAN
Bridge Inspection Report
Pictures
PHOTO 13
Description TYPICAL LONGITUDINAL CRACKING OF ARCH UNDERSIDE WITH EFFLORESCENCE, CENTER SPAN AT NORTH PIER SHOWN
PHOTO 14
Description TYPICAL CRACKING OF ARCH UNDERSIDE WITH EFFLORESCENCE, EAST SIDE OF SOUTH
SPAN SHOWN; NOTE TYPICAL EFFLORESCENCE ON RING STONES
Bridge Inspection Report
Pictures
PHOTO 15
Description TYPICAL EFFLORESCENCE ON RING STONES, EAST SIDE OF NORTH SPAN SHOWN
PHOTO 16
Description GENERAL VIEW OF NORTH ABUTMENT; NOTE TYPICAL LONGITUDINAL CRACKING OF
ARCH UNDERSIDE WITH EFFLORESCENCE
Bridge Inspection Report
Pictures
PHOTO 17
Description EROSION AT WEST END OF SOUTH ABUTMENT BREASTWALL; NOTE TYPICAL
VEGETATION GROWTH ALONG WINGWALLS
PHOTO 18
Description TYPICAL VEGETATION GROWTH ALONG WINGWALLS, NORTHWEST WINGWALL SHOWN;
NOTE TYPICAL MISSING OBJECT MARKERS
Bridge Inspection Report
Pictures
PHOTO 19
Description TYPICAL DETERIORATION OF FILLER MATERIAL IN VERTICAL EXPANSION JOINTS EAST
SIDE AT NORTH ABUTMENT SHOWN; NOTE TYPICAL VEGETATION GROWTH IN JOINTS
PHOTO 20
Description GENERAL VIEW OF SOUTH PIER, SOUTH SIDE
Bridge Inspection Report
Pictures
PHOTO 21
Description EROSION AT WEST END OF NORTH PIER, CENTER SPAN SHOWN
PHOTO 22
Description ACCUMULATION OF DRIFT IN CENTER SPAN
Bridge Inspection Report
Pictures
PHOTO 23
Description UPSTREAM CHANNEL
PHOTO 24
Description DOWNSTREAM CHANNEL