B08_Att_10_Hydrant_Flow_Test_1-29-21.pdf

PDF 944 KB Posted

Attached to
DETO 228872 - Replace Obsolete Housing with Multip Federal contract opportunity
Solicitation number
140P2025R0002
Issued by
Department of the Interior National Park Service National Office

About this file

This document is a Fire Hydrant Flow Report for Devils Tower National Monument, conducted by Rapid Fire Protection, Inc. on January 29, 2021. The report details a comprehensive water flow test performed at two hydrant locations near the North Seasonal Housing and South Permanent Housing areas. The test utilized two fire hydrants (A and B) with identical specifications: AD/533-G model from 2008, 2.5-inch nozzle diameter, and a nozzle coefficient of 0.9.

Key test results include a static pressure of 68 PSI, a pitot pressure of 8, and a calculated flow of 474 gallons per minute (gpm) when flowing a single 2.5-inch outlet. The water supply is gravity-fed from a water tank, and the test was conducted to assess water flow capabilities for park housing. The additional Water Flow Test Report provides supplementary analysis, indicating potential flow rates of 923 gpm at 20 PSI residual and 1,114 gpm at 0 PSI, which are critical metrics for fire protection and emergency water supply planning at the national monument.

View the file

Other files for this federal contract opportunity

Other files attached to DETO 228872 - Replace Obsolete Housing with Multip, newest first.
File Type Posted
B09_A0004_Att_Solicitation_QandA_as_of_9-3-2025_0004.pdf PDF
Sol_140P2025R0002_Amd_0004.pdf PDF
B09_A0004_Att_01_91_14_Total_Building_Comm_8-27-25_0004.pdf PDF
A0003_Att_Electrical_Report_of_Contact_0003.pdf PDF
A0003_Att_Geotechnical_Report_0003.pdf PDF
A0003_Att_01_41_50_Special_Inspections_0003.pdf PDF
A0003_Att_Hydrant_Location_0003.pdf PDF
A0003_Att_S101_Foundation_Plan_0003.pdf PDF
A0003_Att_StatementStructuralTestsSpecialInspections_0003.pdf PDF
Sol_140P2025R0002_Amd_0003.pdf PDF
A0003_Att_32_33_00_Site_Furnishings_0003.pdf PDF
A0003_Att_Hazmat_Report_0003.pdf PDF
A0003_Att_Hydrant_Flow_Chart_Graph_0003.pdf PDF
A0003_Att_Hydrant_Flow_Report_0003.pdf PDF
A0003_Att_01_91_14_Total_Building_Commissioning_0003.pdf PDF
A0003_Att_Hydrant_Test_Location_0003.pdf PDF
Sol_140P2025R0002_Amd_0002.pdf PDF
B09_A0002_Att_Proposal_Submission_Package_DETO_228872_0002.docx DOCX document
Sol_140P2025R0002_Amd_0001.pdf PDF
B09_A0001_Att_Prebid_Sign-in_Sheet_(6-17-25)_0001.pdf PDF
B09_A0001_Att_Prebid_Slides_(6-17-25)_0001.pdf PDF
B09_A0001_Att_Q-and-A_as_of_6-23-25_0001.pdf PDF
B08_Att_2_Drawings_(7-24-25).pdf PDF
B08_Att_8_Hazmat_Report_2023-06-06.pdf PDF
B08_Att_3_WD_WY20250003_(01-03-25).pdf PDF
B08_Att_7_Wildfire_Report_2023-06-06.pdf PDF
Sol_140P2025R0002.pdf PDF
B08_Att_1_Specs_(7-24-25).pdf PDF
B08_Att_5_Geotechnical_Report_2020_12_08.pdf PDF
B08_Att_9_Floodplain_Hydrologic_Hydraulic_8-15-24.pdf PDF
B08_140P2025R0002_(7-31-25).pdf PDF
B08_Att_4_Structural_Test_Special_Inspections_12-3-24.pdf PDF
B08_Att_6_Electrical_Report_of_Contact.pdf PDF
Show all 33

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Fire Hydrant Flow Report

Rapid Fire Protection, Inc. Date: 1/29/2021 1530 Samco Rd.

Rapid City, SD 57702 Performed by: SB & BH p: (605) 348-2342 f: (605) 348-0108

Devils Tower National Monument, DETO Project

A B Flow Test Hydrant Pressure Test Hydrant

Pitot Gauge

Set Up A B

Location N. Seasonal Housing Location S. Permanent Housing

Make / Model / Year AD/ 533-G/ 2008 Make / Model / Year AD/ 533-G/ 2008

Nozzle Coefficient 0.9 Static Pressure 68

Nozzle Diameter 2.5 Notes

Test 1 - Flowing single 2 1/2" outlet on Hydrant A

Pitot Pressure 8 Residual Pressure 54

Calculated Flow 474 gpm

Test 2 - Flowing two 2 1/2" outlets on Hydrant A

Residual Pressure Residual Pressure

Total Calculated Flow 0 gpm

Test Procedure:

(1) Attach the gauge to Hydrant (B) and obtain static pressure.

(2) Remove cap from Hydrant (A) and record nozzle coefficient.

(3) Fully open Hydrant (A) and allow water to flow to clear debris. Obtain pitot pressure in stream of water.

(4) While water is flowing from Hydrant (A), record residual pressure on gauge located at Hydrant (B).

0.9 0.8 0.7

Nozzle Coefficients

WATER FLOW TEST REPORT

HYDRANT # & LOCATION: 2, N & S Corners of Site Location DATE: 1/29/2021

TEST BY: RFP, SB & BH Day or Week: Friday TIME OF DAY: 9:00am MIN. OF FLOW:

WATER SUPPLIED BY: Gravity Fed Water Tank

PURPOSE OF TEST: Devils Tower National Monument, Park Housing

DATA

FLOW HYDRANT(S) A1 A2 A3

SIZE OPENING: 2.5 2.5

COEFFICIENT: 0.9 0.9

PITOT READING: 8

GPM: 475 0

TOTAL FLOW DURING TEST: 475 GPM

STATIC READING: 68 PSI RESIDUAL: 54 PSI

RESULTS: AT 20 PSI RESIDUAL 923 GPM AT 0 PSI 1114 GPM

ESTIMATED CONSUMPTION: GAL.

REMARKS:

0 68475 54923 201114 0 C = 0.9D = 2.5P = 8

11140

0 500 1000 1500 2000 2500

P re s s u re p s ig

Flow, gpm

Provided by the:

Life Safety and

Fire Protection Engineering

Section

101 S. Spring St

Little Rock, AR 72201

(501) 372-2900

WATER FLOW TEST REPORT

Provided by the:

Life Safety and

Fire Protection Engineering

Section

101 S. Spring St

Little Rock, AR 72201

(501) 372-2900

Devils Tower Housing, Hydrant Flow Report
Devils Tower Hydrant Location
Devils Tower Test Location
HydrantFlowChart Graph, Devils Tower