This is a Work Sequence and Constraints document for a construction project involving Clackamas County and the Oak Lodge Water District in Oregon. The document outlines general project requirements and phasing for work that includes site clearing, demolition, excavation, rough grading, installation of drainage and utility infrastructure, electrical work, pathways, flatwork, park features, planting, and right-of-way improvements. Key constraints require that traffic flow be maintained on Wilmot Street and Hull Avenue during construction, and adjacent residential areas must be protected from work-related equipment traffic except as specifically approved. The contractor must maintain overall coordination of work execution, obtain and incorporate schedules from all subcontractors and suppliers into a master progress schedule, and pre-locate existing utilities through exploratory excavation to minimize service interruptions.
Utility service interruptions are permitted only with written authorization from the engineer, and requests must be submitted at least five business days in advance. The engineer will evaluate interruption requests based on utility owner personnel availability and impact to customer service, with the contractor responsible for minimizing interruption duration through advance planning and procurement. All special and material inspections must comply with the latest edition of the International Building Code, requirements of Oak Lodge Water District and Clackamas County, and state of Oregon standards. The document specifies a general work sequence beginning with site clearing and demolition, followed by grading and berming, underground utility installation, electrical work, flatwork and pathways, park features and planting, and finally right-of-way improvements.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DIVISION 1
GENERAL REQUIREMENTS
SECTION 01015 WORK SEQUENCE AND CONSTRAINTS
PART 1
GENERAL
1.1 Scope
A.
This Section describes general constraints to the Work and identifies proposed project phasing, and coordination requirements.
1.2 Related Work Specified and Performed Under Other Sections.
Section/Division No.
Item
01010 Summary of Work
1.3 General Constraints on Sequence and Scheduling of Work:
A.
Traffic flow must be maintained on Wilmot St. and Hull Ave. during construction.
B.
The work area borders adjacent residential areas, which must be protected from all work-related equipment traffic, except as specifically noted on the Plans or approved by County staff prior to any entry.
1.4 Interruption of Utility Service.
A.
Indicate required shutdowns of existing utilities or interruptions of existing operations on Progress Schedule. Interruptions to utility service will be allowed to the extent that service will not be adversely compromised.
B.
Submit requests for interruptions to utility service not less than five business days in advance of the date scheduled for the interruption.
C.
Following receipt of the request, ENGINEER will notify the CONTRACTOR if the requested date will be permitted. Evaluation of the request will be based upon the availability of the utility owners’ personnel to assist and monitor utilities during the shutdown period and impact to customer service.
D.
Minimize the period of interruption by thorough advance planning. Procure required materials, equipment and labor and have on hand during the shutdown.
E.
Do not begin interruption until written authorization is received from ENGINEER.
PART 2
PRODUCTS
A.
Not Used.
PART 3
EXECUTION
3.1 General Requirements for Execution of Work
A.
Maintain overall coordination of execution of Work.
B.
Obtain schedules from subcontractors and suppliers and assume responsibility for correctness.
C.
Incorporate schedules from all parties into Progress Schedule to plan for and comply with sequencing constraints.
D.
Pre-locate by exploratory excavation existing utilities and all proposed connections to existing to minimize service interruption and demands on OWNER’s personnel.
E.
Coordinate and call for any and all special inspections or material inspections as required by the latest edition of the IBC, Oak Lodge Water District, Clackamas County, and the state of Oregon.
3.2 Work Sequence - Below is provided a general outline of a possible sequence of work:
A.
Site clearing, demolition, and excavation of open areas.
C.
Rough grading of open areas and access or walkway areas; berming.
D.
Installation of drainage facilities, water line / meter and any other associated underground utility work, irrigation.
E.
Electrical work.
F.
Pathways and flatwork.
G.
Park features and planting.
H.
Right of Way Improvements.
END OF SECTION
xxx
01015 - 2