BID 2025-91 Addendum 3.pdf
PDF 920 KB Posted
- Solicitation number
- S-C01010-00017129
- Issued by
- Clackamas County, Mission CDP, Oregon
About this file
This is Addendum Number 3 to Invitation to Bid #2025-91 for a neighborhood park project at Jennings Lodge Campus, issued by Clackamas County on behalf of the North Clackamas Parks and Recreation District on July 8, 2026. The project involves construction and site development work at The Park at Jennings Lodge Campus located at 18521 SE River Road, Milwaukie, Oregon 97267. The addendum modifies key project specifications and bid requirements by converting Deductive Alternate #1 into an Additive Alternate and renaming the previous Deductive Alternate #2 as the new Deductive Alternate #1. The work encompasses sitework, roadways, pedestrian paving, site development, landscaping, utilities, and maintenance of planting and irrigation across both the main campus site and right-of-way areas. The bid schedule includes lump sum pricing for mobilization, temporary traffic control, erosion and sediment control, clearing and demolition, earthwork, paving, site development, landscaping, utilities, and maintenance over a one-year warranty period.
The Additive Alternate #1 carries a fixed allowance of $50,000 for soil treatment and testing to amend or condition existing silty and wet site soils to usable condition. The new Deductive Alternate #1 addresses reduced base rock by four inches for asphalt and concrete surfacing in areas where grass is currently present, eliminating its application to the right-of-way. Bidders are responsible for independent quantity take-offs and verification of all quantities shown on the bid schedule. The addendum requires submission of drawing C0.01, the updated Measurement and Payment section (Division 1, Section 01025), and the revised Bid Schedule dated July 8, 2026. All work must comply with current standard specifications, American Public Works Association standards, state plumbing and building codes, and local authority requirements, with contractor responsibility for utility location notification, erosion control, and restoration of disturbed areas.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INVITATION TO BID #2025-91
Neighborhood Park at Jennings Lodge
ADDENDUM NUMBER 3
July 8, 2026
On June 3, 2026, Clackamas County (“County”) published Invitation to Bid #2025-91 (“BID”) and on July 2, 2026, Addendum #1 and on July 7, 2026, Addendum #2. The County has found that it is in its interest to amend the BID through the issuance of this Addendum #3. Except as expressly amended below, all other terms and conditions of the original BID and subsequent Addenda shall remain unchanged.
1. Drawing C0.01 has been modified to indicate Deductive Alternate #1 has been made an Additive Alternate. Remove and Replace Drawing Sheet No: C0.01 (1 Page)
2. The Measurement and Payment section has been modified to indicate Deductive Alternate #1 has been made an Additive Alternate. Deductive Alternate #2 has been renamed to Deductive Alternate #1 and removes its application to the right of way.
Remove and Replace Division 1- General Requirements- Section 01025 Measurement and Payment (8 pages)
3. The bid tab has been modified per the above changes and slightly reorganized for clarity.
Remove and replace the Bid Schedule with the attached new Bid Schedule dated 7/8/26.
Attachments: Drawing C0.01; The Measurement and Payment section (8 pages) and New Bid Schedule. (1 pages)
End of Addendum #3
ALL RIGHTS RESERVED
MACKENZIE 2026
SHEET TITLE:
JOB NO.
SHEET:
THESE DRAWINGS ARE THE PROPERTY OF
MACKENZIE AND ARE NOT TO BE USED
OR REPRODUCED IN ANY MANNER,
WITHOUT PRIOR WRITTEN PERMISSION
2220400.00
ADDENDUM #1 07/02/2026
Client
NORTH CLACKAMAS
PARKS AND
RECREATION
DISTRICT
150 BEAVERCREEK RD
OREGON CITY, OR 97405
Project
THE PARK AT
JENNINGS LODGE
CAMPUS
18521 SE RIVER RD
MILWAUKIE, OR 97267
EXISTING PROPOSED
RIGHT-OF-WAY LINE
CENTERLINE
CURB
EDGE OF PAVEMENT
EASEMENT
FENCE LINE
STORM SEWER LINE
SANITARY SEWER LINE
WATER LINE
TREE
DRYWELL
FIRE HYDRANT
WATER METER
WATER VALVE
BACKFLOW PREVENTOR
STORM/SANITARY MANHOLE
STORM SEWER CATCH BASIN
SANITARY CLEAN OUT
SIGN
MAIL BOX
FOUND SURVEY MONUMENT
GUY WIRE ANCHOR
UTILITY POLE
LIGHT POLE
SLOPE ARROW
FLOW LINE
LEGEND
ABBREVIATIONS
GENERAL NOTES
1. ALL WORK SHALL CONFORM TO THE CURRENT STANDARD SPECIFICATIONS AND
REQUIREMENTS OF THE AUTHORITIES HAVING JURISDICTION AND THE CURRENT
AMERICAN PUBLIC WORKS ASSOCIATION STANDARDS FOR PUBLIC WORKS
CONSTRUCTION
2. THE SURVEY INFORMATION SHOWN AS A BACKGROUND SCREEN IS BASED ON A SURVEY
BY OTHERS AND IS SHOWN FOR REFERENCE ONLY. CONTRACTOR TO VERIFY ALL
EXISTING CONDITIONS WITH ITS OWN RESOURCES PRIOR TO START OF ANY
CONSTRUCTION
3. CONTRACTOR MUST COMPLY WITH LOCAL AND STATE REQUIREMENTS TO NOTIFY ALL
UTILITY COMPANIES FOR LINE LOCATIONS SEVENTY-TWO (72) HOURS (MINIMUM) PRIOR
TO START OF WORK. DAMAGE TO UTILITIES SHALL BE CORRECTED AT THE
CONTRACTOR'S EXPENSE
4. CONTRACTOR SHALL ADJUST ALL STRUCTURES IMPACTED BY CONSTRUCTION
IMPROVEMENTS TO NEW FINISH GRADES
5. REQUEST BY THE CONTRACTOR FOR CHANGES TO THE PLANS MUST BE APPROVED BY
THE ENGINEER.
6. ALL WORK WITHIN THE PUBLIC RIGHT-OF-WAY REQUIRES A PUBLIC WORKS PERMIT
7. CONTRACTOR SHALL PROVIDE THE ENGINEER OF RECORD WITH AS-BUILT PLANS AT
LEAST 2 WEEKS PRIOR TO REQUESTING AGENCY SIGN OFF ON PERMITS FOR OCCUPANCY
8. CONTRACTOR SHALL PERFORM ALL THE WORK SHOWN ON THE DRAWINGS AND ALL
INCIDENTAL WORK NECESSARY TO COMPLETE THE PROJECT
SITE DEMOLITION NOTES
1. COMPLY WITH ALL APPLICABLE CODES AND REGULATIONS FOR DEMOLITION OPERATIONS
AND SAFETY OF ADJACENT STRUCTURES AND THE PUBLIC
2. INSTALL EROSION CONTROL MEASURES AND TEMPORARY FENCING PRIOR TO ANY
DEMOLITION ACTIVITIES
3. MITIGATE DUST POLLUTION DUE TO DEMOLITION ACTIVITIES
4. PROTECT ALL EXISTING STRUCTURES, UTILITIES, LANDSCAPE AND OTHER ELEMENTS
THAT ARE NOT DESIGNATED FOR REMOVAL. ANY DAMAGE TO EXISTING IMPROVEMENTS
NOT DESIGNATED FOR REMOVAL SHALL BE REPAIRED/REPLACED AT THE CONTRACTOR'S
EXPENSE
5. DO NOT BEGIN REMOVAL UNTIL ITEMS TO BE SALVAGED OR RELOCATED HAVE BEEN
REMOVED AS NOTED. IF REMOVED GRAVEL OR PAVEMENT MATERIALS ARE TO BE
RECYCLED OR REUSED, PREVENT CONTAMINATION OF THESE MATERIALS FROM TOPSOIL
OR OTHER DELETERIOUS MATERIAL
6. CONTRACTOR SHALL COORDINATE DEMOLITION WORK WITH AFFECTED UTILITY
COMPANIES, OBTAIN ALL REQUIRED PERMITS, NOTIFY THEM PRIOR TO STARTING WORK,
AND COMPLY WITH THEIR REQUIREMENTS. ADDITIONAL REMOVALS MAY BE REQUIRED BY
THE AUTHORITIES HAVING JURISDICTION AND THE CONTRACTOR SHALL CONFIRM
ACCORDINGLY PRIOR TO BID. ACCURATELY RECORD ACTUAL LOCATIONS OF CAPPED
AND ACTIVE UTILITIES FOR AS-BUILT PURPOSES AND SUPPLY TO OWNER AND
ARCHITECT/ENGINEER OF RECORD
7. DEMOLISH AND REMOVE ALL NON-BUILDING SITE STRUCTURES AND ASSOCIATED
FEATURES (APPURTENANCES) AS SHOWN. WITHIN AREA OF NEW CONSTRUCTION,
REMOVE DESIGNATED WALLS AND FOOTINGS TO 2 FEET MINIMUM BELOW FINISHED
GRADE. DEMOLISH ALL PAVED AREAS DESIGNATED FOR REMOVAL DOWN TO NATIVE
SUBGRADE
8. ALL VEGETATION AND DELETERIOUS MATERIALS WITHIN THE LIMITS OF WORK SHALL BE
STRIPPED AND REMOVED FROM THE SITE PRIOR TO GRADING WORK UNLESS NOTED
OTHERWISE (E.G. PROTECTED TREES)
9. IF HAZARDOUS MATERIALS ARE DISCOVERED DURING DEMOLITION, STOP WORK AND
IMMEDIATELY NOTIFY THE OWNER AND ARCHITECT/ENGINEER OF RECORD
GRADING NOTES
1. ROUGH GRADING: ROUGH GRADE TO ALLOW FOR DEPTH OF PAVEMENTS, BASE
COURSES, AND TOPSOIL PER DETAILS AND SPECIFICATIONS
2. FINISH GRADING: BRING ALL FINISH GRADES TO LEVELS INDICATED. WHERE GRADES ARE
NOT OTHERWISE INDICATED, HARDSCAPE FINISH GRADES ARE TO BE THE SAME AS
ADJACENT SIDEWALKS, CURBS, OR THE OBVIOUS GRADE OF ADJACENT STRUCTURE.
SOFTSCAPE GRADES (INCLUDING ADDITIONAL DEPTH OF TOPSOIL) SHALL BE SET 6
INCHES BELOW BUILDING FINISHED FLOORS WHERE ABUTTING BUILDINGS, 1-2 INCHES
WHERE ABUTTING WALKWAYS OR CURBS, OR MATCHING OTHER SOFTSCAPE GRADES.
GRADE TO UNIFORM LEVELS OR SLOPES BETWEEN POINTS WHERE GRADES ARE GIVEN.
ROUND OFF SURFACES, AVOID ABRUPT CHANGES IN LEVELS. AT COMPLETION OF JOB
AND AFTER BACKFILLING BY OTHER TRADES HAS BEEN COMPLETED, REFILL AND
COMPACT AREAS WHICH HAVE SETTLED OR ERODED TO BRING TO FINAL GRADES
3. EXCAVATION: EXCAVATE FOR SLABS, PAVING, AND OTHER IMPROVEMENTS TO SIZES AND
LEVELS SHOWN OR REQUIRED. ALLOW FOR FORM CLEARANCE AND FOR PROPER
COMPACTION OF REQUIRED BACKFILLING MATERIAL. DAMAGE TO UTILITIES SHALL BE
CORRECTED AT THE CONTRACTOR'S EXPENSE
4. EFFECTIVE EROSION PREVENTION AND SEDIMENT CONTROL IS REQUIRED. EROSION
CONTROL DEVICES MUST BE INSTALLED AND MAINTAINED MEETING THE LOCAL AGENCY
AND STATE AGENCY REQUIREMENTS. THE AUTHORITIES HAVING JURISDICTION MAY, AT
ANY TIME, ORDER CORRECTIVE ACTION AND STOPPAGE OF WORK TO ACCOMPLISH
EFFECTIVE EROSION CONTROL
5. DRAINAGE SHALL BE CONTROLLED WITHIN THE WORK SITE AND SHALL BE ROUTED SO
THAT ADJACENT PRIVATE PROPERTY, PUBLIC PROPERTY, AND THE RECEIVING SYSTEM
ARE NOT ADVERSELY IMPACTED. THE ENGINEER AND/OR AUTHORITIES HAVING
JURISDICTION MAY, AT ANY TIME, ORDER CORRECTIVE ACTION AND STOPPAGE OF WORK
TO ACCOMPLISH EFFECTIVE DRAINAGE CONTROL
6. SITE TOPSOIL STOCKPILED DURING CONSTRUCTION AND USED FOR LANDSCAPING SHALL
BE APPROVED BY THE LANDSCAPE ARCHITECT
7. CONTRACTOR TO REVIEW AND CONFIRM GRADES AT JOIN POINTS, SUCH AS AT DAYLIGHT
LIMITS AND BUILDING ENTRANCES, PRIOR TO CONSTRUCTION
8. SITE SOILS ARE EXPECTED TO BE SILTY AND WET. CONTRACTOR IS RESPONSIBLE FOR
DEVELOPING AND EXECUTING A WORKPLAN FOR REVIEW AND APPROVAL BY OWNER
THAT PROTECTS EXCAVATED SOILS. SEE GEOTECHNICAL REPORT.
9. AGGREGATE BASES SHOULD BE PLACED AND COMPACTED IMMEDIATELY AFTER SOIL HAS
BEEN EXPOSED AND COMPACTED TO PROTECT PREPARED GRADES.
10. ADDITIONAL MEASURES MAY BE NEEDED TO TREAT, DRY OR CONDITION THE SOIL.
DEDUCTIVE ALTERNATE #1: $50,000 ALLOWANCE FOR SOIL TREATMENT.
UTILITY NOTES
1. ALL WORK SHALL CONFORM TO THE CURRENT EDITIONS OF THE STATE PLUMBING AND
BUILDING CODES WITH LOCAL AMENDMENTS AS APPLICABLE ALONG WITH ANY
ADDITIONAL REQUIREMENTS OF THE AUTHORITIES HAVING JURISDICTION.
2. THE WORKING DRAWINGS ARE GENERALLY DIAGRAMMATIC. THEY DO NOT SHOW EVERY
OFFSET, BEND OR ELBOW REQUIRED FOR INSTALLATION IN THE SPACE PROVIDED. THEY
DO NOT SHOW EVERY DIMENSION, COMPONENT PIECE, SECTION, JOINT OR FITTING
REQUIRED TO COMPLETE THE PROJECT. ALL LOCATIONS FOR WORK SHALL BE CHECKED
AND COORDINATED WITH EXISTING CONDITIONS IN THE FIELD BEFORE BEGINNING
CONSTRUCTION. EXISTING UNDERGROUND UTILITIES WITHIN THE LIMITS OF EXCAVATION
SHALL BE VERIFIED AS TO CONDITION, SIZE AND LOCATION BY UNCOVERING
(POTHOLING), PROVIDING SUCH IS PERMITTED BY THE AUTHORITIES HAVING
JURISDICTION, BEFORE BEGINNING CONSTRUCTION. CONTRACTOR TO NOTIFY ENGINEER
IF THERE ARE ANY DISCREPANCIES.
3. NOT ALL REQUIRED CLEANOUTS ARE SHOWN ON THE PLANS. PROVIDE CLEANOUTS PER
DETAIL AS REQUIRED BY THE AUTHORITIES HAVING JURISDICTION AND THE
CURRENT EDITION OF THE STATE PLUMBING CODE (E.G. UNIFORM PLUMBING CODE
CHAPTER 7, SECTIONS 707 AND 719, AND CHAPTER 11, SECTION 1101.13).
4. ALL SANITARY AND STORM PIPING IS DESIGNED USING CONCENTRIC PIPE TO PIPE AND
WYE FITTINGS, UNLESS OTHERWISE NOTED
5. ALL DOWNSPOUT LEADERS TO BE 6 INCHES AT 2.0% MINIMUM UNLESS NOTED
OTHERWISE
6. IF APPLICABLE, PROVIDE 2 INCH PVC DRAIN LINE FROM DOMESTIC WATER METER VAULT
AND BACKFLOW PREVENTER VAULT TO THE DOUBLE DETECTOR CHECK VALVE (FIRE)
VAULT. PROVIDE 1/3 HP SUMP PUMP AT BASE OF FIRE VAULT AND INSTALL 2 INCH PVC
DRAIN LINE WITH BACKFLOW VALVE FROM SUMP PUMP TO DAYLIGHT AT NEAREST CURB.
FURNISH 3/4 INCH DIAMETER CONDUIT FROM BUILDING ELECTRICAL ROOM TO FIRE VAULT
FOR SUMP PUMP ELECTRICAL SERVICE. NOTE: COORDINATE WITH FIRE PROTECTION
CONTRACTOR FOR FLOW SENSOR INSTALLATION AND CONDUIT REQUIREMENTS
7. PREFABRICATED PLUMBING PRODUCTS USED SHALL BE LISTED ON THE IAPMO R&T
PRODUCT LISTING DIRECTORY (pld.iapmo.org). ALL SUBMITTALS FOR REVIEW SHALL BE
ACCOMPANIED BY MANUFACTURER'S LITERATURE CLEARLY STATING THIS CERTIFICATION
AND/OR THE PRODUCT LISTING CERTIFICATE FROM THE IAPMO DIRECTORY WEBSITE
8. IF APPLICABLE, CONTRACTOR TO PROVIDE POWER TO IRRIGATION CONTROLLER. SEE
LANDSCAPE PLANS AND SPECIFICATIONS
9. SEE BUILDING PLUMBING DRAWINGS FOR PIPING WITHIN THE BUILDING AND UP TO 5 FEET
OUTSIDE THE BUILDING, INCLUDING ANY FOUNDATION DRAINAGE PIPING
10. CONTRACTOR TO MAINTAIN MINIMUM 3 FEET OF COVER OVER ALL UTILITY PIPING AND
CONDUITS, UNLESS NOTED OTHERWISE
11. WHERE CONNECTING TO AN EXISTING PIPE, AND PRIOR TO ORDERING MATERIALS, THE
CONTRACTOR SHALL EXPOSE THE EXISTING PIPE TO VERIFY THE LOCATION, SIZE, AND
ELEVATION. NOTIFY ENGINEER OF ANY DISCREPANCIES
12. CONTRACTOR SHALL SCOPE ALL PRIVATE ONSITE GRAVITY SYSTEM LINES THAT ARE
BEING CONNECTED TO FOR PROPOSED SERVICE. SCOPING SHALL OCCUR A MINIMUM OF
72 HOURS PRIOR TO CONSTRUCTION AND THE ENGINEER SHALL BE NOTIFIED
IMMEDIATELY OF ANY DISCREPANCIES WITH AS-BUILT RECORDS/SURVEY FINDINGS OR IF
THE EXISTING UTILITIES ARE DAMAGED OR SHOW SIGNS OF SIGNIFICANT
DETERIORATION. CONTRACTOR SHALL PROVIDE THE ENGINEER WITH VIDEO RECORDS,
ALONG WITH A SKETCH IF THE LOCATIONS DIFFER FROM AS-BUILT PLANS OR SURVEY
FINDINGS
13. PRODUCT MATERIAL SUBMITTALS FOR REVIEW BY THE ENGINEER SHALL BE
ACCOMPANIED BY A MANUFACTURER'S CERTIFICATION THAT THE PRODUCT IS CAPABLE
OF MEETING PERFORMANCE EXPECTATIONS (I.E. - WATERTIGHT, MINIMUM/MAXIMUM
BURIAL, PREVENTION OF GROUNDWATER INTRUSION, ETC.) BASED ON THEIR REVIEW OF
THE PROJECT PLANS. IN THE ABSENCE OF A MANUFACTURER'S CERTIFICATION, THE
GENERAL CONTRACTOR'S REVIEW STAMP SHALL CONSTITUTE THAT THEY HAVE
PERFORMED THE NECESSARY REVIEW TO CERTIFY THE PRODUCT'S CONFORMANCE TO
PROJECT SPECIFICATIONS AND GENERAL EXPECTATIONS
14. PIPE LENGTHS SHOWN ON PLANS ARE TWO DIMENSIONAL AND MEASURED FROM CENTER
OF STRUCTURE TO CENTER OF STRUCTURE
15. MANHOLE RIM ELEVATIONS SHOWN ON PLANS REFERENCE THE CENTER OF THE
STRUCTURE. THE CONTRACTOR SHALL BE RESPONSIBLE FOR RECONCILING
LIDS/GRATES/ETC TO THE SLOPES OF THE SITE GRADING
16. MANHOLE OR VAULT RIM ELEVATIONS SHALL BE SET FLUSH IN PAVEMENT AREAS AND 3-4
INCHES ABOVE GRADE IN LANDSCAPE AREAS. RIMS IN PAVEMENT AREAS SHALL BE H-20
TRAFFIC RATED
EROSION CONTROL NOTES
1. HOLD A PRE-CONSTRUCTION MEETING OF PROJECT CONSTRUCTION PERSONNEL THAT
INCLUDES THE LOCAL AGENCY INSPECTOR TO DISCUSS EROSION AND SEDIMENT
CONTROL MEASURES AND CONSTRUCTION LIMITS
2. EROSION AND SEDIMENT CONTROL MEASURES MUST BE IN PLACE BEFORE ANY LAND IS
DISTURBED AND MUST REMAIN IN PLACE AND BE MAINTAINED, REPAIRED, AND PROMPTLY
IMPLEMENTED FOLLOWING PROCEDURES ESTABLISHED FOR THE DURATION OF
CONSTRUCTION, INCLUDING APPROPRIATE NON-STORMWATER POLLUTION CONTROLS
3. THE EROSION CONTROL DRAWING IS FOR GENERAL GUIDANCE ONLY. THE CONTRACTOR
SHALL KEEP THE PLAN CURRENT FOR ALL PHASES OF CONSTRUCTION AND MEET
EROSION/SEDIMENT CONTROL REQUIREMENTS OF ALL AUTHORITIES HAVING
JURISDICTION (AHJ). ALL EROSION CONTROL MEASURES SHALL CONFORM TO THE
REQUIREMENTS OF THE AHJ, THE PLANS, AND THE PROJECT SPECIFICATIONS
4. CONSTRUCT EROSION CONTROL IN CONJUNCTION WITH ALL CLEARING AND GRADING
ACTIVITIES, AND IN SUCH A MANNER AS TO ENSURE THAT SEDIMENT AND SEDIMENT
LADEN WATER DO NOT ENTER THE DRAINAGE SYSTEM, ROADWAYS, OR VIOLATE
APPLICABLE WATER STANDARDS
5. METHOD OF INSTALLATION FOR SEDIMENT FENCE SHALL NOT CAUSE DAMAGE TO
VEGETATED SLOPE EXCEPT AT POINT OF INSTALLATION. SIDECAST MATERIAL SHALL BE
KEPT TO A MINIMUM AND SHALL BE TO THE UPHILL SIDE OF THE SEDIMENT FENCE. THE
FENCE SHALL BE INSTALLED AT LEAST 4 FEET FROM ADJACENT TREES
6. ALL EROSION CONTROL DEVICES SHALL BE EXAMINED AND REPAIRED AFTER EACH
STORM OCCURRENCE, AND INLETS SHALL BE CLEANED OF SEDIMENT WHENEVER
NECESSARY
7. HYDROSEED AND MULCH ALL DISTURBED AREAS UPON COMPLETION OF CONSTRUCTION
OR AS DIRECTED BY THE AUTHORITIES HAVING JURSIDICTION
8. THE CONTRACTOR SHALL LIMIT CONSTRUCTION TRAFFIC TO PAVED AREAS TO PREVENT
AND MINIMIZE SEDIMENT TRACKING OFF-SITE. CONTRACTOR SHALL SWEEP OR VACUUM
PAVED AREAS IF SEDIMENT ACCUMULATION OCCURS. DO NOT TRACK SEDIMENT TO THE
PUBLIC STREET OR NEIGHBORING PROPERTIES
9. INSTALL TEMPORARY EROSION PREVENTION SUCH AS JUTE NETTING OR GEOTEXTILE ON
DISTURBED AREAS STEEPER THAN 4H:1V
10. STAGING AND STOCKPILE AREAS TO BE DETERMINED BY CONTRACTOR AND ADJUSTED
TO ACCOMMODATE THE PROGRESS OF CONSTRUCTION
1/C5.10
CENTER LINE
PROPERTY LINE
AC ASPHALT CONCRETE
AHJ AUTHORITY HAVING JURISDICTION
AWWA AMERICAN WATER WORKS ASSOCIATION
BC BOTTOM OF CURB
BCR BEGIN CURB RETURN
BMP BEST MANAGEMENT PRACTICE
BS BOTTOM OF STEP
BW BACK OF WALK
C COMPACT
CB CATCH BASIN
CI CAST IRON
CIP CAST IN PLACE
CO CLEANOUT
CONC CONCRETE
CLR CLEAR
CVR COVER
DI DUCTILE IRON
DW DOMESTIC WATER
ECR END CURB RETURN
ELEV ELEVATION
EP EDGE OF PAVEMENT
ESC EROSION/SEDIMENT CONTROL
EW EACH WAY
EX EXISTING
FDC FIRE DEPARTMENT CONNECTION
FF FINISH FLOOR
FG FINISHED GRADE
FH FIRE HYDRANT
FI FIELD INLET
FL FLOWLINE
FW FIRE WATER/FACE OF WALL
G/GUT GUTTER LINE
GB GRADE BREAK
H ACCESSIBLE STALL
HDPE HIGH-DENSITY POLYETHYLENE
HMA HOT MIX ASPHALT
IE INVERT ELEVATION
LT LEFT
ME MATCH EXISTING
MH MANHOLE
MJ MECHANICAL JOINT
NTS NOT TO SCALE
OC ON CENTER
ODOT OREGON DEPARTMENT OF TRANSPORTATION
OSHA OREGON STATE HEALTH AUTHORITY
OSSC OREGON STATE SPECIFICATIONS FOR CONSTRUCTION
PC POINT OF CURVATURE
PCC POINT OF COMPOUND CURVATURE
PCCP PORTLAND CEMENT CONCRETE PAVING
PP POWER POLE
PR PROPOSED
PRC POINT OF REVERSE CURVATURE
PT POINT OF TANGENCY
PVC POLYVINYL CHLORIDE
RD ROOF DRAIN
ROW RIGHT OF WAY
RSGV RESILIENT SEAT GATE VALVE
RT RIGHT
S STANDARD
SAN SANITARY SEWER
STA STATION
STM STORM
SW SIDEWALK
TC TOP OF CURB
TH THRESHOLD
TS TOP OF STEP
TW TOP OF WALL
TYP TYPICAL
WC WHEELCHAIR
ABBREVIATIONS
W M
S
STM
WAT
STM
SAN
DW
WDC
CO
MB
D
W
C0.01
CIVIL GENERAL
NOTES,
SYMBOLS AND
ABBREVIATIONS
SAN
REVISION SCHEDULE
Issued AsDelta Issue Date
1 PLAN CHECK 03/06/2026
2 ADD 1 07/01/2026
07/02/2026
ADDITIVE
3 ADD 2 07/07/202607/08/2026
xxxx
01025 - 1
DIVISION 1
GENERAL REQUIREMENTS
SECTION 01025 MEASUREMENT AND PAYMENT
1.0 Scope
Measurement and payment for all work shown or specified herein will be made on a unit price basis in accordance with the prices set forth in the bid proposal for individual items of work. CONTRACTOR shall take special note that some elements of materials and work may be furnished by others. CONTRACTOR shall make a careful assessment when preparing the bid. The prices stated include all materials and work required to complete the entire project in accordance with the plans and specifications. If any material, item or service required by the plans and specifications has not been mentioned specifically in the PLANS, DETAILS AND SPECIFICATIONS, the same shall be furnished and placed with the understanding that the full cost has been merged with the several prices stated in the
OTHER SECTIONS.
1.1 Mobilization
Mobilization shall consist of preparatory work and operations necessary for the movement of personnel, equipment, materials, and supplies to the project site;
establishment of project offices, storage areas, and temporary facilities; removal and replacement of fence panels required for construction access; premiums and paperwork associated with bonds and insurance; obtaining and coordinating permits required for the work (excluding permit fees paid directly by the District unless otherwise specified);
coordination with the District and other contractors; construction surveying and layout required to complete the work; and all other work and costs incurred prior to beginning construction.
2025-91
01025 - 2
Mobilization shall also include demobilization, including removal of temporary facilities, equipment, materials, and restoration of areas disturbed by construction activities.
Measurement and payment for Mobilization shall be on a Lump Sum basis.
Payment will be made as follows:
1. When 5 percent of the total original contract amount is earned from bid items other than Mobilization, the lesser of 50 percent of the amount bid for Mobilization or 5 percent of the original contract amount, less retainage, will be paid.
2. When 10 percent of the total original contract amount is earned from bid items other than Mobilization, the lesser of 100 percent of the amount bid for Mobilization or 10 percent of the original contract amount, less retainage, will be paid.
3. Upon completion of all work on the project, Mobilization in excess of 10 percent of the original contract amount will be paid.
Payment shall constitute full compensation for all labor, materials, equipment, tools, transportation, supervision, and incidentals necessary to complete the work.
1.2 Temporary Traffic Control
Temporary Traffic Control shall consist of furnishing, installing, maintaining, relocating, and removing all traffic control devices, signs, barricades, delineators, pedestrian accommodations, public notification signage, flaggers, and other measures necessary to safely direct vehicular, bicycle, and pedestrian traffic during construction.
The work shall include preparation of traffic control plans; obtaining and complying with all applicable traffic control permits; maintaining access to park facilities, adjacent properties, emergency services, and construction operations; and complying with the latest edition of the Manual on Uniform Traffic Control Devices (MUTCD), County requirements, and District requirements.
Measurement and payment for Temporary Traffic Control shall be on a Lump Sum basis.
01025 - 3
Payment shall constitute full compensation for preparing traffic control plans, obtaining permits, furnishing, installing, maintaining, relocating, and removing traffic control devices and signs, providing flagging operations, maintaining public access, and all labor, equipment, materials, and incidentals necessary to complete the work.
1.3 Temporary Erosion and Sediment Control
Temporary Erosion and Sediment Control shall consist of furnishing, installing, maintaining, inspecting, repairing, replacing, and removing temporary erosion and sediment control measures required to prevent erosion and the discharge of sediment from the project site.
The work shall include obtaining erosion control permits, preparing and implementing erosion and sediment control plans, conducting required inspections, maintaining records, and complying with all applicable County, Oregon Department of Environmental
Quality (DEQ), Clean Water Services (if applicable), and District requirements.
Temporary erosion and sediment control measures may include, but are not limited to, silt fence, inlet protection, sediment barriers, wattles, stabilized construction entrances, soil stabilization, dust control, temporary seeding, mulch, and other measures necessary to maintain permit compliance throughout construction.
Measurement and payment for Temporary Erosion and Sediment Control shall be on a
Lump Sum basis.
Payment shall constitute full compensation for permits, inspections, monitoring, maintenance, replacement of failed measures, removal of temporary controls, and all labor, equipment, materials, and incidentals necessary to complete the work.
01025 - 4
1.4 Clearing, Grubbing and Demolition
Payment for clearing, grubbing, tree / stump removals, tree and bush trimming and demolition of all structures and for all schedules of the Work shall be made on a lump sum basis as set forth in the CONTRACTOR's proposal which shall constitute full compensation for all work specified herein. This item includes disposal of all strippings offsite.
1.5 Site Earthwork
Common Excavation, Embankment and Subgrade Prep - Payment for common excavation, embankment and subgrade prep will be made at the lump sum price set forth in the CONTRACTOR's proposal. Payment shall constitute full compensation for excavation, embankment and fine grading of existing soil, asphalt, concrete pavements, and any other existing surface and subsurface structures or facilities within the project limits and necessary for the construction of the improvements specified or shown on the drawings. Payment for the work shall also include loosening, blending, and compacting of subgrade material whether in fill or excavated areas, replacing any unsuitable or unstable materials with suitable material, and maintaining the prepared surface until aggregate base material is placed and is contingent on preparing and executing an approved workplan that protects existing and excavated soils. No additional payment will be made for rehandling or reworking materials to meet moisture, density, and compaction requirements. No additional payment will be made for excavation or embankment materials associated with subgrade preparation on establishment of elevation and grade.
Measurement from Common Excavation, Embankment and Subgrade Preparation shall be by the cubic yard. Quantities shall be determined from field survey-based measurements of existing and finished grades using accepted engineering methods.
1.6 Roadways
01025 - 5
Payment for roadways shall include asphalt concrete and its full profile and shall be made at the unit price as lump sum as set forth in the CONTRACTOR’s proposal and shall include full compensation for furnishing and installing asphalt concrete. No deductions and no separate measurement will be made for asphalt cement, mineral filler, lime, anti-strip or any other additive used in the mixture. No separate measurement and payment will be made for asphalt tack coat. Payment also includes traffic signs and shall include furnishing all labor and materials for signs, posts, and footings. Payment includes thermoplastic markings and paint for typical striping as defined and described by
ODOT/APWA standards and the plans set. Payment will include furnishing all labor, materials, and striping associated with symbols, parking stalls.
1.7 Pedestrian Paving
Payment for concrete and asphaltic concrete surfacing and all associated base courses will be made at the lump sum price set forth in the Contractor’s proposal. Payment includes furnishing, forming, placing, compacting, testing and curing of base course; and all minor items including but not limited to dowels, joints, surface treatments and cleanup necessary to complete the work per construction documents. No deductions and no separate measurement will be made for asphalt cement, mineral filler, lime, anti-strip or any other additive used in the mixture. No separate measurement and payment will be made for asphalt tack coat.
1.8 Site Development
Payment for Site Development will be made at the lump sum price set forth in the
Contractor’s proposal. Payment includes, but is not limited to, purchase and installation of site furnishings, playground equipment, surfacing, fencing, stones and boulders as indicated on drawings. Payment includes transport of all materials and products, as well as submittals, base prep and installation.
01025 - 6
1.9 Landscaping
Payment for Landscaping includes planting, seeding and irrigation and will be paid on a lump sum basis. Payment shall constitute full payment for all work activities to complete seed and plant establishment during the establishment period, such as watering, fertilizing, feeding, and seed or material replacement as directed by the
Engineer. The Work shall include procurement and planting of approved trees along with specified soil amendments and stakes per construction documents. The Work shall include installation of a fully functional permanent irrigation system per Construction
Documents and shall include but not be limited to all associated appurtenances.
Payment for this item includes and is contingent on a complete design-build submittal subject to approval by District Parks prior to start of installation.
1.10 Utilities
Payment for all work specified under this item shall be made at the unit price stated by the CONTRACTOR in his proposal by lump sum. Payment consists of storm drain pipe, perforated pipe, French drains, inlets, meters, vaults, backflow device, hydrants, water lines, rip rap and staking. Payment shall include trench excavation, disposal, shoring, dewatering, backfill, District-approved temporary storm runoff bypass system where required, bedding, backfill, pipe zone, pipe, compaction, saw-cutting, fittings, marker tape, testing, television inspection, surface restoration, site preparation, bedding, formwork, placing and curing concrete, pipe stubouts, removal of formwork, applying specified finishes, and backfill and all other work required for a complete system.
Payment includes testing, disinfection, and all labor and means necessary to gain approvals from Water Authority. Payment includes all work associated with relocating the power poles. Survey staking consists of staking to establish the subgrade and field finish elevations, establish the finish grade of the field, all structures and curb, the line and grade of the utility lines, and the centerline of all pathway layouts at ten foot intervals.
The length will be measured, with no deduction for structures or fittings, along the pipe flow line from center to center of manholes, inlets, special sections, or the ends of pipe, whichever is applicable.
01025 - 7
1.11 Maintenance of Planting and Irrigation
Payment for all work specified herein will be made as a lump sum price set forth in the contractor’s proposal. Payment will include furnishing all labor, materials, tools, equipment, fencing and incidentals for performing all work necessary for maintaining, mowing, fertilizing the planted areas and operating the irrigation system. Payment will be made in 3 month intervals over the 1 year warranty period.
1.12 Deductive Alternate #1
Deductive Payment (credit) for all work specified herein shall be identified as a lump sum price set forth in the contractor’s proposal. Credit back to owner shall consist of an allowance of $50,000 for the labor, materials, tools, equipment, inspections, work anticipated to test, treat and amend or fix the soil to a usable condition.
1.13 Deductive Alternate #2
Deductive Payment (credit) for all work specified herein shall be identified as a Lump Sum price set forth in the contractor’s proposal. Credit back to owner shall consist of the labor, materials, tools, equipment, inspections, work anticipated to install reduced base rock by
4” for asphalt and concrete surfacing for right of way and onsite work where grass is currently present.
2025-91
Additive
Additive stuttle Text Box #1 stuttle Line stuttle Cloud stuttle Snapshot stuttle Snapshot stuttle Cloud stuttle Snapshot
01025 - 8
END OF SECTION
BID SCHEDULE: Park at Jennings Lodge Campus Bidder is responsible for performing independent quantity take-offs and for verification of all quantities
Description Unit Quantity Price per Unit Total per Item
Sitework Mobilization LS Temporary traffic control LS Temporary erosion and sediment control LS Site clearing, grubbing and demolition LS Site earthwork LS
Pedestrian paving LS Site development LS Landscaping LS
Site utilities LS
Maintenance of planting and irrigation LS
Description Unit Quantity Price per Unit Total per Item
Right of Way Site clearing, grubbing and demolition LS Site earthwork LS
Roadways LS Pedestrian paving LS Site development LS Landscaping LS
Utilities LS
Maintenance of planting and irrigation LS
Total Base Bid (in numbers)
Additive Alternate #1 LS 1 50,000.00$ 50,000.00$ Deductive Alternate #1 CY
Total Bid including alternates (in numbers)Total base bid price in words__________________________________________
Name of Firm____________________________________________
Name Print_________________________________________ Signature________________________________________ dated 7/8/26
| 1. Drawing C0.01 has been modified to indicate Deductive Alternate #1 has been made an Additive Alternate. Remove and Replace Drawing Sheet No: C0.01 (1 Page) |
| 2. The Measurement and Payment section has been modified to indicate Deductive Alternate #1 has been made an Additive Alternate. Deductive Alternate #2 has been renamed to Deductive Alternate #1 and removes its application to the right of way. Remove ... |
| 3. The bid tab has been modified per the above changes and slightly reorganized for clarity. Remove and replace the Bid Schedule with the attached new Bid Schedule dated 7/8/26. |
File details come from the government source that posted it. Updated .