Attachment 9-NIST Bldg 101 2nd Flr Reno - Final MEP FP BOD.pdf
PDF 36 MB Posted
- Attached to
- B101 2nd Floor Renovation
- Solicitation number
- 1333ND24QNB190040
About this file
This solicitation is for construction services to renovate the second floor of Building 101 at the National Institute of Standards and Technology campus. The existing floor will be converted from closed offices and conference rooms to a more open layout with work areas, collaboration spaces, and exposed filing and copy spaces. The magnitude of construction is estimated between $1 million to $5 million. A site visit is scheduled for January 22, 2024 and questions for clarification are due by January 29, 2024. Offers must be submitted by February 27, 2024. Attachments include floor plans, specifications and reports related to asbestos and mechanical, electrical and plumbing systems. The selected contractor will perform renovations to modernize and update the space in accordance with Department of Commerce policies.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Prepared By:
CFR Engineering Consultants, Inc.
20251 Century Blvd, Suite 120
Germantown, MD 20874
(877) 871-4229
NIST Building 101 – 2nd Floor Renovation
National Institutes of Standards and Technology
Final Submission
MEP, Fire Protection
Basis of Design
Task Order No.
1333ND20FNB190243
CFR Project Number: 20072
December 22, 2022
CFR Engineering December 22nd, 2022
National Institute of Standards and Technology – Building 101, 2nd Floor Renovation
Basis of Design Report
Table of Contents
1 EXECUTIVE SUMMARY
2 MECHANICAL
APPLICABLE CODES, GUIDELINES AND STANDARDS
HVAC LOAD CALCULATION METHODOLOGY
EXISTING SYSTEM DESCRIPTION
NEW WORK
3 PLUMBING
APPLICABLE CODES, GUIDELINES AND STANDARDS
SCOPE OF WORK
4 ELECTRICAL
APPLICABLE CODES, GUIDELINES AND STANDARDS:
CALCULATION METHODOLOGY
SYSTEM DESCRIPTION
5 FIRE PROTECTION/FIRE ALARM
Appendix A: A/E Statement of Work
Appendix B: Mechanical Product Data and Calculations
Appendix C: Plumbing Product Data
Appendix D: Electrical Product Data
1 Executive Summary
This Basis of Design (BOD) narrative and associated contract documents describe and define the mechanical, and electrical engineering (M-E) systems proposed for the project. The purpose of these documents is to clarify the design basis and intent of this project at the 95% level of completion. The general scope of work is to provide mechanical, plumbing and electrical engineering design services for the entirety of the second floor. Engineering design will be provided for the new equipment and associated piping, ductwork and plumbing.
Each BOD will further describe the design basis as follows:
• Codes and Applicable Guidelines
• Calculation Methodology
• System Descriptions
2 Mechanical
Applicable Codes, Guidelines and Standards
• International Building Code - 2021
• International Mechanical Code – 2021
• International Energy Conservation Code - 2021
• NFPA 70 (2020) - National Electric Code
• NFPA 90A (2021) - Standard for the Installation of Air conditioning and Ventilating Systems.
• NFPA 101 (2021) - Life Safety Code
• ASHRAE Standard 62 - Ventilation for Acceptable Indoor Air Quality
HVAC Load Calculation Methodology
Outdoor Design Conditions
Summer:
• Dry-Bulb Temperature = 95°F
• Wet-Bulb Temperature = 78°F
Winter:
• Dry-Bulb Temperature = 11°F
• Wet-Bulb Temperature = 8°F
Ventilation Rates: The minimum ventilation (outdoor air) rates based on the IMC 2021 and are as follows:
Office
• 0.06 cfm/sf
• 5 cfm/person
• 5 people/ 1000 sf
Corridor
• 0.06 cfm/sf
Conference Room
• 0.06 cfm/sf
• 5 cfm/person
• 50 people/ 1000 sf
Reception
• 0.06 cfm/sf
• 5 cfm/person
• 10 people/ 1000 sf
Existing System Description
HVAC System:
The majority of the second floor is conditioned via perimeter induction units that provide cooling, heating, and ventilation to spaces. The existing corridor and elevator lobby are conditioned via a supply air riser dedicated to conditioning corridor and elevator lobby the entire height of building
101. This existing air riser is served via ACU-A-5 and has an existing hot water heating coil with a single temperature sensor. The perimeter induction units are served via primary air risers and heating hot water risers that are located along the perimeter of the of the building. The primary air risers are served by various Air Conditioning Units (ACUs) that are located on the mechanical floor below. The system return air is achieved via a corridor a side wall returns grille and a plenum return open ended duct above ceiling. Returning air via a side wall return grille within in the corridor is a code issue and will need to be modified in new work to bring up to code. Code requires that air to not be return via a means of egress, which in building 101 is the main center corridor.
Exhaust Air System:
Existing bathrooms are exhausted via an existing toilet exhaust riser. During survey it was observed that the toilet exhaust grilles did not have any flow. Before any demolition and new work is conducted investigation the existing building exhaust system shall be confirmed operational.
New Work
HVAC System
The scope of work requires the redesign of the second floor, to fit the new floor plan. The design of the second floor shall serve as a prototype and template for future renovations of upper floors of the Building 101 office tower. The new architectural floor plan includes new interior spaces including office A201/A202 reception A204, meeting rooms A215/A217 and office A239/A240. These spaces are no longer able to be conditioned via the perimeter induction units. Perimeter spaces will remain conditioned by existing induction units. The majority of induction unit airflows will remain the same except for spaces that require additional airflow due to new architectural floor plan. The existing perimeter induction units will be reused for all exterior rooms. Per the scope of work, all perimeter induction unit dielectric fittings shall be replaced due to leakage.
CFR proposes to serve the new interior zones via horizontal induction units from the existing risers.
Primary air will be routed from perimeter primary air riser and duct take off will be 6” round duct and transition to 4” prior to the inlet of induction unit to help lower duct pressure drop from riser to inlet.
Induction units will match existing induction unit operation and utilize heating water for heating during the winter months. Heating water will be routed from the existing water riser to induction units.
To condition the central corridor and the elevator lobby, the existing corridor air riser will be re-used. The existing duct will be used as much as possible and connect to new ceiling air devices for the corridor and new linear slot diffusers for the elevator lobby.
Exhaust/Return Air System
The existing exhaust air riser serving bathroom stack shall remain existing. New exhaust air devices will be provided and rebalanced to meet code required minimum and ensure bathroom is negatively pressurized to the corridor.
Utilizing a corridor as a return air path is not code compliant and will need to be modified to a plenum return system. The existing return air open ended duct above the ceiling will need to be enlarged to accommodate all return air through the ceiling plenum. Modification of the existing return air open ended duct may require opening the existing duct shaft. Return air from perimeter and interior spaces will be plenum returned. New return air device will be located within each space and utilize transfer ducts to transfer air into the corridor ceiling plenum.
Additional and detailed scope is as follows:
• Remove all existing transfer air devices and corridor air devices and provide new devices.
• Replace all (75) induction unit dielectric fittings. Each induction unit has 2 dielectric fitting, one for the supply side and one for return side.
• Provide new DX split and transfer fan for IT room
3 Plumbing
Applicable Codes, Guidelines and Standards
• International Building Code - 2021
• International Plumbing Code – 2021
• International Energy Conservation Code - 2021
Scope of Work
The existing Bathroom’s cold water, hot water, sanitary, and vent piping will be modified to serve new fixture layout. Demolition includes the removal of one toilet fixture in both the women’s and men’s restroom. Three sinks will be added to the floor. One sink will be placed in Room A220 (lactation room), and a pantry sink will be placed in room A222 (breakroom). To serve the new lavatory sink in the break room, a new instant electric water heater shall be provided and located under the pantry sink. A hot water heater will be installed below the sink, with an instant hot water dispenser located on the countertop. Additional lavatories will be added to the bathrooms. The bathroom lavatories will be replaced with new fixtures.
A new sanitary riser will be added to serve new kitchenette sink. The sanitary riser shall extend up to the floor above and capped for future connection. The riser shall connect to an existing 4” sanitary main located in the mezzanine mechanical room below and serves the janitor sink and bathroom group. The new sink located in the lactation room will require an ejector pump to discharge sink water up and connect to the new pantry sink riser. Due to lack of space due to mechanical equipment on the floor below sanitary for lactation room cannot be connect to the janitor mop sink sanitary line. However, on floors up the building, ejector pumps are not anticipated to be required.
A new vent connection from the pantry sink shall be made to the existing 2-1/2” vent riser serving the janitor closet sink riser.
4 ELECTRICAL
Applicable Codes, Guidelines and Standards:
• IEEE Institute of Electrical and Electronics Engineers
• IESNA Illuminating Engineering Society of North America
• NEMA National Electrical Manufacturers Association
• UL Underwriters Laboratories
• NFPA 70E(2018), 72 (2019), 101 (2018), 110 (2019)
• NEC Latest Adopted National Electrical Code (NFPA 70 - 2020)
• ADA Americans with Disabilities Act Accessibility Guidelines
Calculation Methodology
Load Density Chart
Type of Load Load (VA/Sq Ft)
Receptacles & Equipment 2-3
Lighting 0.5-1.5
HVAC 2-4
Misc 0.5-1
Design Voltages Chart
Equipment Type Voltage
Motors - 1/3 Hp or Less 120V, 1Ø
Motors - All others 208V or 480V, 3Ø
Lighting 120V, 1Ø
Receptacles 120V, 1Ø
Equipment Sizing Chart
Load Type Load Demand Factor
Lighting Installed VA 125% of Installed VA
Receptacles 180 VA per 100% of 1st 10kVA, 50% of remainder
Multiple Outlets Assemblies 180 VA every 2' 100% of 1st 10kVA, 50% of remainder
Special Outlets Installed VA 100% of total VA installed
Motors Motor VA x 1.25 125% of largest plus sum of all others
System Description
Lighting Systems
• A complete lighting system for entire 2nd floor illumination shall be provided.
• Lighting fixtures shall be energy efficient LED type with integral driver and battery packs as required.
Lighting Levels
Function/Space Lighting levels in FC
Offices 25-35
Corridors 10-15
Mech/Elect Room 10-20
Storage 5-10
Restroom 3-5
Design Criteria
Lighting Fixture Types
• New LED lighting will be provided.
o Conference Room- Linear pendant and recessed LED direct fixtures and 3” square downlights o Offices – 2x2 LED Troffers o Common Areas – Linear LED cove, 2x2 LED troffers, 3” square LED downlights, and recessed 1” pin LED lights o Emergency Fixtures – Battery backup provided with the different fixtures
• LED lighting will be 3500°K, CRI: 80 and have a minimum 50,000 hour rated life.
Lamps and Drivers
• LED constant current drivers will be provided for LED fixtures.
Lighting Control
• Lutron Quantum system will be used for lighting control.
• Occupancy sensors will be used in offices spaces and restrooms.
• Office areas have dual-level lighting with vacancy sensors and local wall switch.
• Ceiling mounted occupancy sensors in corridors with local switches.
• Daylight sensors will be used where required.
Lighting Distribution
• Lighting will be served by 120V and 277Vcircuits.
• Circuits are sized for a minimum of 25% future growth.
Emergency Lighting
• Lighting fixtures will be provided with integral emergency battery backup to provide 1 fc of light along the egress path.
Electric Power Distribution
System Description
• The second floor is currently served by (4) electrical panels located in the 2nd floor electrical room. The panels are the following:
1. PA-2-32NN – Westinghouse 100A MCB, 480/277V, 3PH, 4W, 18 poles.
Fed from Switchgear 101-A1
2. PB-2-32NN – Westinghouse 225A MLO, 208/120V, 3PH, 4W, 42 poles.
Fed from panel PB-M-32SS
3. PB-2-32NN-A – Cutler Hammer 225 MLO, 208/120V, 3PH, 4W, 42 poles. Fed from panel PB-2-32NN
4. B-2-32NN-2 – Square D 225 MCB, 208/120V, 3PH, 4W, 42 poles. Fed from panel DPM-29QQ
• Normal Power Services and Distribution – Refer to Electrical Drawings.
• Emergency Power – No emergency generator will serve this space at this time.
Design Criteria
• Normal power distribution panels will contain bolt-on feeder circuit breakers. The capacity of the panels will be sufficient for the connected load and 25% spare capacity
• Panelboards PA-2-32NN and PB-2-32NN will be replaced with new. New panels will be 42 poles and have the same amps, AIC, and voltage rating as old panels.
• Point-of-use power connection devices will include specification - grade receptacles (120V, 20A, single phase, NEMA 5-20R), surface mounted raceway, and Special Configuration receptacles.
• Dedicated receptacles will be provided for copiers and printers.
• Power circuits will be routed in ceiling space.
• Power to modular furniture in open workstation areas will be provided by systems furniture power and data whips to route power and data to the furniture.
5 FIRE PROTECTION/FIRE ALARM
DESIGN CRITERIA:
• ICC International Building Code (IBC) – 2021 Edition
• NFPA 101®, Life Safety Code®(LSC) – 2021 Edition
• NFPA 13, Standard for the Installation of Sprinkler Systems, 2022 Edition
• NFPA 70 - National Electric Code, 2020
• NFPA 72, National Fire Alarm and Signaling Code, 2022 Edition
• Architectural Barriers Act (ABA) Accessibility Standards
• NIST SUBORDER DOCUMENT NIST S7401.01 FIRE PROTECTION & LIFE SAFETY FOR DESIGN AND
CONSTRUCTION
• NIST SUBORDER DOCUMENT NIST S7401.03 FIRE PROTECTION & LIFE SAFETY SYSTEM
IMPAIRMENTS
• Other relevant NFPA codes, as applicable.
DESCRIPTION OF WORK:
Building Description
NIST Building 101, floor 2 is classified as an IBC Group B [IBC, 304.1] and LSC business occupancy
[LSC, 6.1.11.1]. Per the LSC, the small conference room, telecom, etc. spaces are considered incidental to the primary occupancy [LSC, 6.1.14.1.3(1)]. Per the IBC, these spaces are considered accessory to the primary Group B occupancy [IBC, 508.2].
The construction type for the building is required to comply with the fire-resistance requirements contained in the IBC. The tower, which is the area of the scope of work has a IB construction classification. The B Wing and C Wing have exposed steel and, since there are no fire separations between the tower and those areas, the AHJ considers the building to be IIB. Therefore, the entire building is IBC Type IIB construction [IBC, 602], which includes non-combustible, non-fire resistance rated steel construction.
Sprinkler System
There is an existing wet pipe sprinkler system throughout Building 101. The sprinkler system piping will be modified due to the change in the ceiling plan. The sprinkler piping will be demolished back to floor control valve in the stairwell, and a new main will be routed from the floor control valve to serve the reconfigured floor layout.
Once the work is completed, the system shall be hydrostatically tested by re-pressurizing the system and inspecting for leaks. NFPA 13 record of completion report shall be provided to the owner at project completion.
Water Supply Analysis
There is currently a fire pump serving the existing system. It is a 750 GPM fire pump rated at 150 PSI and the suction pressure is 30 PSI. There is a pressure reducing valve that keeps the pressure at or below
170 psi after leaving the pump. Hydraulic calculations have been completed and can be found in the submission package
Fire Alarm System
The existing fire alarm system is an addressable, voice alarm system with a Simplex 2500 fire alarm control unit (FACU). The second-floor fire alarm system is served by a fire alarm control panel on the third floor which is connected to the main building control unit.
New notification appliances (speaker/strobes) will be installed in the project areas to accommodate the new floorplan. A new NAC panel will also be installed to accommodate the new devices The existing class A
NAC circuit will be extended to each of the appliances.
During construction, all fire alarm devices and appliances outside the project area shall remain operational.
Once the new appliances and devices are added to the existing Simplex system, the existing circuits will be extended to the new the appliances and fire alarm programming will be revised as necessary.
Once the systems modifications are completed, all appliances, controls, and initiating devices in project area will be tested at the fire alarm control unit and a test report shall be provided at project completion.
A/E Statement of Work
Appendix – A
STATEMENT OF WORK
BUILDING 101 2ND FLOOR RENOVATION
Background:
Building 101 at the National Institute of Standards and Technology (NIST) is the main administration building for the NIST Gaithersburg Campus. As the tallest structure and the most iconic building on the campus, Building 101 consists of an 11-story administrative office tower and a sprawling first floor and basement level.
The first floor of Building 101 houses the central campus conference facilities, the NIST research library and the main campus cafeteria. The basement level houses the NIST fitness center, badging and security offices, telecommunications suites, and the campus health unit, among other occupancies. The office tower, floors 2 through 11, houses a variety of administrative support and managerial office functions.
Although the original design intent and functions of the lower levels and office tower floors remain largely intact, changing trends, new technologies, and the age of the facility, in general, have been eroding their role as a center where NIST researchers can meet with one another and members of the public to collaborate and innovate.
Scope:
The NIST Administrative Space Strategic Plan, finalized in 2014, provides a planning strategy and conceptual plans for the reorganization of administrative and public space within the principal administrative facilities on the campus.
One of the goals of this Strategic Plan is to bring space utilization rates within the
Department of Commerce (DoC) standard of 170 net assignable square feet (NASF) per person, while allowing flexibility for the administrative program units to expand, shrink, merge, or reorganize as needed.
This DoC standard applies only to administrative spaces such as offices, private conference rooms, copy centers, dedicated mail and storage spaces, training rooms and break areas. Specialty support space, IT and utility spaces, laboratories, shops, warehouse space, and other similar areas are not counted as area in the utilization calculation.
In accordance with Department of Commerce space policies, and with the increasing need for administrative workstations, the Building 101 office tower floors (2 through 11) need to be renovated and modernized. Existing floors will be converted to less restricted layouts, intermingling closed offices and conference rooms with open work areas, collaboration spaces, and exposed filing and copy spaces.
Objective:
The A/E shall develop three possible schematic layout plans for renovated office space on the 2nd floor of Building 101. From a NIST-selected preferred alternative, the A/E shall prepare construction documents and construction cost estimate packages for:
1. The 2nd floor renovations
2. Furnishings for the 2nd floor
The A/E shall submit a Project Design Schedule with proposed periods of performance for each design phase. The schedule shall incorporate the following milestones:
Task Duration
Award Made -----
A/E Design Consultant
Safety Checklist, Certificate of Insurance
7 calendar days
NIST Review 5 calendar days
Notice to Proceed (NTP)
15% schematic planning To be determined
NIST Review 14 calendar days
35% Design To be determined
NIST Review 14 calendar days
65% Design To be determined
NIST Review 14 calendar days
95% Design To be determined
NIST Review 14 calendar days
100% Design To be determined
Period of Performance 270 calendar days after the NTP issued
Optional Item: Post-Construction Award Services
A/E Post-Construction Contract Award Services (PCAS) are an optional item under the task order.
If awarded, PCAS services shall be provided in accordance with the requirements specified in “Part ‘B’ Architect Engineering design services in accordance with 48 CFR
836.606-73 (c),” described elsewhere in this statement of work.
Project Description:
This project is the first in a phased modernization of ten floors of existing office space.
The second floor is currently occupied by a portion of the Office of Human Resources
(OHR). These occupants will be relocated to a temporary office complex (TOC) during renovation work. Procured under a separate contract, this modular TOC will serve as swing space for the relocation of tower floor occupants during phased floor-by-floor renovations. At project completion, OHR personnel from the 1st floor as well as the 2nd floor occupants in the TOC will be consolidated in the newly renovated 2nd floor space.
Existing perimeter HVAC induction units, vertical air distribution systems, and exterior building windows will remain and are not a part of this project.
The design of the 2nd floor may serve as a prototype for the renovation of other floors in the Building 101 office tower.
The A/E shall prepare separate design and construction bid document packages for the following elements of work:
1. 2nd floor construction package (for competitive bidding by construction contractor)
2. 2nd floor furniture package (for procurement by NIST)
A/E Post Construction Contract Award Services (PCAS) are an optional line item under the task order and may be awarded by the Government at a later date, if necessary.
Existing drawings, specifications, planning studies, the Gaithersburg NIST Master Plan, and any other available information will be made available for use in executing the work described in this task order.
The NIST Gaithersburg campus has been determined eligible for listing in the National
Register of Historic Places (NRHP). As such, all design and work performed therein must conform to the Secretary of the Interior’s Standards for the Treatment of Historic
Properties (SOI Standards). The NIST federal preservation officer shall review all designs for conformance with the SOI Standards and coordinate all consultation with the
Maryland Historical Trust, as required by law. The A/E’s schedules shall reflect the requisite consultation and approval times.
Sustainable Design Requirements: This project is a NIST Safety, Capacity, Maintenance and Major Repair (SCMMR) project. The design shall comply with the NIST Sustainable
Design Manual of July 31, 2014 (see Attachment 3) for SCMMR projects.
Phases of Work:
The work shall be accomplished in the following phases (see Statement of Work section
“Requirements” for an explanation of Part A and Part B services):
Basic Services:
1. 15% schematic planning (non-design part B services)
2. 35% design (design Part A services)
3. 65% design (design Part A services)
4. 95% design (design Part A services)
5. 100% design (design Part A services)
Additional Service:
Post Construction Award Services (non-design PCAS)
Period of Performance:
The period of performance for basic services, CLIN 0001, is 270 calendar days (9 months) from issuance of notice-to-proceed.
Requirements:
I. PART A – the A/E shall provide Part “A” Architect Engineering design services in accordance with 48 CFR 836.606-73 (a).
The total cost of the architect or engineer services contracted for must not exceed 6 percent of the estimated cost of the construction project plus any fees for related services and activities such as those shown in paragraph (c) of 48 CFR 836.606-73.
A. 35% Design (design development) submittal requirements:
a) Updated Basis of Design report (see Part B requirements for BOD description); submit 2 copies.
b) Updated building plans, elevations, sections, details, and schedules; submit 4 half size and 2 full size sets.
c) Updated calculations; submit 2 copies.
d) Outline specifications; submit 2 copies.
e) Estimate of probable construction cost; submit 2 copies.
f) Submit electronic files (PDF, Word, Excel and AutoCAD).
B. 65% Design (construction documents) submittal requirements:
a) Updated Basis of Design report; submit 2 copies.
b) Updated building plans, elevations, sections, details, and schedules; submit 4 half size and 2 full size sets.
c) Updated calculations; submit 2 copies.
d) Updated specifications; submit 2 copies.
e) Updated estimate of probable construction cost; submit 2 copies.
C. 95% Design (construction documents) submittal requirements:
a) Updated Basis of Design report; submit 2 copies.
b) Updated building plans, elevations, sections, details, and schedules; submit 4 half size and 2 full size sets.
c) Updated calculations; submit 2 copies.
d) Updated specifications; submit 2 copies.
e) Updated estimate of probable construction cost; submit 2 copies.
D. 100% Design (construction documents for bidding) submittal requirements:
a) Final Basis of Design report; submit 2 copies.
b) Final construction drawings; submit 4 half size and 2 full size sets.
c) Final calculations; submit 2 copies.
d) Final specifications; submit 2 copies.
e) Final estimate of probable construction cost; submit 2 copies.
II. PART B - AE shall provide Part “B” Architect Engineering design services in accordance with 48 CFR 836.606-73 (c).
The 6 percent fee limitation does not apply to the following architect or engineer services:
(1) Investigative services including but not limited to:
(i) Determination of program requirements, including schematic or preliminary plans and estimates;
(ii) Determination of feasibility of proposed project;
(iii) Preparation of measured drawings of existing facility;
(iv) Subsurface investigation;
(v) Structural, electrical, and mechanical investigation of existing facility; and
(vi) Surveys: topographic, boundary, utilities, etc.
(2) Special consultant services that are not normally available in organizations of architects or engineers and that are not specifically applied to the actual preparation of working drawings or specifications of the project for which the services are required.
(3) Other:
(i) Reproduction of approved designs through models, color renderings, photographs, or other presentation media;
(ii) Travel and per diem allowances other than those required for the development and review of working drawings and specifications;
(iii) Supervision or inspection of construction, review of shop drawings or samples, and other services performed during the construction phase; and
(iv) All other services that are not an integral part of the production and delivery of plans, designs, and specifications.
(4) The cost of reproducing drawings and specifications for bidding and their distribution to prospective bidders and plan file rooms.
A. Design Kickoff Meeting
The A/E shall attend kickoff meeting after contract award and prior to commencing any design or survey work, as scheduled by the NIST
Contracting Officer (CO).
B. Health and Safety Checklist
The A/E shall complete the attached A/E Design Consultant Safety
Checklist, see attached. The checklist must be submitted to NIST for review and acceptance within 7 calendar days after the award.
C. 15% Design (schematic planning):
1. Existing Conditions Survey: The A/E shall review, copy, and evaluate existing as-built drawings. Field verify/confirm all government furnished information and conduct a detailed survey based on examination and evaluation of existing conditions. Field measure existing building and utilities and document the condition of materials, equipment, and other items required to complete the design; note any materials to be salvaged and re-used.
2. Program Verification: The A/E shall meet with NIST users, facility managers, and department representatives to determine actual occupancy requirements for the 2nd floor; and to review, verify, or modify as required, any existing programs of requirements.
3. Concept Design Workshop: The A/E shall conduct a Concept Design
Workshop with representatives from NIST and the design team. This workshop shall review the A/E’s draft schematic plans, examine current project conditions and requirements, consider alternate design concepts, and develop a draft final conceptual design.
Prior to conducting the workshop, the A/E shall have completed an existing condition survey and reviewed available project documentation.
4. Deliverables under PART B:
i. Basis of Design (BOD): BOD shall be produced for the initial design submission and shall be updated and resubmitted at each subsequent submission. Sections shall be provided for each design discipline.
The BOD shall fully document the parameters of the project. In conjunction with the drawings and specifications, the BOD is a permanent record of the project design. The BOD shall include discipline narratives, which explain and document all important requirements and decisions made during the design process.
Narratives shall be sufficiently detailed to convey the design intent (e.g. general description, areas served, significant features, provisions for future expansion/flexibility, materials/products to be used, codes, standards, design criteria) and special program requirements pertinent to the design.
In addition, the BOD shall include the Statement of Work, project program, a listing of all applicable codes, standards and regulations, equipment schedules, equipment cut sheets with specific as-selected options identified, meeting minutes, correspondence, sustainability goals and approach, budget and cost estimates, surveys, studies, and any other information that will provide insight and background on the project and its development.
The BOD of each submittal phase may be based on the previous submittal but must be revised and expanded at each stage to reflect the current state of the design and the basis for which each system has been engineered, constructed, and expected to operate.
Manual and/or computer-based calculations shall accompany narratives where required to support technical analysis.
ii. Submittal Requirements:
a) Basis of Design report; submit 2 copies.
b) Schematic drawings; submit 4 half size and 2 full size sets.
c) Outline specifications; submit 2 copies.
d) Estimate of probable construction cost; submit 2 copies.
e) Submit electronic files (PDF, Word, Excel and AutoCAD)
D. Furniture Selection, Design, and Specifications: The A/E shall develop a bid package for purchase and installation of office and conference room furnishings to be procured by NIST separate from the construction contract. This package shall be separate from the construction bid package for procurement made by NIST through the Department of
Commerce Strategic Sourcing contract (which permits furniture selections from ten pre-qualified furniture manufacturers).
The A/E shall meet with NIST stakeholder representatives as required to determine furniture manufacturer(s), planning of furniture layouts and selection of workstation components. Furniture plans shall be fully coordinated with furniture manufacturers and the construction package for layout of power, data, telephone, lighting, and all other aspects of the planned renovation.
III. Post-Construction Award Services:
1. Construction Progress Meetings
Construction Progress Meetings shall be held at the NIST campus at a location to be determined by the Contracting Officer Representative (COR).
The Contractor and other NIST representatives shall meet at least once every two weeks to review the progress of the work and related issues/problems identified during construction.
2. Construction Observation
The A/E shall perform on-site construction observation and inspection in conjunction with each Construction Progress Meeting to verify conformance with Construction Documents.
Based on such on-site observations, the A/E shall keep the COR informed of progress, quality of work, and deficiencies in the work. A complete log of each inspection shall be maintained throughout the construction period of performance and made electronically available to the COR on a bi-weekly basis. A/E inspections during construction related to inadequacies, errors and/or omissions, shall be performed at no additional cost to the government.
3. Requests for Information
All requests for information (RFIs) by the construction contractor a.k.a.
“Contractor” shall be submitted directly to the COR for A/E review. The A/E’s interpretation shall be documented in writing; all RFIs shall be uniquely and sequentially numbered.
The A/E’s responses to RFIs shall be returned to the COR in a timely manner to avoid interruptions to the flow of work and to prevent project delays.
The A/E shall use an information tracking system to ensure that all RFIs and other construction issues are monitored for timely response.
4. Construction Submittal Review
a. The A/E shall review submittals (shop drawings, material samples, mock ups, manufacturer’s clarifications, etc.) and recommend “reviewed”, “reviewed as noted”, “revise and resubmit” or “not approved”.
b. Allow the following timeline for submittal reviews unless otherwise directed:
i. Initial A/E submittal review – 14 days
ii. Contractor response – 7 days
iii. A/E reply to contractor/ response – 3 days
iv. Resolution & submittal approval – 3 days
c. The A/E shall use an information tracking system to ensure that all submittals are received and processed on time.
5. Change Orders
a. The A/E shall prepare and process Change Requests and provide supporting documentation and all data necessary for CO/COR evaluation, approval and modification in accordance with the contract requirements.
b. Under no circumstance shall the A/E authorize additional work through
RFIs, submittals, or through issuance of Architect’s Supplemental
Instructions (ASIs) without approval by the Contracting Officer. In case of required design adjustments, the A/E must prepare ASIs including backup documentation, cost estimates, and schedule impacts, if any, and submit this information to the CO for review and approval.
c. The A/E shall clearly indicate the source of change as being:
i. Due to design deficiency, error or omission, or
ii. Due to unforeseen conditions, or
iii. Due to government’s new request
d. The A/E shall monitor and record all proposed and accepted changes.
6. Punch List
a. The A/E shall keep the COR informed of the progress and quality of the work and shall advise the COR in writing of defects and deficiencies in the work. The A/E shall observe the installation of work and become familiar with the progress and quality of the work throughout the construction period and verify that the work is being performed in a manner that, when completed, will comply with the Contract Documents. Timely corrective measures shall be taken to ensure that problems are not deferred until the punch list is compiled at the end of the project.
b. The COR shall observe the completed work with the A/E prior to the
Contractor’s application for Substantial Completion. The A/E shall submit to the COR a punch list of any defects and omissions noted. Government will also perform an independent punch list inspection and compile a list of deficiencies to be incorporated into the A/E’s list. At an appropriate time, the COR and Fire Marshal shall conduct a final inspection (with the
A/E) to verify that the Contractor has adequately corrected all defects, deficiencies and omissions.
7. Record Documents
Copies of the Contractor’s As-Built Drawings (in hard copy and electronic formats) shall be provided to the A/E at Final Completion or termination of the project by the CO. The A/E shall prepare Record Documents incorporating all changes and red-line information noted on the
Contractor’s installed work, submitted to NIST on mylar sheets, sealed and signed by the A/E, and provided in electronic CAD format complying with
NIST’s CAD standards.
8. Substantial Completion
The A/E shall define the Substantial Completion requirements in the construction document specifications.
The following procedure shall be used in establishing Substantial Completion of the work, unless otherwise agreed to in writing:
When the Contractor determines that the work, or a portion thereof which
NIST agrees to accept separately, is substantially complete, the Contractor shall submit written notice to the COR and shall include a punch list of all items which remain to be completed or corrected. Failure to include any items on the list does not alter the Contractor’s responsibility to complete all work in accordance with the Contract Documents.
a. Inspections for Substantial Completion may be requested by the
Contractor only after the status of completion has been reviewed and assessed by NIST. Upon such review, the A/E shall issue a list of any observed deficiencies that affect Substantial Completion.
b. If the A/E agrees that the work is substantially complete, the A/E may provide the Contractor with a list of additional corrective items which shall be added to the Contractor’s punch lists.
c. If the A/E determines that the work is not substantially complete, the A/E shall notify the Contractor in writing and shall provide a list of observed deficiencies for correction.
d. When the A/E determines that the work is substantially complete, the
NIST Fire Marshal will inspect the installed work for acceptance, which establishes the date of Substantial Completion.
e. The established date of Substantial Completion is the start date of the
Contractor’s warranty period.
9. Final Completion
The A/E shall define the Final Completion requirements in the construction document specifications.
The A/E shall perform a final inspection of the work. If the work is found to be incomplete or defective, the Contractor will be notified in writing and provided with a list of observed deficiencies.
Deliverables:
At the completion of construction documents and prior to the commencement of any construction activities, the A/E shall prepare and submit a NIST Work Permit (form NIST-
383). This form will be provided by the COR.
Computer Aided Design Requirements:
Drawings shall be prepared in accordance with United States Army corps of Engineers
A/E/C CAD Standard Version 8.0 or higher. Drawings shall be prepared in AutoCAD version 2018 or higher.
Invoicing:
Refer to the Base Contract for specific invoicing instructions. The A/E shall invoice the government based on an A/E provided schedule of values. The schedule of values shall be associated with the deliverables identified and shall be submitted for COR approval prior to invoicing.
Attachments:
1) Example Building 101 Office Planning Concept A
2) Example Building 101 Office Planning Concept B
3) NIST Sustainable Design Manual of July 31, 2014
4) A/E Design Consultant Safety Checklist
5) Guidelines for OFPM Contractors and A/E Firms
Example Building 101 Office Planning Concept A
49 Workstations, 154 sf/person
Example Building 101 Office Planning Concept B
44 Workstations, 172 sf/person
Mechanical Product Data and
Calculations
Appendix – B
Specifications are subject to change without notice. © 2021 Mitsubishi Electric Trane HVAC US LLC. All rights reserved.
Job Name:
System Reference: Date:
Indoor Unit TPKA0A0241KA70A
Outdoor Unit Standard Model TRUYA0241HA70NA
Seacoast Model TRUYA0241HA70BA
INDOOR UNIT FEATURES
• Sleek, compact design
• Simple installation
• Vane setting for air flow direction control
• Auto fan speed mode
• Ideal for spaces such as server rooms, daycare centers, classrooms, churches, small offices, and more
• Multiple control options available:
○ kumo cloud® smart device app for remote access
○ Third-party interface options
○ Wired or wireless controllers
OUTDOOR UNIT FEATURES
• Variable speed INVERTER-driven compressor
• Power receiver pre-charged with refrigerant volume for piping length up to 70 ft
• Low ambient cooling down to -40°F providing 100% capacity (with wind baffles)
• 24-hour continuous operation (cooling mode)
• High pressure protection
• Fast restart
• Superior energy and operational efficiency
TPKA0A0241KA70A & TRUYA0241HA70(N/B)A
24,000 BTU/H WALL-MOUNTED INDOOR UNIT
24,000 BTU/H COOLING ONLY OUTDOOR
Specifications are subject to change without notice. © 2021 Mitsubishi Electric Trane HVAC US LLC. All rights reserved.
SPECIFICATIONS: TPKA0A0241KA70A & TRUYA0241HA70(N/B)A
test
Cooling at 95°F1
Maximum Capacity BTU/H 24,000 Rated Capacity BTU/H 24,000 Minimum Capacity BTU/H 10,000 Maximum Power Input W 1,960 Rated Power Input W 1,960 Moisture Removal Pints/h 5.0 Sensible Heat Factor 0.77 Power Factor % 95.7/95.7
Efficiency
SEER 21.4
EER1 12.2
ENERGY STAR® Certified No
Electrical
Voltage, Phase, Frequency 208/230, 1, 60 Guaranteed Voltage Range V AC 198 - 253 Voltage: Indoor - Outdoor, S1-S2 V AC 208/230 Voltage: Indoor - Outdoor, S2-S3 V DC 24 Short-circuit Current Rating [SCCR] kA 5 Recommended Fuse/Breaker Size (Oudoor) A 25 Recommended Wire Size [Indoor - Outdoor] AWG 14 Power Supply Indoor unit is powered by the outdoor unit
Indoor Unit
MCA A 1.0
Fan Motor Full Load Amperage A 0.36 Fan Motor Output W 56 Fan Motor Type DC Motor Airflow Rate at Cooling, Dry CFM 635–705–775 Airflow Rate at Cooling, Wet CFM 570–635–700 Sound Pressure Level [Cooling] dB[A] 39–42–45 Drain Pipe Size In. [mm] 5/8 [16] Coating on Heat Exchanger — External Finish Color White Munsell 1.0Y 9.2/0.2 Unit Dimensions W x D x H: In. [mm] 46-1/16 x 11-5/8 x 14-3/8 [1170 x 295 x 365] Package Dimensions W x D x H: In. [mm] 51 x 14-1/4 x 18-1/2 [1295 x 362 x 470] Unit Weight Lbs. [kg] 46 [21] Package Weight Lbs. [kg] 53 [24]
Indoor Unit Operating Temperature Range
Cooling Intake Air Temp [Maximum / Minimum]* °F 90 DB, 72 WB / 66 DB, 61 WB Heating Intake Air Temp [Maximum / Minimum] °F 77 DB / 59 DB
Outdoor Unit
MCA A 19.0
MOCP A 26
Fan Motor Full Load Amperage A 0.4 Fan Motor Output W 86 Airflow Rate CFM 1940 Refrigerant Control LEV Defrost Method Reverse Cycle Coating on Heat Exchanger Blue Fin Coating (BS Model only) Sound Pressure Level, Cooling1 dB(A) 47 Compressor Type INVERTER-driven twin rotary Compressor Model SNB172FWHM1 Compressor Rated Load Amps A 7 Compressor Locked Rotor Amps A 11.0 Compressor Oil Type // Charge oz. FV50S // 23 External Finish Color Ivory Munsell 3Y 7.8/1.1 Base Pan Heater N/A Unit Dimensions W x D x H: In. [mm] 37-13/32 x 13 (+1-3/16) x 37-1/8 [950 x 330 (+30) x 943] Package Dimensions W x D x H: In. [mm] 40-15/16 x 17-11/16 x 40-11/16 [1040 x 450 x 1033] Unit Weight Lbs. [kg] 151 [68] Package Weight Lbs. [kg] 176 [80]
Outdoor Unit Operating Temperature Range Cooling Air Temp [Maximum / Minimum]* °F 115 DB / -40 DB
Refrigerant
Type R410A Charge Lbs, oz 7, 11.0 Chargeless Piping Length Ft. [m] 70.0 [20.0] Additional Refrigerant Charge Per Additional Piping Length oz./Ft. [g/m] 0.3 [22.5]
NOTES:
AHRI Rated Conditions (Rated data is determined at a fixed compressor speed) 1Cooling (Indoor // Outdoor) °F 80 DB, 67 WB // 95 DB, 75 WB
*Outdoor Unit Operating Temperature Range (Cooling Air Temp (Maximum / Minimum)):
• Wind baffles required to operate below 23°F DB in cooling mode.
• Cooling-only system with advanced wind baffle: -40°F - 115°F.
• Refer to wind baffle documentation for further information.
**Outdoor Unit Operating Temperature Range (Cooling Thermal Lock-out / Re-start Temperatures; Heating Thermal Lock-out / Re-start Temperatures):
• System cuts out in heating mode to avoid thermistor error and automatically restarts at these temperatures.
SEACOAST PROTECTION (TRU*A0*******BA MODELS)
• External Outer Panel: Phosphate coating + Acrylic-Enamel coating
• Fan Motor Support: Epoxy resin coating (at edge face)
• Separator Assembly Valve Bed: Epoxy resin coating (at edge face)
• Blue Fin treatment is an anti-corrosion treatment that is applied to the condenser coil to protect it against airborne contaminants.
melby Highlight
SPECIFICATIONS: TPKA0A0241KA70A & TRUYA0241HA70(N/B)A
test
Piping
Gas Pipe Size O.D. [Flared] In.[mm] 5/8 [15.88] Liquid Pipe Size O.D. [Flared] In.[mm] 3/8 [9.52] Maximum Piping Length Ft. [m] 225 [68] Maximum Height Difference Ft. [m] 100 [30] Maximum Number of Bends 10
NOTES:
AHRI Rated Conditions (Rated data is determined at a fixed compressor speed) 1Cooling (Indoor // Outdoor) °F 80 DB, 67 WB // 95 DB, 75 WB
*Outdoor Unit Operating Temperature Range (Cooling Air Temp (Maximum / Minimum)):
• Wind baffles required to operate below 23°F DB in cooling mode.
• Cooling-only system with advanced wind baffle: -40°F - 115°F.
• Refer to wind baffle documentation for further information.
**Outdoor Unit Operating Temperature Range (Cooling Thermal Lock-out / Re-start Temperatures; Heating Thermal Lock-out / Re-start Temperatures):
• System cuts out in heating mode to avoid thermistor error and automatically restarts at these temperatures.
SEACOAST PROTECTION (TRU*A0*******BA MODELS)
• External Outer Panel: Phosphate coating + Acrylic-Enamel coating
• Fan Motor Support: Epoxy resin coating (at edge face)
• Separator Assembly Valve Bed: Epoxy resin coating (at edge face)
• Blue Fin treatment is an anti-corrosion treatment that is applied to the condenser coil to protect it against airborne contaminants.
Specifications are subject to change without notice. © 2021 Mitsubishi Electric Trane HVAC US LLC. All rights reserved.
Specifications are subject to change without notice. © 2021 Mitsubishi Electric Trane HVAC US LLC. All rights reserved.
INDOOR UNIT ACCESSORIES: TPKA0A0241KA70A
Control Interface
3-Pin Connector PAC-715AD BACnet® and Modbus® Interface PAC-UKPRC001-CN-1 IT Extender PAC-WHS01IE-E kumo station® for kumo cloud® TAC-WHS01HC-E Lockdown bracket for remote controller RCMKP1CB Thermostat Interface PAC-US444CN-1 USNAP Adapter PAC-WHS01UP-E Wireless Interface for kumo cloud® PAC-USWHS002-WF-2
Remote Sensor
Flush Mount Temperature Sensor PAC-USSEN001-FM-1 Remote Temperature Sensor PAC-SE41TS-E Wireless temperature and humitity sensor for kumo cloud® PAC-USWHS003-TH-1
Wired Remote Controller
Deluxe Wired MA Remote Controller† TAR-40MAAU Simple MA Remote Controller† TAC-YT53CRAU-J Touch MA Controller† TAR-CT01MAU-SB
Wireless Remote Controller kumo touch™ RedLINK™ Wireless Controller MHK2 Wireless MA Controller PAR-SR32MA-E Wireless MA Remote Controller TAR-FL32MA-E
Condensate
Blue Diamond (Advanced) Mini Condensate Pump w/ Reservoir & Sensor (208/230V) [recommended] X87-721 Blue Diamond (MegaBlue Advanced) Condensate Pump w/ Reservoir & Sensor X87-835 Blue Diamond Sensor Extension Cable — 15 Ft. C13-103 Drain Pan Level Sensor/Control SS610E Sauermann Condensate Pump SI30-230
Disconnect Switch (30A/600V/UL) [fits 2” X 4” utility box] - Black TAZ-MS303 (30A/600V/UL) [fits 2” X 4” utility box] - White TAZ-MS303W
Lineset
10’ x 3/8” x 10’ x 5/8” Lineset (Twin-Tube Insulation)†† MPLS385812T-10 100’ x 3/8” x 100’ x 5/8” Lineset (Twin-Tube Insulation)†† MPLS385812T-100 15’ x 3/8” x 15’ x 5/8” Lineset (Twin-Tube Insulation)†† MPLS385812T-15 30’ x 3/8” x 30’ x 5/8” Lineset (Twin-Tube Insulation)†† MPLS385812T-30 50’ x 3/8” x 50’ x 5/8” Lineset (Twin-Tube Insulation)†† MPLS385812T-50 65’ x 3/8” x 65’ x 5/8” Lineset (Twin-Tube Insulation)†† MPLS385812T-65
Specifications are subject to change without notice. © 2021 Mitsubishi Electric Trane HVAC US LLC. All rights reserved.
OUTDOOR UNIT ACCESSORIES: TRUYA0241HA70(N/B)A
Air Outlet Guide Air Outlet Guide (1 Piece) PAC-ADG059AA-E
Centralized Drain Pan Centralized Drain Pan PAC-SG63DP-E Drain Pan PAC-SG64DP-E
Control/Service Tool
Control/Service Tool PAC-SK52ST M- & P-Series Maintenance Tool Cable Set M21EC0397 USB/UART Conversion Cable (Required for all laptop connection) M21EC1397
Distribution pipe Twinning Distribution Pipe (50:50)†† MSDD-50TR-E Drain Socket Drain Socket PAC-SG61DS-E Hail Guards Hail Guard HG-A6
M-NET Converter M-NET Converter PAC-SJ85MA-E M-NET Converter PAC-SJ95MA-E
Mini-Split Wire
14 Gauge, 4 wire MiniSplit Cable—250 ft. roll S144-250 14 Gauge, 4 wire MiniSplit Cable—50 ft. roll S144-50 16 Gauge, 4 wire MiniSplit Cable—250 ft. roll S164-250 16 Gauge, 4 wire MiniSplit Cable—50 ft. roll S164-50
Mounting Pad Condensing Unit Mounting Pad: 24” x 42” x 3” ULTRILITE2
Stand
18” Single Fan Stand QSMS1801M 24” Single Fan Stand QSMS2401M Condenser Wall Bracket QSWB2000M-1 Condenser Wall Bracket -Stainless Steel Finish QSWBSS Outdoor Unit Stand — 12” High QSMS1201M
Wind Baffle
Front Wind Baffle WB-PA5 Rear Wind Baffle WB-RE5 Side Advanced Wind Baffle WB-SD5
Specifications are subject to change without notice. © 2021 Mitsubishi Electric Trane HVAC US LLC. All rights reserved.
Front side
46-1/16(1170) 9-1/2(241)33-21/32(855)2-29/32(74)
-3
/8 (3
Emergency operation switch (cooling/heating)
Terminal block for Outdoor unit
Terminal block for MA-remote controller
Front side(Grille open)
Terminal block for power supply (option)
Filter hook
6-1/16(154) 4-27/32(123)
18-31/32(482)Liquid pipe
17-15/32(444)Gas pipeDrain hose
5-9/32(134)
M in
.9 /3
2( 7)
Center measurement hole [ 3/32([ 2.5)
Knockout hole for rear piping
75-[ 3/16([ 5.1) Tapping screw hole
Mount board
Wall hole for right rear piping
Indoor unit outline
4-[ 11/32([ 9) Bolt hole
1/ 8(
3)
R1-15/32(R37.5)
2- 1/
8(
5/8(15.5)
-9
/3 2(
9)
0 17 -9
/3 2(
9)
-1
/8 (3
/3
2(
-3
/8 (5
.4
-7
/8 (4
-3
/3 2(
8.
5)
-1 /8
(3
-1 1/
(3
-3
/8 (3
4-
/3 2(
0)
2- 3/
8(
/3 2(
-5
/1 6(
5.
5)
-7 /8
(4
-3
/3 2(
8.
5)
-1 /8
(3
.5
-1
1/
(3
-3
/8 (3
4-
/3 2(
0)
2- 3/
8(
1-1/4(32)
12-5/32(308.5)
31/32(25)
11-1/2(292) 11(279.5)
9-17/32(242) 7-9/16(192)
5-19/32(142) 4-29/32(125) 4-19/32(117) 3-15/16(100) 2-15/16(75) 1-31/32(50)
-1
/8 (3
)0
-3
/4 (3
.2
-1
5/
(4
.5
1/2(12.5)
11-1/2(292) 10-13/32(264) 9-1/32(229.5) 8-17/32(217) 6-9/16(167) 5-3/32(129.5) 4-1/8(104.5) 3-7/16(87.5) 2-15/32(62.5) 1-15/32(37.5) 1/2(12.5)
2-1/8(54)
31/32(25)
12-1/4(311)
8-
/3 2(
6.
5)
-1
1/
(3
-7
/8 (5
.5
7- 7/
(1
-1
1/
(3
-1
1/
(4
.2
-1
/3 2(
5)
-1
/3 2(
5)
A
5/
(7 .8
3-
1/
(7 7)
2- 5/
8(
2-9/16(65)
B
Knockout hole for piping
13/32(10.7)
2- 9/
(6
5)
3-1/32(77) 3-7/16(87)
C
5/
(7 .8
2-9/16(65)
3- 1/
(7
7) 2-
5/ 8(
Louver(manual)Vane(auto)
Knockout hole for lower piping
Under side
BB
Receiver DEFROST/STAND BY lamp
Operation lamp
2-19/32(66)
/3
2(
1-
1/ 4(
2- 3/
(5
3)
1-3/16(30) 1-3/8(35)
Mount board
C
Knockout hole for right piping
Right side
11-5/8(295) 3/16(5)
Left side
A
Knockout hole for left piping
Top side
2- 9/
(6
5.
2)
5-
/3 2(
0.
3)
7/
(1 1)
17(431.7)16-11/16(423.7)
Air outlet
Air inlet
M in
.1 -7
/8 (4
8)
M in.
9-
/3 2(
0)
Required space(Indoor unit)
Min.3-31/32(100.5)Min.8-21/32(220)
Min.2-1/16(52.3)
3 2
Refrigerant pipe: 3/8 O.D([ 9.52)
Refrigerant pipe: 5/8 O.D([ 15.88)
5/8([ 16) O.D3 Drain hose
Piping connection
1 Liquid pipe
2 Gas pipeThrough hole
[ 2-15/16 ([ 75)
[ 2-15/16~[ 3-5/32 ([ 75~[ 80)
Sleeve (purchased locally) Flared connection: 5/8F
Flared connection: 3/8F
Effective length: 23-1/32 (585)
Unit: inch (mm)
INDOOR UNIT DIMENSIONS: TPKA0A0241KA70A
FORM# TPKA0A0241KA70A &…
This is the start of the file's text. The full file is on GovTribe.