Amendment 0002 - TN NP GRSM 10N(3) 19(1) 107(1).pdf
PDF 610 KB Posted
- Attached to
- Great Smoky Mountains National Park
- Solicitation number
- 693C73-23-R-000019
About this file
This solicitation is for construction services for the Great Smoky Mountains National Park Project TN NP GRSM 10N(3),19(1),107(1). The project consists of asphalt concrete pavement milling and overlay, full depth reclamation with cement stabilization, thin lift asphalt concrete pavement, asphalt concrete pavement patching, repointing stone masonry joints, replacing steel-backed timber guardrail, removing and resetting stone curb, cleaning and repairing drainage structures, reconditioning ditches and shoulders, replacing signs, placing permanent pavement markings, performing concrete deck repairs, and placing new concrete deck overlay across three schedules of work. Schedule A involves work on Lakeview Drive East totaling 6.41 miles. Schedule B involves work on Newfound Gap Road, River Road, Gatlinburg Bypass Road and associated areas totaling 3.05 miles. Schedule C involves work on Heintooga Ridge Road and Balsam Mountain Campground Roads totaling 6.13 miles. The total project cost is expected to be between $25-35 million. The solicitation number is 693C73-23-R-000019 and proposals from certified small businesses are due on the date specified in the SF1442.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE
0002 03/12/2023
6. ISSUED BY CODE 693C73
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY
SUITE E2-3-300
ATTN: ACQUISITIONS
ASHBURN VA 20147
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
CODE FACILITY CODE
1. CONTRACT ID CODE
4. REQUISITION/PURCHASE REQ. NO.
7. ADMINISTERED BY (If other than Item 6)
I
PAGE OF PAGES
1 I 9
5. PROJECT NO. (If applicable)
See Block 14
CODE I 6 93C7 3
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY
SUITE E2-3-300
ATTN: CONSTRUCTION
ASHBURN VA 20147
9A. AMENDMENT OF SOLICITATION NO.
693C7323R000019
X
9B. DATED (SEE ITEM 11)
02/22/2023
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
IXI The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers Dis extended. ra is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor Dis not Dis required to sign this document and return ______ _ copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Project TN NP GRSM 10N(3), 19(1), 107(1):
The purpose of this Amendment is to:
1) Revise the solicitation as follows:
a) Page 3 to correct the Schedule letter designation of North Entrance (Gatlinburg) Sign
Parking Area from Schedule A to Schedule B.
2) Revise the Plans as follows:
a) Sheets A-N0l and A-N02 to revise notes that conflicted with the end dates of permitted closure periods.
3) Provide a summary of responses to questions and clarifications asked by potential
Continued ...
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 1 0A, as heretofore changed, remains unchanged and in full force and effect .
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED
(Signature of person authorized to sign)
Previous edition unusable
Christopher Long
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
REFERENCE NO. OF DOCUMENT BEING CONTINUED
CONTINUATION SHEET
693C7323R000019/0002
NAME OF OFFEROR OR CONTRACTOR
ITEM NO. SUPPLIES/SERVICES
(A) (B) offerors.
4) The Proposal Due Date of March 28, 2023, 2:00 p.m. EST will remain unchanged.
NSN 7540-01-152-8067
QUANTITY UNIT UNIT PRICE
(C) (D) (E) at
OF
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFRl 53.110
Project TN NP GRSM 10N(3),19(1),107(1) Amendment No. 0002
Amendment Information
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
Amendment No. 0002 Project TN NP GRSM 10N(3),19(1),107(1)
GREAT SMOKY MOUNTAINS NATIONAL PARK
Solicitation: 693C73-23-R-000019
The purpose of this Amendment is to:
1) Revise the solicitation as follows:
a) Page 3 to correct the Schedule letter designation of North Entrance (Gatlinburg) Sign
Parking Area from Schedule A to Schedule B.
2) Revise the Plans as follows:
a) Sheets A-N01 and A-N02 to revise notes that conflicted with the end dates of permitted closure periods.
3) Provide a summary of responses to questions and clarifications asked by potential offerors.
4) The Proposal Due Date of March 28, 2023, at 2:00 p.m. EST will remain unchanged.
Offerors are reminded to submit any questions to eflhd.contracts@dot.gov. All questions should be submitted as early as possible so the Proposal Due Date will not be delayed. Questions submitted within 7 days of the Proposal Due Date have the potential of not being answered with enough time for offerors to finalize their proposals.
mailto:eflhd.contracts@dot.gov
B □ Sugarlands Headquarters Road 0.00 To 0.46 2,429 0.46 0.92 (aka Park Headquarters Road)
B □ Fighting Creek Gap Road lo+00 To 13+60 360 0.G7 0.14
B □ Fighting Creek Gap Road Spur from 0.00 To 0.049 259 0.05 0.05 Newfound Gap Road
B 00 Sugarlands Trailhead Parking A 425 39 0.01 0.01
B 00 Sugarlands Trailhead Parking B 790 72 0.01 0.01
B 00 North Entrance (Gatlinburg) Sign
Parking Area 4,475 407 0.08 0.08
B 00 North Entrance Turnaround 6,520 593 0.11 0.11
B 00 Sugarlands Riding Stables Parking Area 9,322 847 0.16 0.16
B 00 Sugarlands Maintenance Yard Parking B 3,406 310 0.06 0.06
B 00 Sugarlands Residence Parking #1 4,326 393 0.G7 0.G7
B 00 Little River Ranger Station Parking 4,838 440 0.08 0.08
B 00 Sugarlands Headquarters Visitor Parking 4,524 411 0.08 0.08
C □ Heintooga Ridge Road 0.00 To 5.34 28,195 5.34 10.68
C □ Balsam Mountain Campground Road 0.00 To 0.32 1,690 0.32 0.64
C □ Balsam Mountain Campground Loop 0.00 To 0.09 475 0.09 0.09
C 00 GRSM/BLRl Boundary Parking 7,003 637 0.12 0.12
C 00 Black Camp Gap Parking 5,404 491 0.09 0.09
C 00 Flat Creek Trail Parking 2,597 236 0.04 0.04
C 00 Polls Gap Trail Parking 2,570 234 0.04 0.04
C 00 Maple Tree Parking 5,510 501 0.09 0.09
Plan Sheet Revisions
Plan Sheet Revisions
Delete Plan Sheet A-N01 and substitute the amended Plan Sheet A-N01.
Plan Sheet A-N01, Temporary Traffic Control Narrative Schedule A and Schedule C; revised Note 2(d) under the Schedule A: Lakeview Drive East Road Closures section to remove the conflict with the end date for permitted closure period for the road.
Delete Plan Sheet A-N02 and substitute the amended Plan Sheet A-N02.
Plan Sheet A-N02, Temporary Traffic Control Narrative Schedule A and Schedule C; revised Note 1(c) under the Schedule C: Balsam Mountain Campground Roads section to remove the conflict with the end date for permitted closure period for the campground.
jj
GENERAL NOTES:
1. Provide and maintain temporary traffic control devices for the duration of the project in accordance with Section 156, Section 635, and the latest edition of the MUTCD.
a) Obtain approval from the CO for location and spacing of temporary traffic control devices.
b) Install temporary traffic control devices for advanced signing prior to beginning the project and maintain devices through the completion of all construction activities. Install additional devices for lane closures according to Standards and Details E635-01, 635-2A, 635-3A, 635-6, and 635-10.
c) Remove temporary traffic control devices upon contract completion or when directed otherwise by the CO.
2. Cover all conflicting signs during construction operations with non-transparent material.
3. Contractor employee's personal vehicles are not permitted to park along roadway shoulders.
4. A weekend is defined as beginning at 12:00 p.m. on Friday and concluding at 7:00 a.m. the following Monday.
5. Unless otherwise noted, construction operations are limited as follows:
a) No work will be permitted on weekends and National legal holidays;
b) No work will be permitted the week before and after Easter Sunday;
c) No work will be permitted the Friday before Memorial Day;
d) No work will be permitted the Friday before Labor Day;
e) No work will be permitted during the month of October;
f) No work will be permitted the Wednesday before Thanksgiving Day through the weekend after Thanksgiving Day;
g) No work will be permitted the week of Christmas Day; and
h) No work will be permitted the week of New Year's Day.
6. No work will be permitted on days with special events occurring in the vicinity, as determined by the CO.
7. Nighttime operations are permitted upon approval by the CO. Submit lighting plan according to Subsection 156.08.
a) Nighttime hours are defined as beginning at 7:00 p.m. and ending at 7:00 a.m. the following day.
b) Supplement al/ lane closures that remain in place during nighttime hours with warning lights. Fasten warning lights to all temporary traffic control devices associated with the lane closure.
c) Do not place the final lift of asphalt concrete pavement, the thin lift asphalt concrete pavement, or permanent pavement markings at night.
; 8. Place post-mounted advance warning signs and portable changeable message signs at locations shown or as directed by the � CO. Coordinate with the CO to input and change messages on portable changeable message signs. Ensure proper operation of portable changeable message signs 24 hours a day, including dimming 50 percent at night, inputting or changing sign message, � and general maintenance of signs.
i f
9. Maintain access to the areas listed below at all times except as noted otherwise. Coordinate any work with the CO that will restrict access to the following areas:
a) Balsam Mountain Campground;
b) Balsam Mountain Ranger Station;
c) Heintooga Overlook; and
d) Heintooga Picnic Area.
NO. DATE BY REVISIONS
� � 03/06/23
PMIS No 317512 NPS No 133/180 095
I AMENDMENT 0002 STATE
NC
PROJECT
TN NP GRSM
10N(3).19(1 ).107(1)
10. Limit construction-caused delays to public traffic to a maximum of 10 minutes per passage through each project site.
SHEET
NUMBER
A-NOl
11. Stage or stockpile material in no more than three pull-offs or parking areas at a time as approved by the CO. Obtain approval from the CO at least 10 days before closing any area for staging or stockpiling. In these areas, only materials approved by the CO will be permitted to be stockpiled. Stockpiling of aggregates, excavated material, and other loose materials will be permitted in areas where the grade is no more than 4 percent. Staging and stockpiling are not permitted in pullouts and parking areas where the final lift of asphalt has been placed. Staging and stockpiling are not permitted in the areas listed in General Note #9.
12. Place temporary pavement markings according to Subsection 635.13 and Details 635-2A and 635-3A.
In addition to the restrictions under General Notes, maintain traffic as follows:
SCHEDULE A: LAKEVIEW DRIVE EAST ROAD CLOSURES:
Closure of Lakeview Drive East is permitted from May 15 through August 15, 2023. Notify the CO at least 10 days in advance of closing the road and beginning the planned work. Complete any construction activities not completed during the closure period under single lane closures.
1. At a minimum, complete the following under full road closure, unless approved otherwise by the CO:
a) Full depth reclamation with cement of Lakeview Drive East;
b) Asphalt concrete pavement binder course (2V2-inch depth);
c) Concrete deck repairs on Noland Creek Bridge; and
d) Concrete overlay on Noland Creek Bridge.
2. Setup and maintain a full road closure of Lakeview Drive East as follows:
a) Close Lakeview Drive East prior to the gate at the Park Boundary. Install temporary traffic control devices in preparation for the closure according to the Temporary Traffic Control Advanced Signing Plan.
b) Accommodate emergency vehicle (i.e., police, fire, ambulance, etc.) access through the work site;
c) Accommodate traffic on days with scheduled cemetery visits through the work site; and _v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_v_)
../,\.. ') Remove temporary traffic control devices for the road closure and open the roadway to traffic no later than the date w hown above, unless approved otherwise by the CO.
A A A
A A
A A
A
A A
A A
A
A A
A
A
A
A
A
A
A
A
3. The road closure and approved construction activities are permitted 24 hours a day, 7 days a week.
SCHEDULE A: LAKEVIEW DRIVE EAST SINGLE LANE CLOSURES:
1. Complete any construction activities not completed prior to the end of the closure period using single lane closures. Setup and maintain single lane closures on Lakeview Drive East as follows:
a) Maintain two-way, one lane of traffic using f/aggers according to Standard 635-6 through the active construction zone;
b) A maximum of one single lane closure is permitted at any one time;
c) The maximum length of a lane closure is 1 mile;
d) Utilize a pilot car to supplement temporary traffic control activities when performing the work; and
e) Lane closures are permitted weekdays and weeknights, except for the periods listed in General Note #5.
Continued on next sheet. ..
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
OFFICE OF FEDERAL LANDS HIGHWAY
GREAT SMOKY MOUNTAINS NATIONAL PARK
TEMPORARY TRAFFIC CONTROL
NARRATIVE
SCHEDULE A AND SCHEDULE C
N jj
. . . Continued from previous sheet.
SCHEDULE C: HEINTOOGA RIDGE ROAD:
1. Setup and maintain single lane closures for the duration of construction activities on Heintooga Ridge Road as follows:
a) Maintain two-way, one lane of traffic using flaggers according to Standard 635-6 through the active construction zone;
b) A maximum of one single lane closure is permitted at any one time;
c) The maximum length of a lane closure is 1 mile;
d) Utilize a pilot car to supplement temporary traffic control activities when performing the work; and
e) Lane closures are permitted weekdays and weeknights, except for the periods listed in General Note #5.
2. For sections of roadway that require patching for the full road width, patch one-half at a time to maintain traffic.
SCHEDULE C: BALSAM MOUNTAIN CAMPGROUND ROADS:
Closure of the Balsam Mountain Campground Roads are permitted from June 5 to June 16, 2023. Notify the CO at least 10 days in advance of closing the roads and beginning the planned work.
1. Setup and maintain a full road closure for the duration of construction activities at the Balsam Mountain Campground as follows:
a) Install temporary traffic control devices in preparation for the full road closure according to the Temporary Traffic Control Advanced Signing Plan.
b) Accommodate emergency vehicle (i.e., police, fire, ambulance, etc.) access through the work site; and-ovvvvvvvvvvvvvvvvvvvvvvvvvvvvvvvvvvvvvvvvvvvvvvvvvvvvvvvvv
/0-
c) Complete all construction activities, remove temporary traffic control devices, and open the Balsam Mountain
'Q"" Campground Roads to public traffic no later than 12:00 Noon on the date shown above. If construction activities are completed before this date, open the roadway within 24 hours unless approved otherwise by the CO.
__ A A A A A A A _ A A A A A A A __ A A A A A A A A A A A A A A __ A A A A A A A __ A A A A A A __
2. Construction operations, except for the activities described in General Note #7, are permitted 24 hours a day, 7 days a week for the duration of the closure.
NO. DATE BY REVISIONS
g:1-------c.--------1-- --+-----l-c--------- - - -- ----------l N 4> 03/06/23 MH �!���re� o c��s��';{ 6�(;�g1gri���� c �i� t �t!i� d C�����6und.
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
OFFICE OF FEDERAL LANDS HIGHWAY
PMIS No 317512 NPS No 133/180 095
I AMENDMENT 0002 STATE
NC
PROJECT
TN NP GRSM
10N(3).19(1 ).107(1)
GREAT SMOKY MOUNTAINS NATIONAL PARK
SHEET
NUMBER
A-N02
TEMPORARY TRAFFIC CONTROL
NARRATIVE
SCHEDULE A AND SCHEDULE C
Questions / Clarifications Page 1 of 2
Questions / Clarifications
Offerors can send written questions or inquiries for clarification to: eflhd.contracts@dot.gov.
Questions can be submitted at any time, but questions submitted within 7 days of the Proposal Due Date may not be answered in time for the offeror to properly incorporate the responses into their proposals.
The following questions and issues were submitted via email. The Government response or clarification is provided. Due to the repetitive nature of several questions and issues, the wording of the questions may have been revised and some questions have not been included.
The Government’s direct response to the sender may also have been updated below for better clarity.
1. On the 3rd page of the solicitation, North Entrance (Gatlinburg) Sign Parking Area is checked as Schedule A. However, on sheet A02 of the plans, the same location, also identified as Route 0900, is listed under Schedule B. Based on the location of similar areas, it appears that it should be on Schedule B, but we would like to confirm.
Response: The North Entrance (Gatlinburg) Sign Parking Area, Route 0900, is part of Schedule B. The Schedule designation shown on Page 3 of the solicitation is incorrect.
Revised Page 3 of the solicitation is included in Amendment 0002 to correct the Schedule designation for the parking area.
NOTE to ACQ: On Page 3 of the ADV Contract Booklet Cover as shown below, the entry for North Entrance (Gatlinburg) Sign Parking Area incorrectly shows the schedule designation as "A". A revised ADV Contract Book Cover PDF has been provided with the corrected schedule designation to "B".
2. On sheet A-N01 of the plans under Schedule A: Lakeview Drive East Road Closures, the first paragraph references the permitted closure of traffic is from May 15 through August 15, 2023. However, in note 2(d) it states to reopen the road to traffic no later than 0500 on the third Thursday in May.
Response: The closure period for Lakeview Drive East is permitted from May 15 through August 15, 2023. On Sheet A-N01, under the Schedule A: Lakeview Drive East Road Closures section, Note 2(d) is incorrect. Revised plan sheet A-N01 is included in Amendment 0002 to remove the conflict with the end date for permitted closure period for the road.
mailto:eflhd.contracts@dot.gov
Questions / Clarifications Page 2 of 2
3. Similarly, on sheet A-N02 under Schedule C: Balsam Mountain Campground Roads it states that roads are permitted to be closed from June 5 to June 16, 2023. However, note 1(c) states that the roads be open to public traffic no later than 0500 on the second Thursday in May.
Response: The closure period for the Balsam Mountain Campground is permitted from June 5 to June 16, 2023. On Sheet A-N02, under the Schedule C: Balsam Mountain Campground Roads section, Note 1(c) is incorrect. Revised plan sheet A-N02 is included in Amendment 0002 to remove the conflict with the end date for permitted closure period for the campground.
| U.S. DEPARTMENT OF TRANSPORTATION FEDERAL HIGHWAY ADMINISTRATION EASTERN FEDERAL LANDS HIGHWAY DIVISION |
| Amendment No. 0002 |
| Project TN NP GRSM 10N(3),19(1),107(1) |