Attachment A1 - Topic 1 -Statement of Objectives.pdf

PDF 143 KB Posted

Attached to
Lunar Enabling Infrastructure Accelerator (LEIA) -Broad Agency Announcement (BAA) NextSTEP-3 Appendix A - Final Solicitation
Solicitation number
80GRC026R0008
Issued by

About this file

This is a Statement of Objectives (SOO) for a NASA NextSTEP-3 contract focused on advancing Vertical Solar Array Technology (VSAT) subsystems for lunar exploration missions.

NASA seeks to mature critical VSAT components from Technology Readiness Level (TRL) 4 to TRL 5-6 through system-level demonstrations in ground environments. The primary mission need addresses the requirement for resilient, scalable, and long-duration surface power architectures to support lunar exploration, including mobility systems, habitats, and landers. The effort focuses on critical risk reduction in three key areas: electrical system integration, thermal rejection, and external power exchange to enable VSAT systems to integrate with a standardized lunar microgrid. The four core objectives are: (1) Electrical System Maturation—demonstrate end-to-end electrical system integration addressing power quality, reliability, redundancy, and monitoring/control; (2) Thermal Control Resiliency—develop and validate thermal control strategies maintaining avionics and electronics within operational and survival temperature limits during extreme solar heating and lunar darkness; (3) External Power Interoperability—implement standardized external power interfaces ensuring VSAT compatibility with external lunar assets; and (4) Technology Transition and Future Integration—define pathways for flight readiness and integration with mobility systems, habitats, landers, and other lunar surface systems.

Performance outcomes require contractors to demonstrate a VSAT external power exchange capability operating on a standardized 120 Vdc, 6-kW hardware-rated interface with power regulation occurring prior to cabled distribution, validate integrated electrical system performance including power quality and fault tolerance, and confirm the interface meets all power-quality and stability limits across a 100-meter cable. All proposed hardware and interface designs must comply with Lunar Power Exchange Interface Requirements (EHP-10069) Electrical Power System requirements. Deliverables include demonstrations and supporting documentation, technical reports, system characterization and performance data, test reports under simulated lunar conditions, TRL advancement pathway documentation, government insight activities, final reports in limited and unlimited versions, and continuation reviews for each Contract Line Item Number (CLIN) prior to completion and authorization to proceed with subsequent CLINs.

View the file

Other files

File Type Posted
NextSTEP-3 Appendix A - Solicitation -Amendment 3.pdf PDF
Attachment A3-Topic 3 -Statement of Objectives - Amendment 3.pdf PDF
80GRC026R0008 SF30 Amendment 3.pdf PDF
Attachment A2- Topic 2- Statement of Objectives - Amendment 3.pdf PDF
Responses to Questions for NextSTEP-3 BAA Appendix A LEIA - Final Batch 3.pdf PDF
Responses to Questions for NextSTEP-3 BAA Appendix A LEIA - Batch 2.pdf PDF
80GRC026R0008 SF30 Amendment 2.pdf PDF
NextSTEP-3 Appendix A - Solicitation -Amendment 2.pdf PDF
80GRC026R0008 SF30 Amendment 1.pdf PDF
NextSTEP-3 Appendix A - Solicitation -Amendment 1.pdf PDF
Responses to Questions for NextSTEP-3 BAA Appendix A LEIA - Final Batch 1.pdf PDF
Attachment B4-Topic 4-System Requirements-Amendment 1.pdf PDF
Attachment C- Model Contract - Amendment 1.pdf PDF
Attachment K - Government Task Agreement Instructions and Template.pdf PDF
Final Request for Proposal (RFP) Cover Letter.pdf PDF
Attachment A4-Topic 4-Statement of Objectives.pdf PDF
Attachment B4-Topic 4-System Requirements.pdf PDF
Attachment D - Pricing Template.xlsx XLSX spreadsheet
Model Contract Att. 2 DRD - Security Requirements for Unclassified IT Resources.pdf PDF
Attachment A5-Topic 5-Statement of Objectives.pdf PDF
Attachment B1- EHP-10069_Rev A_Final.pdf PDF
Attachment B2 -Topic 2-Technical Performance Measures.pdf PDF
Attachment C- Model Contract.pdf PDF
Attachment G - Eligibility Certification for Participation of International Team Members.pdf PDF
Attchment I - International Participation Plan.pdf PDF
Model Contract Att 1 -Pre-Award.pdf PDF
NextSTEP-3 Appendix A - Final Solicitation.pdf PDF
Attachment A2- Topic 2- Statement of Objectives.pdf PDF
Attachment A3-Topic 3 -Statement of Objectives.pdf PDF
Attachment H -Statement of Work Template.pdf PDF
Relationship to Other NASA NextSTEP-3 Solicitations (Scope Boundary).pdf PDF
Attachment E - Representations and Certifications.pdf PDF
Attachment F - Eligibility Certification and Supplemental Information Form.pdf PDF
Attachment J- DRD Title Organizational Conflicts of Interest (OCI) Plan.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment A1: Statement of Objectives (SOO) Topic 1 NextSTEP-3 Appendix A

1. PURPOSE

This Statement of Objectives (SOO) defines mission need, objectives, desired outcomes, and constraints to enable industry to propose commercially viable and credible solutions for the advancement of critical Vertical Solar Array Technology (VSAT) subsystems.

Offerors are expected to apply independent scientific and engineering judgment in selecting technical approaches and proposed solutions that best satisfy the objectives and outcomes defined herein.

See Appendix A for additional solicitation details.

2. BACKGROUND/MISSION NEED

NASA requires resilient, scalable, and long-duration surface power architectures to support lunar exploration, including mobility systems, habitats, and landers. VSAT is a critical component of this infrastructure. However, current VSAT systems cannot progress to a flight program without further maturing key components, as the overall system Technology Readiness Level (TRL) is constrained by its lowest-TRL subsystems (currently at TRL 4).

Furthermore, to prevent the need to oversize VSAT systems, the arrays must be able to flexibly share energy with other lunar assets during eclipses or low-generation periods. This requires integration into a standardized lunar microgrid. This research and development effort focuses on critical risk reduction, specifically targeting electrical system integration, thermal rejection, and external power exchange, to mature these systems for future mission adoption.

3. OBJECTIVES

The overall objective of this effort is to advance critical VSAT subsystems from a starting Technology Readiness Level (TRL) of 4 to a target TRL 5-6 through the system-level demonstrations in relevant ground environments.

3.1 Objective 1 - Electrical System Maturation: Demonstrate end-to-end electrical system integration to resolve existing vulnerabilities regarding power quality, reliability, redundancy, and monitoring/control.

3.2 Objective 2 – Thermal Control Resiliency: Develop and validate thermal control and rejection strategies capable of maintaining core avionics and electronics within survival and operational temperature limits during periods of extreme solar heating and lunar darkness.

3.3 Objective 3 – External Power Interoperability: Implement standardized external power interfaces to ensure VSAT interoperability with external lunar surface assets, providing a basis for a flexible, scalable operational power architecture.

3.4 Objective 4 – Technology Transition and Future Integration: Define a pathway for advancing the demonstrated VSAT technology toward flight readiness and identify integration strategies to support interoperability with mobility systems, habitats, landers, and other future lunar surface systems.

4. PERFORMANCE OUTCOMES

Successful efforts shall achieve the following outcomes:

4.1 Power Exchange Capability: Demonstrate a VSAT external power exchange capability (multiple interfaces) that operates reliably on a standardized 120 Vdc, 6-kW hardware-rated interface. The power regulation interface is considered part of the VSAT system and is expected to occur prior to cabled power distribution.

4.2 Electrical Performance: Demonstrate integrated electrical system performance, explicitly validating power quality, fault tolerance, and system-level monitoring and control.

4.3 Cable Stability: Validate that the external power exchange interface meets all power-quality and stability limits across a 100-meter interface cable.

5. CONSTRAINTS AND SCOPE

The following in-scope and out-of-scope constraints apply to all proposed technical approaches.

Offerors shall ensure their proposed technical approach strictly adheres to these boundaries.

5.1 In-Scope: The following elements shall be considered in scope and included in this effort:

5.1.1 All proposed hardware and interface designs must comply with Lunar Power Exchange

Interface Requirements (EHP-10069) Electrical Power System (EPS) requirements.

6. DELIVERABLES, MILESTONES, AND REVIEWS

Offerors shall propose deliverables, milestones and reviews appropriate to the maturity, scope, and technical approach of their proposed efforts. Proposed milestones shall represent meaningful and measurable technical progress. Proposed deliverables shall provide sufficient objective technical evidence to demonstrate progress toward, or achievement of, the stated objectives and outcomes. Proposed reviews and Government insight activities shall provide the Government with opportunities to assess technical progress, performance, technical maturity, and readiness to proceed. The desired deliverables, milestones, and reviews of a successfully awarded contract include:

6.1 Demonstrations and supporting documentation validating advancements in system design, technology maturation, operational readiness, and risk reduction for critical technology elements and key interfaces of the Vertical Solar Array Technology (VSAT) system.

6.2 Technical reports and briefings documenting system design, hardware fabrication, integration, testing activities, performance characterization (e.g., power quality, thermal control/dissipation/heating, fault tolerance), and technical progress throughout the period of performance.

6.3 System characterization, build, and performance data supporting the assessment of system reliability, thermal stability, and full compliance with the Lunar Surface External Power

Exchange (LSEPE) limits (e.g., demonstrating 120 Vdc, 6-kW capability across a 100-meter interface cable).

6.4 Test reports documenting the end-to-end electrical, thermal, operational, functional, or environmental performance of the VSAT components or subsystems under simulated lunar environmental conditions (e.g., extreme external heating during sunlight, extreme cold during darkness) and anticipated fault scenarios.

6.5 Documentation describing the proposed pathway for advancing the Technology Readiness Level (TRL) of the demonstrated technology to a flight-ready program, alongside integration strategies to ensure VSAT interoperability with mobility systems, habitats, and landers for future NASA space applications.

6.6 Government insight activities, including technical interchange meetings, progress reviews, demonstrations, and site visits, as appropriate and coordinated with the Government, to support technical assessment, collaborative risk reduction, and programmatic visibility.

NASA will actively engage with selected Offerors through ongoing technical engagement, milestone reviews, and Government insight and oversight activities to support assessment of technical progress, and achievement of program objectives.

6.7 Final Report (Limited and Unlimited versions. Unlimited versions shall be free from ITAR/EXPORT control and should be able to be shared with the public.)

6.8 Continuation Review: The Contractor shall support a continuation review for each CLIN prior to completion of the CLIN and, when applicable, prior to Government authorization to proceed with the subsequent CLIN. The Contractor shall provide the Government with information sufficient to assess technical performance, schedule status, risk retirement, deliverable status, unresolved issues, technical maturity, and readiness to proceed. The Contractor shall also provide its recommendation regarding continuation. The Government will use the results of the continuation review to inform its decision regarding exercise of the subsequent Option.