B.08.02.06 TECHNICAL SPECIFICATIONS - ENGLISH.PDF
PDF 1 MB Posted
- Solicitation number
- W912GB21R0030
- Issued by
-
Department of the Army European Command
About this file
This is a request for proposal for an electrical system upgrade at Camp Darby in Livorno, Italy. The scope of work includes replacing the medium voltage distribution system with a new 15kV closed loop configuration and upgrading all associated switchgear, transformers, cables, and protection and control systems across multiple substations. A site visit is scheduled for July 15, 2021 from 1000-1200 hours local time, with registration required by July 8. Proposals are due by an unspecified date. The selected contractor will be responsible for architectural, structural, electrical, and mechanical construction work as well as telecommunications integration and environmental mitigation efforts. The U.S. Army is the contracting agency overseeing this project.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE ARMY
U.S. ARMY GARRISON LIVORNO
DIRECTORATE OF PUBLIC WORKS
APO AE 09613
PROJECT
ED 00176‐8
UPGRADE ELECTRICAL SYSTEM
CAMP DARBY (SOUTH)
LIVORNO, ITALY
TECHNICAL SPECIFICATIONS
Consisting of 120 pages and of 1 enclosed
GIANLUCA LUCETTI
Chief, Engineering Services Branch
Prepared by:
STEPHEN L. DONELLY, PE
Director of Public Works
THE OK DESIGN GROUP S.r.l.
ARCHITECTS – PLANNERS
CONSULTING ENGINEERS
VIA ANGELO BARGONI, 78
00153 ROME, ITALY
on Nov 2020 APPROVAL DATE ________________
ED 00176‐8
‐1‐
TABLE OF CONTENTS
SECTION TITLE No. PAGES
Ia GENERAL PROVISIONS
Ib QUALITY CONTROL BY CONTRACTOR
IIa DESCRIPTION OF WORK
IIIa DEMOLITION AND REMOVAL
IIIb EXCAVATION AND BACKFILLING
IIIj REMOVAL AND DISPOSAL OF ASBESTOS CONTAINING MATERIALS
IVa REINFORCED CONCRETE WORK
IVd ELECTRICAL CABINS
Ve MISCELLANEOUS METALWORK
VIIc PAINTING
VIIIb ROOF WATERPROOFING
VIIIc ROOF MEMBRANE MATERIALS
XId REPAIR OF BITUMINOUS PAVINGS
XIIf AIR CONDITIONING SYSTEM
XIIIa ELECTRICAL SYSTEMS
XIIIb TELECOMMUNICATION SYSTEM
XIIIc EXTERIOR ELECTRICAL SYSTEM
Ia‐1
SECTION Ia
GENERAL PROVISIONS
1a‐01 WORK PHASING.
a. Work Schedule. Whenever the nature of the contract and the work location are such that the work is to be performed in an area assigned to activities and services that cannot be interrupted, work shall be scheduled with concurrence of COR in such a manner as to cause the least possible inconvenience to the normal operations of mentioned activities and services. Contractor shall submit his proposed work schedule to the COR at the time of the pre‐construction conference. Work start shall be contingent upon schedule approval.
b. Utilities Cut‐Offs. As a rule, cut‐off of power and other utilities (water, sewage, heating system, etc.) is not allowed. All temporary connections necessary to insure continuous power distribution shall be provided. If cut‐offs are necessary, they shall not exceed the period of time strictly needed to make the temporary connections. Cut‐off shall be scheduled with the COR not less than 15 days ahead of time.
c. Alarm, Telephone and Televisions Systems. Deenergizing of alarm, telephone and television systems is strictly prohibited. Should these systems, which may not appear on the drawing interfere with the contract work, they shall be temporarily diverted and fed by means of temporary connections to be adequately protected. Written approval must be obtained from COR prior to doing any temporary work.
d. System Reactivating. At the completion of the work, all existing systems, including water, electrical and heating systems, shall be reactivated and placed in their original locations.
e. Temporary Protections. Floors, carpets, and equipment that cannot be removed shall be adequately protected by temporary tarpaulins to be furnished and installed at no cost to the US Government. In addition, temporary protections shall be furnished and installed in some particular areas so as to allow performance of activities that cannot be interrupted or transferred. Also, the Contractor shall be responsible for removing, protecting, and reinstalling all furniture, shelves and furnishings that may interfere with the work course.
A wrong or no evaluation of all requirements specified above does not constitute grounds for a request for additional compensation.
1a‐02 JOBSITE CLEAN UP AND DUST CONTROL. The contractor shall have sufficient trash/waste bins on site, and shall clean the worksite so that all discarded materials, debris and trash are placed in these bins at the end of each workday, and not left or allowed to accumulate anywhere else on the jobsite. These waste bins shall not be allowed to overflow with debris, and shall be emptied as soon as they become full. Haul roads shall be watered sufficiently to prevent excessive dust.
Ia‐2
The work area shall be swept regularly to prevent accumulation of debris. Equipment, construction materials and excavated soil shall be stored in a safe and orderly manner on the jobsite, in accordance with the contractor's approved area use plan.
1a‐03 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT. The contractor is considered the waste generator of all salvage, re‐usable, re‐cyclable and disposable materials derived from the demolition and removal works included in this contract and shall handle these materials as hereinafter indicated.
a. Salvage Material. All salvage end items that the COR will have considered in good operating conditions shall be disassembled without damage, cleared of all dirt and scaling and then transported to the DPW Warehouse, Building 5156, Depot, where they shall be handled over undamaged.
b. Recyclable Material. All construction and demolition recyclable waste material shall be delivered to authorized treatment facilities by the contractor.
c. Special Waste. All special waste, either hazardous or not hazardous, shall be delivered by the contractor to authorized disposal facilities.
d. Waste Storage. Construction and demolition waste shall be stored in waste specific containers provided by the contractor. Containers will be in good conditions, free from severe rusting, bulging, or structural defects. Containers shall be placed in area identified by COR. Containers shall be removed once full or on COR’s decision.
e. Certificates and Authorizations.
(1) Recyclable Materials. As regards to recyclable materials, the Contractor shall submit copy of the authorization of the treatment facility which they are delivered to and will certify that waste have been removed in compliance with applicable law requirements.
(2) Disposable Materials. As regards to material delivery to disposal facilities, the contractor will provide the COR and DPW Environmental Office with copies of the following documents:
Authorization to transport construction and demolition waste;
Authorization of the landfill;
4th copy of Formulario di Identificazione del Rifiuto.
(3) Waste Manifest. All transported waste will be accompanied by the Formulario di Identificazione del Rifiuto (waste manifest) to ensure a complete audit trail from point of origin to ultimate disposal.
Ia‐3
The waste manifest must be completed in quadruplet, all dated and signed by the waste generator and countersigned by the transporter. The first copy of the manifest will remain with the waste generator; of the remaining three copies, (countersigned and dated by the receiver), the second copy will remain with the transporter, the third copy will remain with the receiver, and the fourth copy must be returned by the transporter to the waste generator within 3 months of delivery of the waste to the disposal/treatment facility.
f. Costs. All operations included in this paragraph shall be carried out by the contractor with no additional cost to the US Government.
1a‐04 AUTHORIZATION FOR INSTALLATION OF MATERIAL AND EQUIPMENT. Before installing any material or equipment mentioned in the specifications, approval shall be obtained from the COR. Contractor shall submit material samples, shop drawings, manufacturer's literature, etc., to the COR 10 days prior to installation and shall proceed with installation only after receiving written approval from the COR. All material installed without COR's approval shall be removed.
1a‐05 ISPESL AND CEI STANDARDS. All work described in these specifications shall be accomplished in strict compliance with the ISPESL (Superior Institute of Prevention and Assurance of Work) and CEI (Italian Electrotechnical Committee) standards. In particular, if the work under contract, such as roof repairs, building painting, etc., may cause Contractor's personnel or other individuals to come in contact with non insulated electric lines, these shall be temporarily protected by use of appropriate spiral plastic tubes available on the market.
1a‐06 TRANSLATION AND TITLE ABBREVIATION. The terms COR and "Direzione dei Lavori" used in the Italian version of these specifications are equivalent to the American term "Contracting Officer's Representative," which in the English version is indicated by the letters
COR.
1a‐07 PERMITS AND CHARGES. The following authorizations or practices are needed, prior to starting work, to require from entities outside the United States Government:
Permissions for the search and/or demining of explosive devices to request at the military authorities responsible for the territory (5th DGM Padova), see chapter 3b‐04.
Costs for requests and granting authorizations mentioned above are totally in charge and at the expense of the contractor, who must first find out from the institutions required, provide all the necessary documents and pay all fees required.
1a‐08 DIGGING PERMIT. The Contractor shall obtain a digging permit for all work areas affected by this contract (to insure that all the as‐built information for underground services is received). This permit and related drawings must be received by the Contractor prior to starting any work. After receipt of the digging permit, the Contractor shall immediately notify, in writing the Contracting Officer of the permit receipt.
Ia‐4
The Contractor will be held responsible for any damages caused to existing services, as indicated on the digging permit and related drawings, and will repair such damages at his own expense.
1a‐09 ASBESTOS. No handling of asbestos containing material is included in this project. Use of asbestos containing materials is forbidden.
1a‐10 PARTICULAR REQUIREMENT FOR WORK IN HEATING PLANTS. When the contract requires the work to be performed inside heating plants, the contractor shall provide a new cylinder in the door lock and shall deliver two keys of the new cylinder and the removed cylinder to the personnel in charge of the maintenance. At the work end the contractor shall restore the lock to the original conditions and the temporary cylinder will remain his own property.
1a‐11 ANTI‐TERRORISM TRAINING. The Contractor shall comply with the following security requirements:
a. AT Level I Training. All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date.
The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR within 10 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website: httQ://jko.jten.mil.
b. OPSEC Training. According to AR 530‐1, new contractor employees must complete Level I OPSEC training within 30 calendar days after they report for duty. All contractor employees must complete annual OPSEC awareness training.
The contractor will develop an OPSEC standing operating procedure (SOP)/plan within 90 calendar days after the contract is awarded, to be reviewed and approved by the responsible Government OPSEC officer, according to AR 530‐1. This SOP/plan will include the Government’s critical information, why it needs to be protected, where it is located, who is responsible for it, and how to protect it. The contractor will ensure this individual becomes OPSEC Level II certified according to AR 530‐1.
c. Access and general protection/security policy and procedures. Contractor and all associated sub‐contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office.
Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204‐9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy.
Ia‐5
In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
d. iWATCH Training. The contractor and all associated sub‐contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO).This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 40 calendar days after contract award.
1a‐12 ENVIRONMENTAL PROTECTION SYSTEM. The contractor will provide the following information semi‐annually to be used by the Government to address environmental performance relative to the goals of the USAG Vicenza Environmental Management System.
Please note that the amounts reported are those used/generated by the contractor regardless of source (private purchase or government furnished). Reports for January – June will be submitted by 15 July and reports for July‐December will be submitted by 15 January each year.
Media Report Element #1 Report Element #2
Non‐Hazardous Solid Waste
Total Waste Generated (Kg)
Amount of Waste Diverted from Landfill (Kg)
Construction Debris/Demolition Materials
Total Waste Generated (Kg)
Amount of Waste Diverted from Landfill (Kg)
Compostable/Organic Material
Total Waste Generated (Kg)
Amount of Waste Diverted from Landfill (Kg)
Hazardous Materials Total Used (Kg)
Hazardous Waste Total Generated (Kg) Total Recycled (Kg)
Energy Consumption ‐ Electricity
Total Energy Consumed (MBtu)
Energy Consumption ‐ Fuel
Total Fuel Consumed (L)
Renewable/Alternative Energy
Total Consumed (MW)
Facility Construction/Renovation
Number of Buildings LEED Certified Silver or Higher
SqFt of buildings LEED Certified
Ib‐1
SECTION Ib
QUALITY CONTROL BY CONTRACTOR
1b‐01 GENERAL. The Contractor shall establish and maintain an effective quality control system to implement the requirements of contract clause entitled "Inspection of Construction (July 1986)". The quality control system shall comprise plans, schedules, and organization necessary to provide materials, equipment, workmanship, manufacture, construction, and operations which comply with contract requirements and shall identify personnel and forms to be used. The system shall cover construction operations, both indoors and outdoors, and shall be in accordance with the proposed construction sequence.
1b‐02 COORDINATION MEETING. As soon as practicable after receipt of Notice to Proceed and before start of construction, the Contractor shall meet with the Contracting Officer's Representative (COR) and discuss the Contractor's quality control (CQC) system. During the meeting a mutual understanding of the system details shall be developed including the forms for recording the CQC operations, control activities, testing, administration of the system for both indoors and outdoors construction, and the interrelationship of Contractor's inspection and control with the Government's inspection. Minutes of the meeting will be prepared by the COR and forwarded to the Contracting Officer who will make them a part of the contract file.
There may also be other subsequent meetings will be called to reconfirm understandings.
Minutes of these meetings will also be forwarded to the Contracting Officer.
1b‐03 QUALITY CONTROL PLAN.
a. Prior to starting the construction, the Contractor shall furnish his CQC plan through the COR to the Contracting Officer for acceptance. Construction will be permitted to begin only after acceptance of the CQC plan or approval of that portion of the plan applicable to the particular feature of the work to be started. The QC plan proposed by the Contractor shall identify personnel, procedures, instructions, records and forms, and, as a minimum, shall include:
(1) A description of the quality management organization.
(2) The names, qualifications, duties, responsibilities, and authorities of each person assigned a quality control (QC) function.
(3) A copy of the letter to the QC manager, signed by an authorized official of the firm, which describes the responsibilities and delegates the authorities of the QC manager.
(4) Procedures to perform QC over other activities including subcontractors, manufacturers, and suppliers.
(5) Control testing procedures for each specific test.
(6) Reporting procedures for QC including proposed reporting formats.
Ib‐2
b. After approval of the QC plan the Contractor shall notify the Contracting Officer in writing of any proposed change to his QC plan. Proposed changes are subject to acceptance by Contracting Officer.
c. The acceptance of the QC plan is conditional and will be predicated on a satisfactory performance during the construction. If it is determined that the QC plan, personnel, instructions, controls, tests or records are not providing a construction conforming to contract requirements, the Government will reserve the right to require the Contractor to make changes in his QC plan and operations, as deemed necessary to obtain the specified quality. Any changes required to the plan will be made at no cost to the Government.
1b‐04 QUALITY CONTROL ORGANIZATION.
a. The Contractor shall identify an individual within his organization at the site of the work who shall be responsible for overall management of CQC and have the authority to act in all CQC matters for the Contractor.
b. A staff shall be maintained under the direction of the system manager to perform all QC activities. The actual strength of the staff during any specific work period may vary to cover work phase needs, shifts and rates of placement. The personnel of his staff shall be fully qualified by experience and technical training to perform their assigned tasks, and shall be directly hired by and work for the prime Contractor.
1b‐05 SUBMITTALS.
a. The Contractor shall develop procedures for purchasing materials and equipment, subcontracting, and processing shop drawings, samples, certificates, and other submittals. This procedure shall include the establishment of responsibilities to assure, at each level, adequate review and approval, timely delivery including verification procedures, and proper storage.
Submittals of the shop drawings and/or manufacturer's data shall be, as specified, in accordance with contract clauses entitled "Materials and Workmanship" and "Shop Drawings."
b. Actions shall be taken to ensure that only materials and equipment which comply with contract requirements are purchased and delivered to the job site or used in off site fabrication, unless specific deviations are approved, as specified hereinafter. The COR may request a copy of the document of transportation of the provided material.
c. The Contractor shall review the contract requirements and verify that submittals are confirming to contract compliance. Within 10 days after receipt of notice to proceed, the Contractor shall submit a submittal control document listing and scheduling all submittal items required in the contract. This document shall be in duplicate and shall be addressed through the COR to the Contracting Officer. The control document shall include such items as construction schedules, monthly progress reports, shop drawings, manufacturer's literature, certificates of compliance, material samples, and guarantees.
Ib‐3
The document shall schedule for each item the dates of submittals. The scheduling of submittals shall be coordinated with the approved progress schedule; the information contained therein shall be reviewed and updated at each schedule update. Adequate time shall be allowed to the US Government for approval of submittals. The Contractor shall review the listing at each progress schedule update and copies of updated documents shall be submitted through the COR to the Contracting Officer in the specified quantity. Payments to the Contractor will not be made for material or equipment which does not comply with the Contract requirements.
d. The CQC organization shall be responsible for certifying that all submittals are in compliance with the contract requirements. Submittals to the Contracting Officer without evidence of the certification will be returned for resubmission.
e. The Contractor shall submit copies of all submittals through the COR to the Contracting Officer.
f. Delays in the approval process shall not be the basis for consideration of a time extension when such delay is the result of the Contractor's failure to make proper and timely submittal, or make corrections in accordance with the specifications or the Contracting Officer's comments, or is a result of a resubmittal which is required because of an unsatisfactory original submittal. Approval action by the Contracting Officer will not relieve the Contractor of his responsibility for compliance with the contract but will indicate only that the general method of construction and detailing is satisfactory.
g. All proposed deviations from contract requirements shall be submitted in writing for approval by the Contracting Officer.
1b‐06 CONTROL. Quality control is the means by which the Contractor assures himself that his construction complies with the requirements of the contract plans and specifications. The QC system shall include at least the following three phases of control and management for all definitive features of work:
(1) Preparatory. This control phase shall be performed before beginning work on each definable feature of work. It shall include a review of contract requirements to assure that materials, sample, and equipment conform to contract requirements and that control testing procedures are finalized. The control shall also include examination of the work area to verify that structures over which new work is to be placed conform to contract requirements;
Contractor shall also verify that the required materials be on hand and properly stored. The COR shall be notified at least 24 hours in advance of each preparatory activity.
(2) Initial. This phase of control must be accomplished as soon as a representative portion of the particular feature of work has been accomplished and shall include examination of the quality of workmanship and a review of control testing for compliance with contract requirements, identification of defective or damaged materials, omission, and dimensional requirements.
Ib‐4
The COR shall be notified at least 24 hours in advance of the initial inspection and such inspection shall be made a matter of record in the CQC documentation.
(3) Follow‐Up. The follow‐up phase shall be performed continuously to verify that control procedures are providing an end product which complies with contract requirements.
Adjustments to control procedures may be required based upon the results of this phase.
(4) Completion. At the completion of all work or any increment, the CQC representative shall conduct a joint review with the COR. During this review the work shall be examined, quality control shall be examined, and a list shall be developed of work not properly completed or not conforming to plans and specifications. This list shall be included in the quality control documentation with an estimated date for correction of each deficiency. The Contractor shall make sure that deficiencies be corrected prior to the contract completion date. Payment will be withheld for defective or deficient features until they are satisfactorily corrected except as otherwise provided in the contract.
1b‐07 TESTS.
a. The Contractor shall perform tests specified or required to verify that control measures are adequate to provide a product which conforms to contract requirements. The Contractor shall procure the services of an industry recognized testing laboratory or he may establish an approved testing laboratory at the project site. A list of tests which Contractor believes necessary shall be furnished to the COR. The list shall give the test name, specification paragraph containing the test requirements, and the personnel and laboratory responsible for each type of test. The Contractor shall perform the following activities and provide the following data:
(1) Verify that the testing procedures comply with contract requirements.
(2) Verify that facilities and testing equipment are available and comply with testing standards.
(3) Check test instrument calibration data against certified data.
(4) Verify that recording forms including all pertaining documentation have been prepared.
b. Testing.
(1) The Contracting Officer reserves the right to check laboratory equipment in the proposed laboratory for compliance with the standards set forth in the contract specifications and to check the laboratory technician's testing procedures and techniques.
(2) The Contracting Officer reserves the right to utilize the Contractor's control testing laboratory and equipment to make assurance tests and to check Contractor's testing procedures, techniques, and test results at no additional cost to the Government.
Ib‐5
(3) Cost incidental to the transportation of samples or materials will be borne by the Contractor.
1b‐08 DEFECTIVE WORK. The Contractor shall not build upon or conceal a defective work.
1b‐09 DOCUMENTATION.
a. The Contractor shall maintain current records, on an appropriate form, of quality control operations, activities and tests performed including the work of suppliers and subcontractors. These records shall include factual evidence that the required activities or tests have been performed, including but not limited to the following:
(1) Type and number of control activities and tests involved.
(2) Results of control activities or tests.
(3) Nature of defects, causes for rejection, etc.
(4) Proposed remedial action.
(5) Corrective actions taken.
b. These records shall cover both conforming and defective or deficient features and shall include a statement saying that supplies and materials incorporated in the work comply with the contract. Legible copies of these records shall be furnished to the COR weekly. The records shall cover work performed during the time period for which the records are furnished and shall be verified by persons designated by the Contractor.
IIa‐1
SECTION IIa
DESCRIPTION OF WORK
2a‐01 STATEMENT OF WORK. Contractor shall furnish all plants, labor, equipment, material and transportation necessary for the accomplishment of the work described in these specifications and shown on drawings, both of which are an integral and binding part of the contract. This specification is referred to Batch#1.
2a‐02 DESCRIPTION OF THE WORK. The project consists in the replacement of the existing electrical main distribution system of the Camp Darby South.
Project includes the provision of new communication cable ducts with fiber optic cable which integrates the existing communication system.
New substation control system will be connected to the existing central control workstations at buildings #5112 (DCO), #5155 (PWO) and #5140 (Electrical Shop). These workstations will be updated with the required hardware and software to include all the substations included in this project.
A new monitoring system will be also provided at the Camp Darby Communication node building #204 for the monitoring and tele‐control of the substation’s equipment from a centralized station.
The project includes the UXO inspection procedures for the removal of the unexploded ordinance.
ARCHITECTURAL
All the existing equipment inside the substations including through wall fan and louver will be repaired by replacement and then the interior walls shall be patched to repair holes and cracks and painted with two coats of white distemper paint. Works will include:
‐ All architectural works required for the construction of the new prefabricated concrete substation SS#118 and SS#776;
‐ Patching and painting all substations and repair of architectural and/or structural deficiencies of all the renovated substations;
‐ All the existing equipment inside the substations including through wall fans shall be repaired by replacement, and then the interior walls and ceilings shall be patched to repair holes of the fans not more used and cracks and painted with two coats of white distemper paint;
‐ The exterior walls shall be also patched and painted using quartz paint with synthetic resins, quartz powders and additives;
IIa‐2
‐ Roof of all renovated substations shall be restored by complete removal of the existing waterproofing membranes, and application on the precast‐reinforced concrete elements, of two ply bituminous waterproofing membrane, the top one self protected with slate chips. Existing flashing will be also replaced, or new flashing will be provided were missing;
‐ Concrete floors of the renovated substations shall be also restored by the application of a suitable resin product;
‐ All doors of the substations shall be cleaned and repaired.
STRUCTURAL
‐ Structural work includes mainly the reinforced concrete pad for the new prefabricated substation and minor structural work which support the electrical cable duct installation.
MECHANICAL
‐ Mechanical work includes mainly the provision of new air conditioning systems inside all transformer substation.
ELECTRICAL
‐ Electrical work includes mainly the provision of a two completely new transformer substations (#118 and #776), the replacement of all direct buried medium voltage cables with new cable installed in cable ducts, the replacement of all medium and low voltage switchgears, replacement of all medium/low voltage transformers, new power factor compensating units, new relays and tele‐control system, and accessories in all substations.
The required works are, but they are not limited to, the following:
‐ Convert the existing 10kV distribution system of the Darby South area in a new 15kV closed loop; modify/integrate MV switchgears in Bldg 807 am in bldg. 808 accordingly.
‐ Replace all the existing MV cables with new cables suitable for 15kV operation. The new cables shall run into new underground cable ducts and, or in new one indicated, into the existing ducts. Remove the existing 10kV cables wherever possible.
‐ Replace all the existing MV panels in all the substations. New panels shall be suitable for the new Voltage level (15kV). MV circuit breakers shall be motorized and complete with electronic relays suitable to be connected to a communication network, to allow the remote control of the breaker (open/close), the remote setting of each circuit breaker (trip setting) and the remote monitoring of all the electrical characteristics (Voltage, Amps, Active Power, Reactive Power, Power factor, etc.).
IIa‐3
‐ Replace all the existing transformers currently having 10kV primary winding; new transformers shall be resin insulated type, 15kV primary winding; secondary windings shall be 400V and 230V as indicated.
‐ Replace the LV panels of all the substations. New LV panels shall be composed by circuit breakers with electronic relays, having protection and measurement functions. Main LV breakers shall be motorized. LV circuit breakers shall be suitable to be connected to a communication network, to allow the remote setting of each circuit breaker (trip setting) and the remote monitoring of all the electrical characteristics (Voltage, Amps, Active Power, Reactive Power, Power factor, etc.). New LV panels shall be suitable for being fed through emergency generators (purchasing and installation of generators is excluded by the scope of work).
‐ Replace the interior electrical system for the services of each transformer station (lighting, power, emergency shutdown, etc.)
‐ Replace the fixed and automatic power factor compensators in each transformer station as indicated.
‐ Provide physical separation of the MV cables and LV cables. Install new manholes and cable ducts in order to avoid MV and LV cables sharing the same manholes or conduits.
‐ Install new LV cables ducts and cables where necessary in order to have each building fed with 1 dedicated circuit breaker and 1 dedicated cable. Reconnect the existing cables to the new LV panels as much as possible. Convert all the existing TN‐C distribution into TN‐S.
‐ Verify the existing grounding system of every substation and integrate/upgrade/modify it if necessary.
‐ Connect each substation to the existing communication duct system; new cable ducts shall be installed from the existing communication manholes up to each substation.
‐ Install a new communication architecture dedicated to the renovated electrical system. New communication architecture shall be composed by new dedicated fiber optic cables, to be routed inside the existing and new cable ducts, and new communication equipment inside each substation, in order to:
‐ Control the motorized MV and LV circuit breakers ‐ Monitor the electric parameters measured by the MV and LV circuit breakers, as well as the alarms relative to faults.
‐ Monitor the Transformers temperatures and alarms ‐ Monitor the UPSs status and alarms ‐ Monitor the Air Conditioning Units status and alarms
IIa‐4
One dedicated workstation for the electrical system monitoring and control is currently present in bldg 5155 (PWO) and one in bldg. 5140 (electrical shop), installed with a similar project involving the electric substations of Depot Area. These workstations shall be updated to include all the substations subject of the present project, integrating adequately the existing hardware and software in order to have a fully operating system.
‐ Electrical work includes a detailed study and calculations based on the equipment selected of:
suitable TA and TV, in accordance with CEI 0‐16 connection point‐to‐point and programming of the relays short circuit currents calculations (radial configuration, with main supply at compensated neutral and isolated neutral, capacitive currents) performed by skilled technician designated by the Protection Relay Manufacturer selectivity study of the relays, including main substation supervision of protection operational tests.
The relay setting study shall be performed on the basis of an official letter from the Commercial Power Company dated no more than three months before the study.
CIVIL
‐ Civil work includes mainly the excavation and grading along new cable duct run, and some minor ground works.
ENVIRONMENTAL IMPACT MITIGATION WORK.
‐ Mitigation works are provided by this project to reduce the impact of the electrical upgrading; mitigation includes the demolition of three existing abandoned building to compensate the loss of area for construction of two new larger substation and new manholes and special attention to reduce noise, etc.
‐ Contractor shall pay attention to the instruction foreseen in the Work Schedule attached to the “Piano di Sicurezza e Coordinamento”.
2a‐03 PHASING.
1. Before starting work the contractor shall perform an accurate check of the contract documents, shall submit for approval the material, the equipment and the shop drawings, shall inspect the site and the substation; shall request the permits for excavation. Contractor shall request the official letter of the electrical parameters at the power delivery point by the commercial power provider (ENEL) and shall submit the qualification resume of the technician which shall perform the protection and selectivity study of the medium voltage network.
2. Contractor shall investigate the location of underground service lines, submit for approval a trenching plan, and then perform the signalization of the cable duct trenching with suitable marks. In addition the Contractor shall verify the cables TNC from the substations to the loads for next integration of cables needed for the TNS system.
IIa‐5
3. Work shall be started with "UXO" procedure and in accordance with requirements of "VINCA" about allowed period of construction. Works in all areas cannot be started until completion of "UXO" procedure and receipt of notification of official approval by the 5th department infrastructure of Padova.
4. Start trenching from SS#808 as indicated on the drawings, provide a temporary substation adjacent each substation, connect the existing load to temporary substation, disconnect the existing loads and provide removal and demolitions as indicated on contract drawings. Perform all architectural, structural, electrical and mechanical works in the substations and install medium voltage, low voltage (extension of cables and addition to obtain the TNS system) and signal cables in the cable ducts from substation SS#808 to all, and from all the substations and close the loop in substation 808. Provide signal connections of the relays and communication devices and perform the temporary setting of the protection relays. Perform the grounding tests and submit the results to c.o.
5. Perform phasing as detailed in the contract drawing E‐3 “Work Phasing Notes”.
At the completion of the work in all substations provide the adjustment of the relay setting and perform the final test of the overall network a presence of the technician designated by protection relay manufacturer. Provide al the as‐built drawing and certifications as per requirements of contract documents
2a‐04 SAFETY DURING CONSTRUCTION. The project is performed assuming the possible presence of more than one firm, also not at the same time, on the work place, as per paragraphs 3 and 4 of art. 90 of Legislative Decree 81/2008. The “Piano di Sicurezza e Coordinamento” (safety and coordination plan) is included as part of the contract documentation. The Contractor shall provide his/her own “Piano Operativo di Sicurezza” (operational safety plan) and comply with the requirements of the mentioned Law in all applicable parts.
All the connection and disconnection works of the electrical cables shall be executed in compliance with the procedures included in the D.lgs 81/10 art.82. A special requisite refers to the disconnection of the medium voltage cables that shall be performed by skilled operators provided with personal certification as per requisites of decree 04/02/2011. The cables, once the disconnect switch ahead and downstream are open, shall be grounded to drain the capacitive residual charge before any handling.
The contractor will be required to obtain the approval to perform the UXO survey, perform the UXO survey and have the results certified by the 5th division in Padova, in compliance with all Italian laws in force and the provisions contained in the security plan in the design phase (see also the PSC). The inspector must be certified in the Italian roles authorized to perform this work. All request and certification packages must be prepared by the Contractor, including payment of any fees for submission to the competent Italian authorities and transmitted via the COR.
IIa‐6
2a‐05 EMERGENCY SITUATIONS. Contractor will maintain the following documentation available and usable at the work site, to be provided by the COR:
- A copy of the Camp Darby Emergency Plan, to which contractor will refer in the case of the emergency conditions indicated in the plan itself.
- Base Grid Coordinates layout, with the work site highlighted.
- List of emergency telephone numbers.
2a‐06 PROJECT IDENTIFICATION SIGN. The contractor shall supply and install a sign identifying the project. The sign shall be of high‐resistant plywood for outdoor installation, white painted. The dimensions shall be 1200x2400x12 mm. The letters of the wording shall be uppercase, black color, 5 cm high, except the letters of the project title which shall be 10
cm. The sign shall be fixed to a structure made of any material provided it is lasting and in compliance with all safety requirements. The sign shall be well visible, with the lower side at
1.2 m from ground level.
IIIa‐1
SECTION IIIa
DEMOLITION AND REMOVAL
3a‐01 GENERAL. Demolition and removal shall be performed in compliance with low prescription of D.Lgs No. 81, 9 April 2008 and U.S. Army Corps of Engineers “Safety and Health Requirements” Manual EM 385‐1‐1. Breakups of predetermined dimensions and partial or total demolition of masonry and concrete surfaces, floor, etc., must be performed in a workmanlike manner, by taking the necessary precautions or by shoring the surfaces in order to avoid damages to the structures to be left in place, accidents, inconveniences or interference. Waste material shall not be thrown down, but rather, it shall be conveyed or guided downward, after wetting it to prevent raising dust. During demolition or removal work, the Contractor shall adopt every measure suitable to avoid deterioration of the items which may be reinstalled, or which, in the opinion of the COR, may be used at a later date.
These items shall be cleaned, guarded, hauled and set neatly in the storage areas indicated by the COR. The demolition work shall be limited to the work, or to its parts, and to the dimensions specified. Reconstruction of structures demolished over and above the quantities indicated, as well as rehabilitation of work damaged as a result of lack or omission of precautions or shoring, shall be performed by the Contractor. All waste material resulting from demolition and removal shall be handled by the Contractor in accordance with para. 1a‐ 02 of these specifications. Oil transformers shall be emptied, before transportation, following the procedure required by Italian Law and Base regulations. All the areas surrounding the transformer substations and along cable duct run shall be left clean and as previous condition.
3a‐02 REMOVAL OF EXISTING PLANTS. Any necessary cutting and removal of vegetation shall be carried out manually, with the help of cutting tools, chain saws, bush grubbers, to be directly controlled by men. Cutting shall skim the soil as much as possible and be followed by choice and stacking of the debris, loading, transport and unloading in specific disposal areas as identified by the COR, to be carried out by the Contractor; then shall be also removed the radical apparatus.
IIIb‐1
SECTION IIIb
EXCAVATION AND BACKFILLING
3b‐01 EXCAVATION.
a. General. During excavation, material suitable for backfilling shall be piled at a sufficient distance from the banks of the excavation to avoid backslides. All earthy material in excess or unsuitable for backfilling shall be delivered to the location indicated by the COR and within 10 km from work site. This does not apply to debris and rubble of all types, from which excavation material shall be rid of; these shall be disposed of at a dump, as prescribed at paragraph 1a‐02. Particular attention is required during the autumn and winter seasons and in case of special storm events when the water is outcropping on the ground and the excavation operations must still take place with appropriate techniques implemented by the Contractor in compliance with the safety regulations and at Contractor’s expense. In case excavation is performed in presence of water and water level is below 20 cm height, the contractor shall remove water at his expense using the means he deems suitable. If water reaches higher levels, removal shall still be at contractor's expense only if the possible presence of groundwater is indicated on the drawings or in these specifications, and only to the extent indicated. In addition, the contractor shall prevent the access of water deriving from outside to the excavation site: in case water accumulates in excavated area, removal will be at contractor's expense. Struts and shoring shall be placed as necessary for the protection of the work and for the safety of personnel. Adequate precautions shall be taken for the protection of existing underground pipelines or electrical cables. Before any excavation is started, plans showing the approximate location of underground utility lines shall be furnished to the Contractor, upon his request. The area of excavation shall be delimited by trestles, gangplanks, and warning signs visible during night and day, to prevent injuries to persons, as prescribed by the ISPESL standards.
b. Trenches. Trenches shall be of the necessary width for the proper laying of the pipes and electric cables, and the banks shall be as nearly vertical as practicable. The bottom shall be accurately graded so as to provide bearing for the pipe on firm soil. The clear space between the pipe and the trenches wall shall not exceed 8" (20 cm.) on either side of the pipe.
Further excavation will be required for housing and sealing of pipe joints. In proximity of buildings, existing underground utility lines, and wherever specifically requested in other sections of these specifications or on drawing notes, trenches shall be excavated manually.
c. Excavation for Foundation and Appurtenances. Excavation for manholes and similar structures shall be of sufficient dimensions as to leave a 12 inches (30 cm.) free space between their outer surfaces and the embankment or timber which may be used to hold the banks.
IIIb‐2
3b‐02 BACKFILLING. Trenches shall not be backfilled until foundation, pipes or cables have been inspected and approved. Where, in the opinion of the COR, damage is likely to result from withdrawing of shoring, the latter shall be left in place. Trenches shall be backfilled with the excavated materials, if deemed suitable, free from large clods of earth, stones, and roots.
Backfilling material shall be deposited in 15 cm. (6") layers, thoroughly rammed until the trench is completely covered, and watered as necessary. Any material rejected by COR shall be replaced with material acceptable to the COR, coming from borrow pits located outside the US military base.
3b‐03 REPAIRS. All crossings of existing paved or asphalt coated surfaces shall be cut neatly vertical and horizontal. At the completion of the work, pavement and sidewalks shall be restored to the original conditions. Damaged lawns shall be sown again and damaged plants shall be replaced with others of the same kinds. Any damage caused during the work progress shall be repaired by and at the expense of the Contractor. The Contractor shall be responsible also for injuries caused to persons as a result of non‐compliance with prescribed ISPESL norms.
3b‐04 CLEARANCE OF EXPLOSIVE DEVICES (U.X.O.). The search for unexploded ordnance shall be performed by the Contractor in the areas indicated in the PSC and Contract drawings. All activities of land clearance will be performed according to the prescriptions issued by the military authorities competent for territory, the 5th “Reparto Infrastrutture Direzione Genio Militare di Padova, Sezione B.C.M.”. In the project are indicated the areas to be inspected as specified in the Safety and Coordination Plan; for the bid purpose a range of +/‐ 10% on the linear excavation shall be considered without additional expenses by Government. If it become necessary to deviate the excavation outside the strip surveyed for the UXO procedure, Contractor must notify the Contracting Officer submitting adequate documentation of the motivation of the deviation and the plan of the new proposed route.
For the issue of opinion and permit of land clearance service the Contractor presents, on behalf of the Government of the United States, a request to the territorial jurisdiction of the Infrastructure Department. The request shall be enclosed with:
‐ chorography and floor plans that indicate the areas on which they will be carried out the activities of explosive clearance;
‐ report describing the main work to be performed;
‐ geological report;
‐ name of the specialist B.C.M. company that will perform the search operations, which must be duly registered in the register of authorized companies;
Upon receipt of request the Infrastructure Department issues the obligatory assessment and related technical requirements within approximately 30 days. In accordance with the assessment the company perform the design of land clearance, implementing faithfully and in detail the technical requirements issued by the Infrastructure Department, referring them to the specific area to be cleared.
IIIb‐3
Research activities and the unveiling of explosive remnants of war will begin only upon approval of the design by the Infrastructure Department, with following release of permit within 30 days. At land clearance completed the company B.C.M. issues the declaration of guarantee that sends the Infrastructure Department which provides to carrying out checks and inspections of the work performed. Subsequently it is released within 60 days from the same Military Authority, the minutes of assessment that allows the practicality of the area for the construction of future works.
NOTE: In addition to above requirements, before starting the excavation, the Contractor must investigate with a metal detector furnished by himself the location of existing underground utility lines, e.g. electrical, communications, water, TV lines, or any other utility which may not be shown on the existing condition drawings, in order to prevent damaging or interrupting any existing utility. Investigation shall be done in the presence of the COR. Trial runs shall be done with the metal detector in the presence of the COR or his representative prior to the investigation. Investigation shall be done following COR approval of metal detector. The Contractor shall mark‐up on a copy of the existing conditions the exact field location of the existing utility lines which are found during excavation. This copy shall then be submitted to the COR. Excavation work performed close to existing utility lines shall be done by hand within a 3 meter radius.
IIIj‐1
SECTION IIIj
REMOVAL AND DISPOSAL OF ASBESTOS MATERIALS
3j‐01 CONTRACTOR QUALIFICATIONS FOR PERFORMANCE OF WORK. Due to the highly specialized nature of this work and the health hazards involved with execution, only personnel experienced and trained in asbestos work will be allowed to perform these service. To perform this work the Contractor must be authorized to perform removal, collection, transportation, treatment and disposal of material containing asbestos in accordance with all requirements and applicable publication and laws.