Attachment C4 - LAS Schedule_r7_230125 - 1 pg.pdf
PDF 151 KB Posted
- Attached to
- 751/20015. TAP; Newberry Customer Service Center
- Solicitation number
- RFP - 171 - 230000001121
- Issued by
- Luce County, Michigan
About this file
This document is an attachment to a state and local contract opportunity titled "751/20015. TAP; Newberry Customer Service Center" located in Luce County, Michigan. The document contains a detailed schedule for the project's preliminary and final design phases, including key milestones such as kickoff, site survey, geotechnical analysis, program verification, code analysis, design reviews, LEED administration, mass timber planning, and cost estimating. The design phases are expected to take approximately 29 weeks, with final design submission targeted for August 2022 and the potential for a restart in December 2022. The contract also includes construction administration services for 52 weeks, with shop drawing reviews, RFIs, field reports, progress meetings, LEED administration, punchlist, and closeout documentation.
The contract opportunity does not provide any details on pricing terms, set asides, incumbents, funding requirements or sources, or other salient commercial information. The focus of the document is on the technical scope and schedule of the design and construction administration services.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Notes Task Name Duration Start Finish
1 Phase 400 - Preliminary Design 12.8 wks Tue 1/25/22 Fri 4/22/22
2 400 Preliminary Design Kickoff 4 days Tue 1/25/22 Fri 1/28/22
3 400 Site Survey 3 wks Tue 1/25/22 Mon 2/14/22
4 400 Geotechnical Analysis & Report 3 wks Tue 1/25/22 Mon 2/14/22
5 400 Phase I ESA 2 wks Tue 1/25/22 Mon 2/7/22
6 400 Program Verification (if needed) 2 days Fri 1/28/22 Mon 1/31/22
7 400 Code Analysis 2 wks Mon 1/31/22 Fri 2/11/22
8 400 Preliminary Design 5 wks Mon 1/31/22 Fri 3/4/22
9 400 Outline Specifications 4 wks Mon 3/28/22 Fri 4/22/22
10 400 50% Review Submission 0 days Wed 2/23/22 Wed 2/23/22
11 400 50% Review Meeting 0 days Wed 3/9/22 Wed 3/9/22
12 400 90% Review Submission 0 days Mon 3/28/22 Mon 3/28/22
13 400 90% Review Meeting 0 days Fri 4/8/22 Fri 4/8/22
14 400 LEED Administration - Design 12 wks Mon 1/31/22 Fri 4/22/22
15 400 Mass Timber Planning 10 wks Mon 2/14/22 Fri 4/22/22
16 400 Prelim Cost Estimate 2 wks Fri 4/8/22 Thu 4/21/22
17 Phase 500 - Final Design 16.2 wks Fri 4/22/22 Fri 8/12/22
18 500 Specification Development 16 wks Mon 4/25/22 Fri 8/12/22
19 500 Final Design Documents 16 wks Fri 4/22/22 Thu 8/11/22
20 500 50% Review Submission 0 days Mon 5/30/22 Mon 5/30/22
21 500 50% Review Meeting 0 days Fri 6/10/22 Fri 6/10/22
22 500 90% Review Submission 0 days Mon 7/18/22 Mon 7/18/22
23 500 90% Review Meeting 0 days Fri 7/29/22 Fri 7/29/22
24 500 LEED Administration - Design 16.2 wks Fri 4/22/22 Fri 8/12/22
25 Phase 500 - Final Design Restart 17.2 wks Mon 12/5/22 Mon 4/3/23
26 500 CLT Supplier LOI submittal - for production
15.2 wks Mon 12/19/22 Mon 4/3/23
27 500 Specification Development 11 wks Mon 12/5/22 Fri 2/17/23
28 500 Final Design Documents 11 wks Mon 12/5/22 Fri 2/17/23
29 500 50% Review Submission 0 days Mon 1/16/23 Mon 1/16/23
30 500 50% Review Meeting 0 days Mon 1/23/23 Mon 1/23/23
31 500 90% Review Submission 0 days Fri 2/10/23 Fri 2/10/23
32 500 90% Review Meeting 0 days Mon 2/13/23 Mon 2/13/23
33 500 Bidding 5 wks Mon 2/20/23 Fri 3/24/23
34 500 Contract Award 1 wk Mon 3/27/23 Fri 3/31/23
35 Phase 600 - CA Office Services 52 wks Mon 4/17/23 Fri 4/12/24
36 600 Shop Drawing/Submittal Reviews 36 wks Mon 4/17/23 Fri 12/22/23
37 600 RFI's, Field Reports, Progress Meeting
Notes
48 wks Mon 4/17/23 Fri 3/15/24
38 600 LEED Administration - CA 52 wks Mon 4/17/23 Fri 4/12/24
39 600 Punchlist/Closeout Documentation 3 wks Mon 3/18/24 Fri 4/5/24
40 Phase 700 - CA Field Services 53 wks Mon 4/17/23 Fri 4/19/24
41 700 Construction Administration 52 wks Mon 4/17/23 Fri 4/12/24
42 700 Bi-Weekly Site Reviews 51 wks Mon 4/17/23 Fri 4/5/24
43 700 Final Completion Meeting 1 wk Mon 4/8/24 Fri 4/12/24
44 700 Post-Occupancy Inspections 1 wk Mon 4/15/24 Fri 4/19/24
1/16
1/23
2/10
2/13
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024